Decker Constr. Co. v. Ohio River Pipe Line, Unpublished Decision (2-1-2007)

2007 Ohio 421
CourtOhio Court of Appeals
DecidedFebruary 1, 2007
DocketNo. 06AP-483 (C.P.C. No. 04CV10920).
StatusUnpublished
Cited by3 cases

This text of 2007 Ohio 421 (Decker Constr. Co. v. Ohio River Pipe Line, Unpublished Decision (2-1-2007)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Decker Constr. Co. v. Ohio River Pipe Line, Unpublished Decision (2-1-2007), 2007 Ohio 421 (Ohio Ct. App. 2007).

Opinion

OPINION
{¶ 1} Defendants-appellants, Ohio River Pipe Line, LLC ("ORPL"), Marathon Ashland Petroleum, LLC ("MAP"), Safeco Insurance Company of America and General Insurance Company of America (collectively, "appellants"), appeal the judgment of the Franklin County Court of Common Pleas granting summary judgment in favor of plaintiff-appellee, Decker Construction Company ("appellee"), on appellee's claim for money damages against the bond substituted in place of appellee's mechanic's lien, which had formerly been placed upon property owned by Emerald Glen Housing Limited Partnership ("Emerald Glen").

{¶ 2} The following pertinent facts are undisputed. Emerald Glen is the owner in fee simple of a certain parcel of land located in Franklin County. ORPL owns an interstate petroleum pipeline that travels from Kenovia, West Virginia to Columbus, Ohio.

{¶ 3} On June 9, 1998, ORPL recorded an instrument entitled "Easement Deed" in the office of the Franklin County Recorder. The Easement Deed reflected an agreement between ORPL and Emerald Glen under which ORPL agreed to pay $8,000 in exchange for:

[A]n easement to lay, construct, operate, inspect, maintain, replace, change the size of, relocate and remove a pipeline for any uses or substances, at routes selected by [ORPL], in and through the "SITE". * * * [ORPL's] right-of-way will consist of a strip of land extending 25 feet on either side of the pipeline as first installed (the "Strip"). Company shall have the rights to, from time to time: install, operate, inspect, maintain, replace, relocate and remove pipeline appurtenances, cables and equipment in the Strip; * * * and use a reasonable working area for exercise of rights granted hereunder. * * *

{¶ 4 The easement deed specified that the "agreement shall bind and benefit the parties' heirs, legal representatives, successors and assigns * * * [and] the terms herein shall be independent and survive execution of any further agreements." Following recording of this instrument, ORPL proceeded to construct its pipeline. During construction, ORPL determined that it required placement of a gravitometer in the area of the pipeline located on the Emerald Glen property. This required ORPL to obtain a second easement.

{¶ 5} On October 28, 1999, ORPL recorded an instrument entitled, "Appurtenance Deed." This deed reflected a June 14, 1999 agreement whereby ORPL paid the sum of $500 in exchange for "an easement for above and below ground facilities located on the Site and appurtenant to [ORPL's] pipeline traversing the Site." Specifically, Emerald Glen granted:

[A]n easement to install, operate, inspect, maintain, replace, change the size of, relocate and remove piping, valves, meters, communication equipment, pipeline protection devices, including rectifiers, anodes, cables, test leads and other pipeline appurtenances above and below ground at the Site. [ORPL] shall have right to, from time to time: fence, secure, grade, gravel and pave; permit utilities to cross [Emerald Glen's] property to supply utility service; comply in a convenient manner with any present or future legal obligation or governmental request; access any point at the Site over any property which [Emerald Glen] owns now or in the future; install additional piping and appurtenances at no additional cost; and use a reasonable working area for any purpose convenient to [ORPL's] exercise of its rights granted hereunder.

{¶ 6} This deed, too, included language benefiting the heirs, legal representatives, successors and assigns of the parties thereto.

{¶ 7} On or about May 5, 2003, MAP, the parent company of ORPL, entered into a contract with H.L. Crouse Construction Company, Inc. ("Crouse"), the general contractor for the pipeline construction project, for the construction of a paved access road on the Emerald Glen property, for purposes of accessing the gravitometer site. In turn, on May 13, 2003, Crouse entered into a contract with appellee for all labor, materials and equipment required for the construction of the paved access road. Appellee commenced work on the road on June 4, 2003, and completed work on June 20, 2003. Crouse ultimately defaulted on its contract with appellee, leaving a balance due and owing to appellee in the amount of $25,871.

{¶ 8} On August 27, 2003, appellee filed for record in the office of the Franklin County Recorder an Affidavit for Mechanic's Lien upon the Emerald Glen property. Appellee served notice of the affidavit for mechanic's lien upon Emerald Glen, Crouse, and MAP, but did not serve ORPL. On December 30, 2003, the Franklin County Court of Common Pleas journalized an order approving ORPL's application to substitute a bond for appellee's mechanic's lien. On October 18, 2004, appellee filed this action to validate its mechanic's lien and to recover money damages on the bond substituted for the lien.

{¶ 9} The parties filed cross-motions for summary judgment. The trial court ultimately found that appellee's mechanic's lien was unenforceable against ORPL and MAP, but nonetheless found that it was entitled to collect on the bond because it had properly perfected its lien against Emerald Glen. Appellants timely appealed and advance one assignment of error for our review:

Assignment of Error No. 1

THE TRIAL COURT ERRED IN GRANTING PLAINTIFF'S MOTION FOR SUMMARY JUDGMENT REGARDING RECOVERY ON THE BOND SUBSTITUTED IN PLACE OF PLAINTIFF'S MECHANIC'S LIEN AND IN DENYING DEFENDANTS-APPELLANT'S MOTION FOR SUMMARY JUDGMENT[.]

{¶ 10} We review the trial court's grant of summary judgment de novo.Coventry Twp. v. Ecker (1995), 101 Ohio App.3d 38, 654 N.E.2d 1327. Summary judgment is proper only when the party moving for summary judgment demonstrates: (1) no genuine issue of material fact exists, (2) the moving party is entitled to judgment as a matter of law, and (3) reasonable minds could come to but one conclusion, and that conclusion is adverse to the party against whom the motion for summary judgment is made, when the evidence is construed in a light most favorable to the nonmoving party. Civ.R. 56(C); State ex rel. Grady v. State Emp. Rels.Bd. (1997), 78 Ohio St.3d 181, 183, 677 N.E.2d 343. We review questions of law de novo. Nationwide Mut. Fire Ins. Co. v. Guman Bros. Farm (1995), 73 Ohio St.3d 107, 108, 652 N.E.2d 684, citing Ohio Bell Tel.Co. v. Pub. Util. Comm. (1992), 64 Ohio St.3d 145, 147, 593 N.E.2d 286.

{¶ 11} Appellants make two arguments in support of their assignment of error.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kreuzer v. Kreuzer
2015 Ohio 3253 (Ohio Court of Appeals, 2015)
Fifth Third Bank v. Ohio Farmers Ins. Co.
2011 Ohio 1774 (Ohio Court of Appeals, 2011)
Geier v. Swank
928 N.E.2d 1162 (Ohio Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
2007 Ohio 421, Counsel Stack Legal Research, https://law.counselstack.com/opinion/decker-constr-co-v-ohio-river-pipe-line-unpublished-decision-2-1-2007-ohioctapp-2007.