International Talent Group, Inc. v. Copyright Management, Inc.

769 S.W.2d 217, 9 U.C.C. Rep. Serv. 2d (West) 951, 1988 Tenn. App. LEXIS 785
CourtCourt of Appeals of Tennessee
DecidedDecember 9, 1988
StatusPublished
Cited by22 cases

This text of 769 S.W.2d 217 (International Talent Group, Inc. v. Copyright Management, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Talent Group, Inc. v. Copyright Management, Inc., 769 S.W.2d 217, 9 U.C.C. Rep. Serv. 2d (West) 951, 1988 Tenn. App. LEXIS 785 (Tenn. Ct. App. 1988).

Opinion

OPINION

LEWIS, Judge.

This is an appeal by plaintiff, International Talent Group, Ltd. (ITG), from the Chancellor’s vacating an arbitration award to it in the amount of $76,400 by the extent it exceeded “the amount of license fees paid to [defendant], Copyright Management, Inc. (CMI).”

The pertinent facts are as follows:

ITG is a booking agency which books concert tours for performing artists, mainly rock musicians.

CMI administers music publishing copyrights and collects publishing and mechanical royalties. CM Systems, a division of CMI, markets CMI services as a consultant on computer systems and designs computer software programs.

ITG and CMI entered into an agreement for CMI to design a software package for ITG. The agreement also set forth the type of computer that would be used. CMI recommended a computer, but ITG contracted directly with Datapoint for its purchase.

The computer did not arrive when promised by Datapoint. After a lengthy delay, CMI recommended a different computer, also made by Datapoint, which was delivered. CMI received a commission for the sale from Datapoint.

There were long delays in delivery of the software and, even when delivered, the software was unusable. CMI proposed several “fixes” and “every fix” deranged another aspect of the system. During this time ITG’s business was disrupted and employees’ time was needlessly taken up.

CMI had promised a delivery date of 1 May 1984 for a fully operational software package. However, a full year after the new computer was installed, the promised software had not been delivered. As a result of failure of delivery of the software package, a dispute arose between the parties.

Pursuant to paragraph 14 of the “Software License Agreement” (the Agreement), the dispute between the parties was submitted to arbitration. Proceedings were held before the American Arbitration Association in Nashville, Tennessee. Following a lengthy hearing, the arbitrators rendered an award in favor of ITG in the amount of $76,400 “for failure to deliver a workable system.” ITG then filed its petition in the Chancery Court for Davidson County, Tennessee, to confirm the award. CMI answered, denying that ITG was entitled to have the award confirmed, and filed a counterclaim in which it sought to have the award vacated on the ground that the Arbitrators had exceeded their powers.

The Chancellor, following his consideration of (1) the Software License Agreement, (2) the award of the arbitrators, (3) the modified award of the arbitrators, (4) the rules of the American Arbitration Association, and (5) the $7,500 license fee paid by ITG to CMI, found that the award should be vacated on the ground that the arbitrators had exceeded their authority in making an award in excess of the license fee paid by ITG to CMI.

ITG has presented two issues. The first is: “The trial court erred in reducing the lump-sum arbitration award in favor of ITG against CMI for failure to deliver a workable software-hardware computer system.”

The Uniform Arbitration Act, Tenn.Code Ann. § 29-5-301 et seq., governs the scope of judicial review of arbitration awards. Tenn.Code Ann. § 29-5-320 provides that the Uniform Arbitration Act is to be interpreted in a consistent manner with other jurisdictions. It has been held that the scope of authority of the arbitrators is determined by the terms of the agreement between the parties which includes the agreement of the parties to arbitrate the dispute. Swift Industries, Inc. v. Botany Industries, Inc., 466 F.2d 1125, 1131 (3rd Cir.1972); Malecki v. Burnham, 181 Conn. 211, 435 A.2d 13, 14 (1980).

*219 Rule 43 of the Rules of the American Arbitration Association provides in pertinent part:

43. SCOPE OF AWARD
The Arbitrator may grant any remedy or relief which the Arbitrator deems just and equitable and within the scope of the agreement of the parties, including, but not limited to, specific performance of a contract.

The arbitrators may not award relief in excess of the limit of,that relief agreed upon by the parties in the agreement entered into between the parties.

