Crock Construction Co. v. Stanley Miller Construction Co.

66 Ohio St. 3d 588
CourtOhio Supreme Court
DecidedJune 30, 1993
DocketNos. 92-1018 and 92-1389
StatusPublished
Cited by14 cases

This text of 66 Ohio St. 3d 588 (Crock Construction Co. v. Stanley Miller Construction Co.) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crock Construction Co. v. Stanley Miller Construction Co., 66 Ohio St. 3d 588 (Ohio 1993).

Opinions

Alice Robie Resnick, J.

This case requires us to construe the provision of former R.C. 1311.26 which specified that a “sworn and itemized statement of the amount and value” of labor performed and material or machinery furnished be filed when seeking a mechanic’s lien in connection with a public works project.1 (Emphasis added.)

[591]*591The principal issue to be addressed is whether the sworn statement filed by appellees was insufficient, as a matter of law, to establish a mechanic’s lien. The trial court found the statement to be insufficient, due to the failure to itemize, and granted appellant’s Civ.R. 56(C) motion for summary judgment, determining that no genuine issue of material fact existed and appellant was entitled to judgment as a matter of law. The court of appeals, in reversing the trial court, found that the lack of itemization was not fatal to the assertion of a mechanic’s lien, concluding that appellant was not entitled to judgment as a matter of law. We thus begin our consideration by examining what “itemized” means in this context.

Black’s Law Dictionary (6 Ed.1990) 833, defines “itemize” as “[t]o set down by items. To state each item or article separately.” Applying this definition, in order for a statement of the amount and value of labor performed and material or machinery furnished to be itemized, the statement should set forth in some detail the separate instances in which labor was performed, and should also set forth in some detail a list of the material or machinery furnished. The portion of the sworn statement filed by appellees which is relevant to our inquiry contained the following information:

“Material charges from 5/8 to 11/14 $ 86,513.94

“Equipment charges from 4/1 to 11/14 120,853.10

“Rec’d payment (5/30/86) 11,500.00-

“Rec’d payment (8/4/86) 50.000. 00 -

“Rec’d payment (8/28/86) 35,803.10-

“Rec’d payment (10/23/86) 59.000. 00 -

“Total amount due from Brock Const. 51,063.94

“Amount due from Plumbsng [sic] Contractors 16,515.00-

“Amount due from Miller for Brock 34,548.94 ”

It is apparent that the charges listed for material and equipment are not itemized. No attempt has been made to set forth separately each item involved pertaining to material and equipment furnished. Material charges [592]*592are lumped together, with no elaboration, and set forth as one sum, covering the period from May 8 to November 14. Equipment charges likewise are lumped together, without elaboration, and set forth as one sum, covering the period from April 1 to November 14. It is impossible to determine from these figures the “amount and value” of material and equipment supplied, in any other than the most general way. Furthermore, it is unclear which payments received were applied to which charges. Even though appellees continue to argue that the sworn statement was itemized, we agree with the trial court and the court of appeals that appellees failed to itemize in accordance with R.C. 1311.26.

We proceed to the specific issue to be determined, which is: What is the consequence of a failure to itemize? In concluding that a failure to itemize was not fatal to appellees’ cause of action based on the mechanic’s lien, the court of appeals determined that R.C. 1311.26 should be liberally construed, in the same way that former R.C. 1311.24 (now R.C. 1311.22) required a liberal construction of former R.C. 1311.01 to 1311.24 (now R.C. 1311.01 to 1311.22). The court of appeals held that, because former R.C. 1311.24 (now R.C. 1311.22) provided that “substantial compliance * * * is sufficient for the validity of” a mechanic’s lien, “technical objections are disfavored.” The court of appeals decided that proof could be presented at trial to correct the failure to itemize.

The interpretation given by the court of appeals to the provisions of R.C. 1311.26 is not consistent with prior case law established by this court. In Robert V. Clapp Co. v. Fox (1931), 124 Ohio St. 331, 178 N.E. 586, paragraph one of the syllabus, this court held: “Mechanics’ lien statutes create rights in derogation of the common law and should therefore be strictly construed as to question whether a lien attaches, but their procedural and remedial provisions should be liberally construed, after the lien has been created.” See, also, C. C. Constance & Sons v. Lay (1930), 122 Ohio St. 468, 469, 172 N.E. 283, 283 (The statutory steps to establish a mechanic’s lien must be followed, “and in that respect the law is strictly construed and applied.”).

In a decision consistent with the holdings of Robert V. Clapp Co. and C. C. Constance & Sons, the Court of Appeals for Hamilton County, in Banks, supra, 31 Ohio App.3d 54, 31 OBR 94, 508 N.E.2d 966, held at paragraph one of the syllabus: “To assert a valid mechanic’s lien against a property owner for work performed as a by-product of a public improvements contract, a subcontractor must comply with the procedural requirements set forth in R.C. 1311.26. Failure to submit an itemized statement in accordance with these mandatory statutory requirements precludes relief as a matter of law on the basis of a mechanic’s lien.”

[593]*593We approve of the approach of Banks on this issue. We hold that the failure to comply with former R.C. 1311.26’s requirement of an itemized statement of the amount and value of labor performed and material, fuel, or machinery furnished precludes relief as a matter of law on the basis of a mechanic’s lien.2

Appellant also argues that appellees’ filing of a combined statement which did not indicate which charges were applicable to each company should have precluded recovery on the mechanic’s lien. Because we hold that the mechanic’s lien was invalid due to the failure to itemize, we do not separately address this contention. However, we do observe that a properly itemized statement would have indicated the “amount and value” of the charges asserted by each company.3

Appellees' failure to file an itemized sworn statement precluded the right to recover on the mechanic’s lien, as a matter of law. The judgment of the court of appeals is reversed, and the judgment of the trial court is reinstated.

Judgment reversed.

Moyer C.J., A.W. Sweeney, Douglas and F.E. Sweeney, JJ., concur. Wright and Pfeifer, JJ., dissent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zara Constr., Inc. v. Belcastro
2022 Ohio 788 (Ohio Court of Appeals, 2022)
Premier Const. Co., Inc. v. Maple Glen Apts. & Townhomes, Ltd.
2020 Ohio 4779 (Ohio Court of Appeals, 2020)
SRS Distrib., Inc. v. Axis Alliance, L.L.C.
2020 Ohio 1529 (Ohio Court of Appeals, 2020)
McGarry & Sons, Inc. v. Constr. Resources One, L.L.C.
2018 Ohio 528 (Ohio Court of Appeals, 2018)
Danopulos v. Am. Trading II, L.L.C.
2016 Ohio 5014 (Ohio Court of Appeals, 2016)
Burroughs Framing Specialists, Inc. v. 505 W. Main St., L.L.C.
2014 Ohio 3961 (Ohio Court of Appeals, 2014)
Fifth Third Bank v. Ohio Farmers Ins. Co.
2011 Ohio 1774 (Ohio Court of Appeals, 2011)
Abrams v. Fuerst
2011 Ohio 1641 (Ohio Court of Appeals, 2011)
Guernsey Bank v. Milano Sports Enterprises, L.L.C.
894 N.E.2d 715 (Ohio Court of Appeals, 2008)
State Ex Rel. Asti v. Ohio Department of Youth Services
2005 Ohio 6432 (Ohio Supreme Court, 2005)
Hoppes Builders & Development Co. v. Hurren Builders, Inc.
692 N.E.2d 622 (Ohio Court of Appeals, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
66 Ohio St. 3d 588, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crock-construction-co-v-stanley-miller-construction-co-ohio-1993.