MidSouth Construction, LLC v. Daniel Burstiner

CourtCourt of Appeals of Tennessee
DecidedJune 12, 2025
DocketM2023-01396-COA-R3-CV
StatusPublished

This text of MidSouth Construction, LLC v. Daniel Burstiner (MidSouth Construction, LLC v. Daniel Burstiner) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MidSouth Construction, LLC v. Daniel Burstiner, (Tenn. Ct. App. 2025).

Opinion

06/12/2025 IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE Assigned on Briefs December 5, 2024

MIDSOUTH CONSTRUCTION, LLC V. DANIEL BURSTINER ET AL.

Appeal from the Chancery Court for Maury County No. 20-551 Christopher V. Sockwell, Judge

No. M2023-01396-COA-R3-CV

This appeal concerns a homeowner’s attempt to vacate an arbitration award entered after a dispute arose regarding the homeowner’s contract with a construction company to build a deck on the homeowner’s property. We have determined that the trial court properly confirmed the arbitration award and that the contractor waived any argument that the trial court erred by not awarding the company its attorney’s fees at the trial level. However, we remand the matter to the trial court for a determination of the contractor’s reasonable appellate attorney’s fees.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed and Remanded

ANDY D. BENNETT, J., delivered the opinion of the Court, in which CARMA DENNIS MCGEE and KRISTI M. DAVIS, JJ., joined.

Daniel Burstiner, Columbia, Tennessee, pro se.

Peter A. Angelov, Nashville, Tennessee, for the appellee, MidSouth Construction, LLC.

OPINION

FACTUAL AND PROCEDURAL HISTORY

This case involves a challenge to an arbitration award. In August 2020, Daniel Burstiner entered into a contract with MidSouth Construction, LLC (“MidSouth”) to remove an existing deck structure and build a new deck at Mr. Burstiner’s property in Maury County. The contract included the following language regarding disputes between the parties: Any controversy or claim arising out of or relating to the Agreement, or breach thereof, other than OWNER’S or MIDSOUTH’S default, shall be resolved by mutual agreement of the parties. Failing such agreement, disputes shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association (AAA) with one arbitrator. The locale of any arbitration hearing shall be Davidson County, Tennessee. Any judgment upon the award rendered by the Arbitrator shall be binding on both parties and may be entered in any court having jurisdiction thereof. The Arbitrator’s fees shall be shared equally by the OWNER and MIDSOUTH, and other service charges of the AAA shall be paid by the party incurring same according to the established AAA procedure. If it becomes necessary for either party to enforce provisions of this Agreement, the prevailing party shall be entitled to any reasonable attorneys’ fees, court costs, or other legal fees incurred herein.

Later that month, the parties signed an addendum to the contract, which increased the scope of work and correspondingly increased the price. This resulted in a contract price of $55,586.76. The parties later became involved in a dispute over the quality of the work, which resulted in the underlying action.

In November 2020, MidSouth’s attorney sent a demand letter to Mr. Burstiner stating that he continued to owe $29,561.32 and provided notice to Mr. Burstiner that MidSouth would be filing a contractor’s lien against the property. On November 19, 2020, MidSouth filed a verified complaint in the Chancery Court for Maury County against Mr. Burstiner, Aixia Burstiner, Harvey Burstiner, Judith Burstiner, and Quicken Loans, Inc. (collectively “the defendants”),1 asserting claims for breach of contract, unjust enrichment, and for a lien to be placed on the property. MidSouth contemporaneously filed a motion to stay the litigation and compel arbitration. On May 12, 2021, the trial court entered an agreed order staying the litigation and submitting the matter to arbitration.

In September 2022, the parties entered into an arbitration agreement, which included the following:

WHEREAS, Claimant and Respondent (collectively the “Parties”) entered into a contract with an effective date of August 10, 2020, and certain disputes and claims have arisen by and between the Parties in relation to their obligations under the contract. The Parties hereby agree to arbitrate such claims and disputes, and do hereby supplement and amend their agreement by and in this Agreed Submission to Arbitration.

1 Aixia Burstiner is Mr. Burstiner’s wife. Harvey and Judith Burstiner are Mr. Burstiner’s parents and are tenants with rights of survivorship in the property. Quicken Loans is a mortgagee with respect to the property. -2- THEREFORE, for valuable consideration, the Parties agree as follows:

1. Submission. Any and all disputes, claims and counterclaims of any kind by and between the Parties arising from their agreement shall be and hereby are submitted to binding Arbitration pursuant to and in accordance with T.C.A. 29-5-301, et. seq. In addition, the Parties agree that the rules or procedures set out more specifically in paragraph 6 shall govern this proceeding.

