R.E.M. Constr., Inc. v. Cleveland Constr.

CourtCourt of Appeals of North Carolina
DecidedAugust 16, 2022
Docket21-781
StatusPublished

This text of R.E.M. Constr., Inc. v. Cleveland Constr. (R.E.M. Constr., Inc. v. Cleveland Constr.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.E.M. Constr., Inc. v. Cleveland Constr., (N.C. Ct. App. 2022).

Opinion

IN THE COURT OF APPEALS OF NORTH CAROLINA

2022-NCCOA-557

No. COA21-781

Filed 16 August 2022

Buncombe County, No. 19 CVS 1433

R.E.M. CONSTRUCTION, INC., Plaintiff,

v.

CLEVELAND CONSTRUCTION, INC.; MHG ASHEVILLE TR, LLC; ASHEVILLE ARRAS RESIDENCES, LLC; AND FEDERAL INSURANCE COMPANY; Defendants,

and

UNITED STATES SURETY COMPANY, Intervenor.

Appeal by defendant Cleveland Construction, Inc., from judgment and order

entered 10 September 2021 by Judge Alan Z. Thornburg in Buncombe County

Superior Court. Heard in the Court of Appeals 24 May 2022.

Erwin, Capitano & Moss, P.A., by Fenton T. Erwin, Jr., and Erin C. Huegel, for plaintiff-appellee R.E.M. Construction, Inc.

Chamberlain Hrdlicka White Williams & Aughtry, by Seth R. Price, pro hac vice, and Hamilton Stephens Steele + Martin, PLLC, by Tracy T. James and Carmela E. Mastrianni, for defendant-appellant Cleveland Construction, Inc.

Everett Gaskins Hancock LLP, by James M. Hash, and Thompson Law Group, LLC, by Kelley Herrin, pro hac vice, for intervenor-appellee.

ZACHARY, Judge. R.E.M. CONSTR., INC. V. CLEVELAND CONSTR., INC.

Opinion of the Court

¶1 Defendant Cleveland Construction, Inc., (“CCI”) appeals from the trial court’s

judgment and order (1) granting the motion of Plaintiff R.E.M. Construction, Inc.,

(“REM”) to confirm the arbitration panel’s award, and (2) denying CCI’s motion to

modify or, in the alternative, to partially vacate the panel’s award. After careful

consideration, we affirm.

Background

¶2 This appeal arises out of an arbitration proceeding following CCI’s termination

of REM from a construction project in Asheville. CCI’s appeal presents a narrow

question of law concerning the arbitration panel’s award of damages to REM. On

appeal, CCI does not challenge the panel’s conclusions that (1) CCI did not properly

terminate REM for default under the terms of the parties’ subcontracts, and (2) REM

was “entitled to monetary compensation from CCI[.]” Instead, CCI argues that the

panel exceeded its authority by awarding damages that were not permissible under

the express terms of the parties’ subcontracts, and that the trial court thus erred by

confirming the panel’s award. As CCI does not contest the panel’s conclusions

regarding the merits of REM’s claims, we recite only those facts pertinent to the

present dispute concerning the award of damages.

¶3 On 29 August 2017, CCI entered into a pair of substantially identical

subcontracts (“the Subcontracts”) with REM for work on the “exterior envelope” of a

nineteen-story building in Asheville. Intervenor United States Surety Company R.E.M. CONSTR., INC. V. CLEVELAND CONSTR., INC.

(“USSC”) issued performance bonds dated 25 January 2018 for both of the

Subcontracts. REM began work in November 2017, but between May and September

2018 the project suffered several problems and resultant delays. On 5 October 2018,

CCI terminated REM for default and notified USSC of the termination.

¶4 On 3 April 2019, REM filed suit against Defendants CCI, MHG Asheville TR,

LLC, and Asheville Arras Residences, LLC in Buncombe County Superior Court.1

CCI elected to arbitrate REM’s claims pursuant to the terms of the Subcontracts,

each of which provides in pertinent part that “[a]ny controversy or claim of . . . [REM]

against [CCI] shall, at the option of [CCI], be resolved by arbitration pursuant to the

Construction Industry Arbitration Rules of the American Arbitration Association in

effect on the date on which the demand for arbitration is made.” Accordingly, on 3

May 2019, CCI filed a motion to stay pending arbitration alongside its motion to

dismiss. On 26 June 2019, the trial court entered an order staying proceedings

pending the arbitration.

