C.W. Over & Sons, Inc. v. United States

54 Fed. Cl. 514, 2002 U.S. Claims LEXIS 324, 2002 WL 31686136
CourtUnited States Court of Federal Claims
DecidedNovember 26, 2002
DocketNo. 98-741C
StatusPublished
Cited by21 cases

This text of 54 Fed. Cl. 514 (C.W. Over & Sons, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C.W. Over & Sons, Inc. v. United States, 54 Fed. Cl. 514, 2002 U.S. Claims LEXIS 324, 2002 WL 31686136 (uscfc 2002).

Opinion

OPINION

MILLER, Judge.

This contract case is before the court after argument on cross-motions for summary judgment. After defendant obtained summary judgment on this claim, plaintiff succeeded in reopening proceedings, and the pending dispositive motions followed. Prompted by the Government’s admission that the subject state tax for which the contractor seeks refund was not included in the Government-supplied price that the contractor utilized in its proposal, plaintiff seeks judgment in its favor. Defendant contends that the law affords no relief for the contractor’s mistaken interpretation of the subject contract as exempt from state sales tax, so that the Government’s admission does not afford plaintiff grounds for relief.

FACTS

1. Background

The facts germane to this matter are recited in the court’s previous opinions. See C.W. Over & Sons, Inc. v. United States, 44 Fed. Cl. 18 (1999) (Over I”) (granting defendant’s motion for summary judgment only on Count I that claimed reimbursement for sales tax costs); C.W. Over & Sons, Inc. v. United States, 45 Fed.Cl. 502 (1999) (“Over II”) (granting defendant’s motion for summary judgment on Count III alleging that Government applied expired coefficients to certain delivery orders); C.W. Over & Sons, Inc. v. United States, 48 Fed.Cl. 342 (2000) (“Over III ”) (denying defendant’s motion for summary judgment on Count II concerning Government’s alleged obligation to aggregate small work projects into one delivery order). Therefore, only the material facts involved in resolving the pending motions are discussed. The facts are drawn from the court’s previous opinions and from the parties’ proposed statements of fact, responses, and materials appended to the parties’ motions. All facts are undisputed unless otherwise noted.

On May 20, 1993, the Maryland Procurement Office of the National Security Agency (the “NSA”) issued a Request for Proposal (the “solicitation”) for construction and repair work to be performed at Fort George G. Meade, Maryland. The solicitation indicated that the resultant contract would contain one base year and four one-year options. On January 14,1994, the NSA awarded Contract No. MDA904-94-D-2502 to C.W. Over & Sons, Inc. (“plaintiff’). The contract was an indefinite delivery, indefinite quantity job order contract. The contracting officers were Robert M. DuCharme and Mark C. Doling. Mr. Doling drafted both the solicitation and the contract, with Mr. DuCharme reviewing and approving Mr. Doring’s efforts.

Certain provisions of the contract directly impact the motions for summary judgment. First, section G.3 of the contract stated:

Certain transactions which occur pursuant to this contract, for example, the purchase of materials or supplies, may be exempt from the imposition of state or local taxes. It is the contractor’s responsi[516]*516bility to determine whether any transactions under the contract are exempt under the particular tax statute and to take advantage of any applicable exemptions. In addition, it may be useful for the contractor to inform the taxing authorities that the Maryland Procurement Office (MPO) is a federal government agency. In Maryland, it may be useful to inform Maryland taxing authorities that the MPO has been assigned Maryland State Tax Exemption Certificate Number 3000500 4.

Second, the contract incorporated by reference Federal Acquisition Regulation (FAR), 48 C.F.R. § 52.229-3 (2001), entitled “Federal, State, and Local Taxes.” FAR § 52.229-3(b) provides: “The contract price includes all applicable Federal, State, and local taxes and duties.” Third, the contract also incorporated by reference the Job Order Contract Unit Price Book, Vol. II (Aug. 19, 1991) (the “UPB”), “which is a project-segment based compilation of pre-priced work items and provides the costs for individual construction tasks.” Over I at 20. Fourth, section B.2 of the contract clarified that the “unit prices [in the UPB] include all labor, material and equipment necessary to install one unit of a particular line item.” The same section specifies that the contractor must formulate three fixed coefficients for the base year and for each of the four option periods. The three coefficients cover: 1)-normal working hours, 2) other than normal working hours (overtime), and 3) flyaway services.1 These coefficients “will be used to price the cost of each Delivery Order by multiplying the applicable coefficient by the unit prices and quantities. The coefficients must include all associated costs that are not included in the [UPB].” Id.