The parties engaged in arbitration on February 6 and 7, 2023. On February 28, 2023, the arbitrator issued an award, in which he made numerous findings regarding the poor quality of the deck, including that “there were multiple aesthetic problems with the work performed,” such as “unsightly and poor workmanship” and “omissions” that necessitated repair. The arbitrator found next that, after Mr. Burstiner raised issues with the quality of the work, workers from MidSouth had attempted to correct the defects on two separate occasions. Despite these attempts, the deficiencies remained, and Mr. Burstiner thereafter refused to allow MidSouth onto the property, even though between November 2020 and the fall of 2022, MidSouth repeatedly offered to return to the property. The arbitrator found that, “[a]lthough, clearly defective work existed and continues to exist on the premises, it is incumbent upon a party to a contract to allow reasonable notice of the defects alleged in the premises and provide a reasonable opportunity to effectuate a cure.” The arbitrator concluded that the defendants had breached their duty to provide MidSouth with a reasonable opportunity to correct defective work.

The arbitrator awarded MidSouth the remaining balance owed under the contract, $29,561.32. Due to the remaining problems with the deck, the arbitrator determined that the defendants were entitled to a set-off of $16,920.67. The arbitrator also awarded MidSouth $33,859 in attorney’s fees, $8,656.21 in arbitration costs, and the arbitrator’s fees of $4,381.11. The award to Midsouth, therefore, totaled $50,827.77.

On March 23, 2023, Mr. Burstiner, acting pro se,2 filed a “petition to vacate arbitration award,” asserting that MidSouth had breached the contract in various ways. As

2 Mr. Burstiner filed this petition without the knowledge of his counsel. On May 15, 2023, the trial court granted his counsel’s motion to withdraw, and Mr. Burstiner continued through the litigation pro se. Troublingly, Mr. Burstiner signed numerous filings in the trial court in which all of the Burstiners were listed as parties and in which it appears Mr. Burstiner is representing the other parties as well as himself. The “right of self-representation extends only to the individual’s right to conduct and manage his or her own case; a non-attorney may not conduct litigation on behalf of an entity or another individual, because doing so would constitute the unauthorized practice of law.” Beard v. Branson, 528 S.W.3d 487, 495 (Tenn. 2017). Mr. Burstiner is the only party to file a notice of appeal, and therefore, is only representing himself on appeal.

-3- relief, the petition sought the vacatur of the award, an award of fees and costs, and $45,000 as compensation for the cost of repairing the defective work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Options of Chicago, Inc. v. Kaplan
514 U.S. 938 (Supreme Court, 1995)
Dick Broadcasting Company, Inc. of Tennessee v. Oak Ridge FM, Inc.
395 S.W.3d 653 (Tennessee Supreme Court, 2013)
Chiozza v. Chiozza
315 S.W.3d 482 (Court of Appeals of Tennessee, 2009)
Pugh's Lawn Landscape Co. v. Jaycon Development Corp.
320 S.W.3d 252 (Tennessee Supreme Court, 2010)
Hessmer v. Hessmer
138 S.W.3d 901 (Court of Appeals of Tennessee, 2003)
International Talent Group, Inc. v. Copyright Management, Inc.
769 S.W.2d 217 (Court of Appeals of Tennessee, 1988)
Arnold v. Morgan Keegan & Co., Inc.
914 S.W.2d 445 (Tennessee Supreme Court, 1996)
D & E Construction Co. v. Robert J. Denley Co.
38 S.W.3d 513 (Tennessee Supreme Court, 2001)
Bobby Murray v. Dennis Miracle
457 S.W.3d 399 (Court of Appeals of Tennessee, 2014)
Joan Stephens v. Home Depot U.S.A., Inc.
529 S.W.3d 63 (Court of Appeals of Tennessee, 2016)
Elizabeth Eberbach v. Christopher Eberbach
535 S.W.3d 467 (Tennessee Supreme Court, 2017)
Linda Beard v. James William Branson
528 S.W.3d 487 (Tennessee Supreme Court, 2017)
Lacy v. Mitchell
541 S.W.3d 55 (Court of Appeals of Tennessee, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
MidSouth Construction, LLC v. Daniel Burstiner, Counsel Stack Legal Research, https://law.counselstack.com/opinion/midsouth-construction-llc-v-daniel-burstiner-tennctapp-2025.