¶5 A panel of arbitrators confirmed by the American Arbitration Association

(“AAA”) and approved by the parties heard this matter. On 15 March 2021, the panel

issued its award, determining in pertinent part “that CCI did not properly terminate

1 On 26 June 2019, the trial court entered an order allowing Plaintiff to amend its complaint to bring claims against additional Defendant Federal Insurance Company. Defendants MHG Asheville TR, LLC, Asheville Arras Residences, LLC, and Federal Insurance Company are not involved in the present appeal. R.E.M. CONSTR., INC. V. CLEVELAND CONSTR., INC.

REM for default; . . . and REM shall be entitled to monetary compensation from CCI

in accordance with the terms of” the Subcontracts. To calculate the amount of the

damage award, the panel first looked to the terms of the Subcontracts:

73. As stated above, the termination for default by [CCI] against REM was improper. In a case of an improper termination, the contract provides in Article 31.8 as follows:

“If after termination it is determined that, for any reason, [REM] was not in default or that [REM] is not properly terminated for default, then such termination shall have been deemed to be for the convenience of [CCI] and [REM] shall be entitled to the actual direct cost of all Subcontract Work satisfactorily performed and materials furnished prior to notification of termination. [REM] shall not be entitled to compensation for profit and overhead. [REM] shall not be entitled to compensation for work not performed or materials not furnished. [REM] shall not be entitled to recover exemplary, special or consequential damages, or anticipated profit on account of such termination or on account of [CCI’s] breach of the subcontract agreement.”

(Emphases added.)

¶6 The panel then reviewed the record, but found insufficient evidence on which

to base a calculation of the “actual direct cost” to which REM was entitled under the

Subcontracts. As such, the panel determined that it would fashion an equitable

remedy pursuant to the AAA rules: R.E.M. CONSTR., INC. V. CLEVELAND CONSTR., INC.

74. The contractual starting point for determining the damages or compensation for REM is the actual direct cost of all Subcontract Work prior to October 5, 2018. The problem is that there is no evidence of “actual direct cost” of all work. There was little evidence of the job costs of REM presented to the Panel.

75. It is unfair to deny any compensation to REM as a result of the improper termination of its subcontracts with [CCI]. Therefore, the Panel develops an equitable remedy pursuant to the AAA Rules. Specifically, Rule R-48 (a) of the Construction Industry Rules of the AAA states, “The arbitrator may grant any remedy or relief that the arbitrator deems just and equitable and within the scope of the agreement of the parties, including, but not limited to, equitable relief and specific performance of a contract.”

¶7 Therefore, the panel set out to estimate REM’s “actual direct cost” under

Article 31.8 of the Subcontracts. The panel examined the evidence in the record to

determine “the amount of the contract funds earned by REM at the time of

termination.” The panel identified a document provided by CCI as “the best source

for contract funds earned by REM through September 30, 2018” and calculated a total

of $211,151.00 in earnings for that period. Then, recognizing that this amount “d[id]

not include the work of REM performed from October 1-5, 2018[,]” the panel

determined that “the labor and equipment, including demobilization for October 1-5,

2018, is $25,000.00.” Ultimately, the panel concluded that “REM is entitled to a total

of $236,151.00 for contract work performed on this project.” The panel added $926.00

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cyclone Roofing Co. v. David M. LaFave Co.
321 S.E.2d 872 (Supreme Court of North Carolina, 1984)
Faison & Gillespie v. Lorant
654 S.E.2d 47 (Court of Appeals of North Carolina, 2007)
Dalenko v. Peden General Contractors, Inc.
676 S.E.2d 625 (Court of Appeals of North Carolina, 2009)
WMC, INC. v. Weaver
602 S.E.2d 706 (Court of Appeals of North Carolina, 2004)
Carteret County v. United Contractors of Kinston, Inc.
462 S.E.2d 816 (Court of Appeals of North Carolina, 1995)
In Re Fifth Third Bank, Nat. Ass'n
716 S.E.2d 850 (Court of Appeals of North Carolina, 2011)
James Warfield v. ICON Advisers, Inc
26 F.4th 666 (Fourth Circuit, 2022)
Williams v. State
608 S.E.2d 330 (Supreme Court of North Carolina, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
R.E.M. Constr., Inc. v. Cleveland Constr., Counsel Stack Legal Research, https://law.counselstack.com/opinion/rem-constr-inc-v-cleveland-constr-ncctapp-2022.