Premier Const. Co., Inc. v. Maple Glen Apts. & Townhomes, Ltd.

2020 Ohio 4779, 159 N.E.3d 1201
CourtOhio Court of Appeals
DecidedOctober 5, 2020
DocketCA2020-03-011
StatusPublished
Cited by3 cases

This text of 2020 Ohio 4779 (Premier Const. Co., Inc. v. Maple Glen Apts. & Townhomes, Ltd.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Premier Const. Co., Inc. v. Maple Glen Apts. & Townhomes, Ltd., 2020 Ohio 4779, 159 N.E.3d 1201 (Ohio Ct. App. 2020).

Opinion

[Cite as Premier Const. Co., Inc. v. Maple Glen Apts. & Townhomes, Ltd., 2020-Ohio-4779.]

IN THE COURT OF APPEALS

TWELFTH APPELLATE DISTRICT OF OHIO

CLERMONT COUNTY

PREMIER CONSTRUCTION CO., INC., : CASE NO. CA2020-03-011

Appellant, : OPINION 10/5/2020 : - vs - :

MAPLE GLEN APARTMENTS AND : TOWNHOUSES LTD., et al., : Appellees.

CIVIL APPEAL FROM CLERMONT COUNTY COURT OF COMMON PLEAS Case No. 2018 CVE 00481

Law Office of John H. Forg, John H. Forg, III, 11156 Main Street, Suite D, Sharonville, Ohio 45241, for appellant

Patrick L. Gregory, 717 West Plane Street, P.O. Box 378, Bethel, Ohio 45106, for appellees

M. POWELL, P.J.

{¶ 1} Premier Construction Co., Inc. appeals the decision of the Clermont County

Court of Common Pleas, dismissing its claims against Maple Glen Apartments and

Townhouses, Ltd. For the reasons that follow, this court reverses the trial court's decision

and remands for further proceedings. Clermont CA2020-03-011

{¶ 2} In 2018, Premier filed suit against Maple Glen and its owner and manager,

Indira Murthy, asserting breach of contract and mechanic's lien foreclosure claims.1 The

matter proceeded to a bench trial, where the evidence revealed that Premier was engaged

in the business of supplying materials for residential construction. Maple Glen is a business

engaged in owning and managing apartments.

{¶ 3} In January 2017, Murthy came to Premier's offices and met with Premier's

owner, Jan Gilkey. Murthy presented Gilkey with blueprints for the construction of an 18-

unit apartment building on Maple Glen's property. Murthy apparently wanted Premier to

provide the materials and labor to construct the building. However, Gilkey informed Murthy

that Premier did not have sufficient workers to construct a building of that size. Instead,

Premier agreed to supply building materials for the project, including lumber for framing,

and trim materials. Premier further agreed to assist Murthy in finding carpenters for the

project.

{¶ 4} Based on Murthy's blueprints, and with some modifications suggested by

Premier, Premier provided Murthy with an initial estimate. Murthy determined that the price

was too high and did not proceed. Later, Premier provided Murthy with a second estimate.

This written estimate was presented to Murthy on a Premier form titled "Estimate" which

appears similar to a standard price quotation form. The form contains four columns,

"Description," "Qty," "Price/Each" and "Total."

{¶ 5} The "Description" column listed the building materials that Premier proposed

to deliver, including framing materials, exterior trim, and interior trim. The "Qty" column was

left blank. The "Price/Each" column listed the unit prices for the materials that Premier

1. Premier filed suit against "Glen Maple Apartments and Townhouses, Ltd" but referred to the defendant in the body of the complaint as "Maple Glen Apartments and Townhouses, Ltd." Throughout these proceedings the parties and court have variously referred to the defendant as either "Glen Maple" or "Maple Glen." Maple Glen points out that its legal name is Maple Glen Apartments and Townhouses, Ltd. -2- Clermont CA2020-03-011

proposed to deliver. For example, the framing materials were listed at a price of $107,300.

