Cyclone Roofing Co. v. David M. LaFave Co.

321 S.E.2d 872, 312 N.C. 224, 1984 N.C. LEXIS 1791
CourtSupreme Court of North Carolina
DecidedNovember 6, 1984
Docket181A84
StatusPublished
Cited by99 cases

This text of 321 S.E.2d 872 (Cyclone Roofing Co. v. David M. LaFave Co.) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cyclone Roofing Co. v. David M. LaFave Co., 321 S.E.2d 872, 312 N.C. 224, 1984 N.C. LEXIS 1791 (N.C. 1984).

Opinion

MARTIN, Justice.

By contract dated 2 May 1978 Joseph C. Frye, Jr. and Emma Gray Frye (Fryes) engaged the services of David M. LaFave Company (LaFave Company) to build a house. David M. LaFave (La-Fave) is president of LaFave Company. The contract price of $191,000 included a contractor’s fee of $20,000, and the contract specified that construction of the house was to be completed by 15 May 1979.

During construction of the house disagreements arose among the parties concerning progress of the work, quality of worksite supervision, installation of fixtures and flooring, and other aspects of construction. Negotiations between counsel for each of the parties failed to resolve the dispute satisfactorily, and on 24 September 1979 LaFave Company notified the Fryes that it was ceasing work under the contract. On 18 October 1979 LaFave Company filed a claim of lien against the property. Thereafter the Fryes spent more than $60,000 to complete the house and correct defective work. While this further construction was being carried out, counsel for the Fryes and LaFave Company continued to correspond, trying to resolve outstanding differences in the parties’ contentions. Although the contract between the Fryes and La-Fave Company provided for arbitration of problems arising out of the contract, neither side demanded arbitration while these negotiations were going on.

On 5 March 1980 Cyclone Roofing Company, Inc. (Cyclone), a subcontractor of LaFave Company, filed this action against *226 LaFave Company and the Fryes in Mecklenburg County District Court. On 7 July 1980 LaFave Company answered the complaint and crossclaimed against the Fryes for breach of the construction contract. The crossclaim alleged that LaFave Company had performed its duties under the contract and that the Fryes owed the company a balance of $47,449.27. The crossclaim included a demand for jury trial. On 9 July 1980 the Fryes filed an answer to the Cyclone complaint and a crossclaim against LaFave Company. The Fryes’ crossclaim alleged that LaFave Company breached the contract, causing damages of $50,000. The Fryes’ answer also included a third-party claim against LaFave individually, alleging negligence resulting in damages of $50,000. The Fryes demanded a jury trial. On 14 July 1980 the Fryes answered the LaFave Company crossclaim, denying that the company had performed under the contract and denying that any balance was due. On 11 August 1980 LaFave Company and LaFave filed an answer to the Fryes’ crossclaim and third-party complaint, alleging for the first time that the dispute between the parties was subject to mandatory arbitration pursuant to the contract. On the same date LaFave Company and LaFave individually also filed a motion to stay litigation pending arbitration. The Fryes filed affidavits and a memorandum in opposition to this motion, denying that arbitration was mandatory and that it was the exclusive remedy for resolving disputes under the contract. The Fryes also contended that LaFave Company had waived any right to demand arbitration.

On 18 November 1980 District Court Judge L. Stanley Brown entered an order staying litigation between LaFave Company and the Fryes while they arbitrated their differences in accordance with the terms of the contract. In its discretion the court also stayed litigation between the Fryes and LaFave individually pending the outcome of arbitration between the Fryes and LaFave Company. The Fryes appealed the district court’s order that they proceed to arbitration; this appeal was dismissed by the Court of Appeals. On 24 November 1980 the case was properly transferred to the Mecklenburg County Superior Court. 1

*227 In accordance with the contract, LaFave Company and the Fryes first submitted their dispute to the architect of the project. The architect determined that the Fryes had not breached the construction contract and ordered that because of LaFave Company’s breach, LaFave Company was to pay the Fryes $32,500.01. 2 Pursuant to the contract, LaFave Company appealed this award to an arbitrator, and arbitration was conducted under the Construction Industry Arbitration Rules of the American Arbitration Association. The arbitrator ordered the Fryes to pay LaFave Company $37,094.27, without any offset for the amount awarded to the Fryes by the architect.