Before awarding the contract to plaintiff, the NSA gave potential offerors2 a copy of a document entitled “Job Order Contract (JOC) Proposal Preparation Requirements,” vol. II (Feb. 5, 1993) (the “PPR”). Although not incorporated into the contract, the document was provided in order to facilitate the award process. Page 7 of the PPR indicates that the “Government requires the contractor to provide a breakdown and explanation of all elements used to derive the contractor’s coefficients.” Among the “elements” to be included in the coefficients were “[t]ax laws (local, Federal, State, etc.).” Id. The PPR also noted that “[t]he Government will analyze this information [used to formulate the coefficients] to determine if the contractor has a sufficient understanding of the requirement.” Id.

In its proposal to the NSA, plaintiff explained how it derived its coefficients. Plaintiff noted that the solicitation “indicates the use of Maryland State Tax Exemption Certificate number 3000500[sic] and therefore the coefficient does not contain any allowance for sales tax. Corporate taxes are estimated at 2.561%.” The NSA issued several clarification questions in response to plaintiffs proposal, none of which questioned plaintiffs invocation of the exemption certificate or the exclusion of sales tax from its coefficients.

After the NSA awarded plaintiff the contract, plaintiff requested a tax exemption letter to provide to its material suppliers. On February 14, 1994, Mr. DuCharme denied the request “because the Tax Exemption clause is not applicable to the pre[-]priced line items. Any sales tax on materials is already included in the prices in the [UPB].”3 Despite this denial, plaintiff continued to perform the contract, and the NSA ultimately exercised three of the four option years.

On February 20, 1998, plaintiff submitted a certified claim to Contracting Officer DuC[517]*517harme, seeking, inter alia,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Govwave, LLC v. United States
Federal Claims, 2025
CKY, Inc.
Armed Services Board of Contract Appeals, 2020
Dell Federal Systems, L.P. v. United States
133 Fed. Cl. 92 (Federal Claims, 2017)
Idaho Stage LLC v. United States
131 Fed. Cl. 727 (Federal Claims, 2017)
Stathis v. United States
120 Fed. Cl. 552 (Federal Claims, 2015)
Allen v. United States
119 Fed. Cl. 461 (Federal Claims, 2015)
Business Integra, Inc. v. United States
116 Fed. Cl. 328 (Federal Claims, 2014)
Bcpeabody Construction Services, Inc. v. United States
112 Fed. Cl. 502 (Federal Claims, 2013)
Seven Resorts, Inc. v. United States
112 Fed. Cl. 745 (Federal Claims, 2013)
St Net, Inc. v. United States
112 Fed. Cl. 99 (Federal Claims, 2013)
Armour of America v. United States
96 Fed. Cl. 726 (Federal Claims, 2011)
Valley Realty Co. v. United States
96 Fed. Cl. 16 (Federal Claims, 2010)
Camden Shipping Corp. v. United States
89 Fed. Cl. 433 (Federal Claims, 2009)
Imprimis Investors LLC v. United States
83 Fed. Cl. 46 (Federal Claims, 2008)
Burchick Construction Co. v. United States
83 Fed. Cl. 12 (Federal Claims, 2008)
PHT Supply Corp. v. United States
71 Fed. Cl. 1 (Federal Claims, 2006)
M.G. Construction, Inc. v. United States
67 Fed. Cl. 176 (Federal Claims, 2005)
Mid-States General & Mechanical Contracting Corp. v. Town of Goodland
811 N.E.2d 425 (Indiana Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
54 Fed. Cl. 514, 2002 U.S. Claims LEXIS 324, 2002 WL 31686136, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cw-over-sons-inc-v-united-states-uscfc-2002.