Finally, the "Total" column contained identical figures as the "Total/Each" column. The

grand total for the project was listed at the bottom of the form and was $165,666.08. Murthy

signed the estimate on behalf of Maple Glen on September 6, 2017. Gilkey also signed the

estimate.

{¶ 6} Gilkey testified that after the estimate was signed, the only issue left to resolve

was when to make delivery to the job site. Gilkey said he and Murthy agreed that Premier

would deliver the building materials in stages corresponding to the construction of the

building's floors. Thus, Premier and Maple Glen agreed that the first delivery would contain

the materials necessary to construct the first floor.

{¶ 7} Premier delivered the materials for the first floor to Maple Glen's job site in

early October. On October 16, 2017, Premier issued Maple Glen an invoice for $24,331.20,

which constituted payment for the first floor materials. The invoice indicated it was due

upon receipt and that 1.5% interest would accrue per month after 30 days.

{¶ 8} Thereafter, due to a problem with the installation of foundation steel column

supports, Murthy decided to postpone construction until the spring of 2018.2 Murthy asked

Premier to retrieve the delivered materials, store them for her over the winter, guarantee

their pricing, and redeliver the materials in March 2018.

{¶ 9} Gilkey told Murthy that what she was proposing would be expensive and

asked for payment for the delivered materials. However, Maple Glen did not pay. Gilkey

testified that when it became apparent that Maple Glen did not intend to pay for the

materials, he rented heavy equipment and transferred the materials from the job site to

Premier's location.

2. The evidence indicated that without steel columns in place, carpenters could have worked for a few days before they would need to stop work and wait for the steel column installation. -3- Clermont CA2020-03-011

{¶ 10} Premier issued a second invoice to Maple Glen that listed charges for the

costs to retrieve the materials from the job site. This included charges for the rental of a

forklift, two truck trips, and labor. This invoice totaled $3,447.00.

{¶ 11} Maple Glen did not pay this invoice. In January 2018, Premier issued two

updated invoices, adding accrued interest. Also, in January 2018, Premier recorded an

affidavit for mechanic's lien on Maple Glen's real property in the amount of $29,516.70. This

amount represented the entire unpaid balance on both updated invoices.

{¶ 12} Gilkey testified that he sought to sell the retrieved building materials. Over

the course of the next year, he was able to recoup approximately $18,000 by selling the

materials. Thus, he was seeking approximately $7,000 from Maple Glen in contractual

damages.

{¶ 13} After hearing the evidence, the trial court issued a decision dismissing

Premier's contract claim. The court analyzed the issue as a "sale of goods" under the

Uniform Commercial Code (UCC) and found that the parties had not validly contracted

because the written estimate did not list the quantity of goods and therefore violated the

statute of frauds as set forth in R.C. 1302.04. The court further noted that it found the

estimate vague as to the goods to be supplied, and lacking a place of delivery, time of

delivery, and terms of payment.

{¶ 14} The court also dismissed Premier's claim to foreclose its mechanic's lien. The

court found that the lien was invalid because it was premised on an invalid contract. The

court further found that the lien was invalid because the materials furnished by Premier

were not used to improve Maple Glen's property and had been removed from the job site.

Premier appeals, raising two assignments of error.

{¶ 15} Assignment of Error No. 1:

-4- Clermont CA2020-03-011

{¶ 16} THE TRIAL COURT ERRED IN RULING THAT PREMIER CONSTRUCTION

AND MAPLE GLEN APARTMENTS DID NOT ENTER INTO A CONTRACT FOR THE

DELIVERY OF MATERIALS FOR THE CONSTRUCTION OF A MULTI-UNIT

APARTMENT BUILDING AND THAT MAPLE GLEN APARTMENTS BREACHED THAT

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2020 Ohio 4779, 159 N.E.3d 1201, Counsel Stack Legal Research, https://law.counselstack.com/opinion/premier-const-co-inc-v-maple-glen-apts-townhomes-ltd-ohioctapp-2020.