Pursuant to N.C.G.S. 1-567.12, LaFave Company properly applied for confirmation of this award by the superior court. Upon motion of the Fryes the superior court ordered the arbitrator to clarify his award. After reviewing the arbitrator’s clarification of his findings, calculations, and conclusions, the superior court confirmed the award. From this order and judgment the Fryes appealed to the Court of Appeals. N.C. Gen. Stat. § l-567.18(a)(3) (1983). They also renewed their appeal from the order of the district court directing the parties to pursue arbitration under the contract. A divided panel of the Court of Appeals vacated the award of the arbitrator, holding that the district court erred in ordering arbitration. LaFave Company appealed the decision of the Court of Appeals to this Court pursuant to N.C.G.S. 7A-30(2). LaFave Company’s petition for discretionary review of the question whether the superior court erred by confirming the arbitration award was allowed 6 July 1984.

We now turn to an analysis of the questions arising upon the foregoing facts. The first issue for consideration is whether the Court of Appeals erred in holding that as a matter of law both parties waived the arbitration agreement contained in the construction contract. We hold that the court did so err, and we reverse.

N.C.G.S. l-567.2(a) provides:

*228 Two or more parties may agree in writing to submit to arbitration any controversy existing between them at the time of the agreement, or they may include in a written contract a provision for the settlement by arbitration of any controversy thereafter arising between them relating to such contract or the failure or refusal to perform the whole or any part thereof. Such agreement or provision shall be valid, enforceable, and irrevocable except with the consent of all the parties, without regard to the justiciable character of the controversy.

The contract between the Fryes and LaFave Company contained a provision stating that if any dispute arose between the parties it would first be submitted for decision to the architect for the project. After the architect rendered a decision, the claim or dispute involved “shall be subject to arbitration upon the written demand of either party.” Under N.C.G.S. l-567.2(a) this provision was enforceable and irrevocable except with the consent of both the Fryes and LaFave Company.

N.C.G.S. l-567.3(a) provides in pertinent part that “[o]n application of a party showing an agreement described in G.S. 1-567.2; and the opposing party’s refusal to arbitrate, the court shall order the parties to proceed with arbitration. . . .” N.C.G.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gallagher-Masonis v. Masonis
Court of Appeals of North Carolina, 2024
Canteen v. Charlotte Metro Credit Union
Supreme Court of North Carolina, 2024
Canteen v. Charlotte Metro Credit Union
Court of Appeals of North Carolina, 2022
R.E.M. Constr., Inc. v. Cleveland Constr.
Court of Appeals of North Carolina, 2022
Hyosung USA, Inc. v. Travelers Prop. Cas. Co. of Am.
2021 NCBC 16 (North Carolina Business Court, 2021)
Register v. Wrightsville Health Holdings
Court of Appeals of North Carolina, 2020
Gzo, LLC v. Lkn, Inc.
2020 NCBC 10 (North Carolina Business Court, 2020)
Wygand v. Deutsche Bank Tr. Co. Ams.
829 S.E.2d 681 (Court of Appeals of North Carolina, 2019)
iPayment
Court of Appeals of North Carolina, 2018
iPayment, Inc. v. Grainger
808 S.E.2d 796 (Court of Appeals of North Carolina, 2018)
Thompson v. Speller
808 S.E.2d 608 (Court of Appeals of North Carolina, 2017)
Town of Belville v. Urban Smart Growth, LLC
796 S.E.2d 817 (Court of Appeals of North Carolina, 2017)
Epic Games, Inc. v. Murphy-Johnson
785 S.E.2d 137 (Court of Appeals of North Carolina, 2016)
T.M.C.S., Inc. v. Marco Contr'rs
Court of Appeals of North Carolina, 2015
T.M.C.S., Inc. v. Marco Contractors, Inc.
780 S.E.2d 588 (Court of Appeals of North Carolina, 2015)
Cold Springs Ventures, LLC v. Gilead Scis., Inc.
2014 NCBC 10 (North Carolina Business Court, 2014)
Elliott v. KB Home North Carolina, Inc.
752 S.E.2d 694 (Court of Appeals of North Carolina, 2013)
HCW Retirement & Financial Services, LLC v. HCW Employee Benefit Services, LLC
747 S.E.2d 236 (Supreme Court of North Carolina, 2013)
Elliott v. Kb Home North Carolina, Inc.
2012 NCBC 55 (North Carolina Business Court, 2012)
HCW Retirement & Financial Services, LLC v. HCW Employee Benefit Services, LLC
731 S.E.2d 181 (Court of Appeals of North Carolina, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
321 S.E.2d 872, 312 N.C. 224, 1984 N.C. LEXIS 1791, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cyclone-roofing-co-v-david-m-lafave-co-nc-1984.