Paragraph 14 of the Agreement provides:

GOVERNING LAW: This agreement and performance hereunder shall be governed and construed in accordance with the laws of the State of Tennessee. Any and all proceedings relation [sic] to the subject matter hereof other than equitable remedies shall be settled by arbitration in the State of Tennessee in accordance with the Rules of the [sic] obtaining of the American Arbitration Association and judgement [sic] upon the award rendered may be entered in any Court having jurisdiction thereof.

ITG contends that the limited repair remedy set forth in paragraph 8 of the Agreement has failed its essential purposes, that “the issues subject to arbitration are unlimited and the remedies available to the arbitrators are unrestricted except for equitable remedies” and that, since the arbitrators are governed by Tennessee Law, the full range of remedies under the Tennessee Uniform Commercial Code are available when a limited repair remedy fails of its essential purpose.

Paragraph 8 of the agreement provides in pertinent part:

User [ITG] agrees that its sole remedy and Licensor’s [CMI’s] sole obligation if a warranted licensed program product does not substantially conform to Li-censor’s corresponding specification is for Licensor to provide programming support of services to correct the defect at licensor’s [CMI’s] sole cost and expense.

Paragraph 9 of the agreement provides in pertinent part:

LIMITATION OF LIABILITY: IN NO EVENT SHALL LICENSOR [CMI] BE LIABLE FOR ANY LOST PROFITS, INCIDENTAL, SPECIAL OR CONSEQUENTIAL OR OTHER DAMAGES SIMILARLY ARISING OUT OF ANY BREACH OF THIS LICENSE OR OBLIGATIONS UNDER THIS LICENSE. LICENSEE [ITG] AGREES THAT IN NO EVENT SHALL LICENSOR’S [CMI’s] LIABILITY EXCEED THE TOTAL LICENSE FEE PAID HEREUNDER.

The total license fee paid by ITG to CMI was $7,500.

Tennessee Code Ann. § 47-2-719(2) provides: “Where circumstances cause an exclusive or limited remedy to fail of its essential purpose, remedy may be had as provided in chapters 1 through 9 of this title.”

In support of its argument that the full range of remedies under the Uniform Commercial Code as adopted by Tennessee is available to the arbitrators where the limited repair remedy fails of its essential purpose, ITG cites Chatlos Systems, Inc. v. National Cash Register Corp., 635 F.2d 1081, 1084 (3rd Cir.1980), cert. dismissed, 457 U.S. 1112, 102 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CARBON FIBER RECYCLING, LLC v. TIMOTHY SPAHN
Court of Appeals of Tennessee, 2025
MidSouth Construction, LLC v. Daniel Burstiner
Court of Appeals of Tennessee, 2025
Lasco Inc. v. Inman Construction Corp.
467 S.W.3d 467 (Court of Appeals of Tennessee, 2015)
Timegate Studios, Inc. v. Southpeak Interactive, LLC
860 F. Supp. 2d 350 (S.D. Texas, 2012)
Baptist Memorial Hospital v. Argo Construction Corp.
308 S.W.3d 337 (Court of Appeals of Tennessee, 2009)
Lawrence County Education Ass'n v. Lawrence County Board of Education
244 S.W.3d 302 (Tennessee Supreme Court, 2007)
Williams Holding Co. v. Willis
166 S.W.3d 707 (Tennessee Supreme Court, 2005)
Marcia McAlexander v. Albert McAlexander
Court of Appeals of Tennessee, 2003
D & E Construction Co. v. Robert J. Denley Co.
38 S.W.3d 513 (Tennessee Supreme Court, 2001)
Parr v. Tower Management
Court of Appeals of Tennessee, 1999
Millsaps v. Robertson-Vaughn Construction Co.
970 S.W.2d 477 (Court of Appeals of Tennessee, 1997)
William Boyle v. Virginia Thomas
Court of Appeals of Tennessee, 1997
Arnold v. Morgan Keegan & Co., Inc.
914 S.W.2d 445 (Tennessee Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
769 S.W.2d 217, 9 U.C.C. Rep. Serv. 2d (West) 951, 1988 Tenn. App. LEXIS 785, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-talent-group-inc-v-copyright-management-inc-tennctapp-1988.