Crest Ridge Construction Group, Inc. v. Newcourt Inc.

78 F.3d 146, 1996 WL 82626
CourtCourt of Appeals for the Fifth Circuit
DecidedFebruary 27, 1996
Docket94-41228
StatusPublished
Cited by34 cases

This text of 78 F.3d 146 (Crest Ridge Construction Group, Inc. v. Newcourt Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crest Ridge Construction Group, Inc. v. Newcourt Inc., 78 F.3d 146, 1996 WL 82626 (5th Cir. 1996).

Opinions

PATRICK E. HIGGINBOTHAM, Circuit Judge:

This diversity case concerns a dispute between a subcontractor and a supplier. The supplier appeals, on the grounds of sufficiency of the evidence, a jury verdict awarding the subcontractor damages for breach of contract. We have jurisdiction under 28 U.S.C. § 1291, and we affirm.

I

In 1989, two brothers, John and Joseph Brower, formed a company called Crest Ridge Construction Group, Inc. and sought to enter the construction business. Previously, the Browers had brokered construction deals through a company called J.B. & Associates.

In early 1990, Taylor Woodrow Construction Co., a general contractor, awarded a subcontract to Crest Ridge for certain portions of the construction of the Liberty Science Center in Jersey City, New Jersey. One portion of the subcontract required Crest Ridge to supply architectural wall paneling for the Center. The Browers began discussions with Newcourt, Inc., a former client of J.B & Associates that supplied relatively low-cost foam paneling. The Browers succeeded in gaining Taylor Woodrow’s approval for the use of Newcourt’s foam paneling in the construction of the Center, and the parties began to exchange information detailing the requirements for the paneling job.

In late October, 1990, Newcourt issued a price quotation to J.B. & Associates of $758,-000 to supply the necessary paneling. The price quotation was made “subject to credit department approval.” Four days later, John Brower wrote to Newcourt requesting that Newcourt issue a quotation to the name of Crest Ridge and that Newcourt make further clarifications regarding the details of the job. The record contains no subsequent price quotation in the name of Crest Ridge. It does, however, contain two “add-ons,” modifications to the price quotation reflecting changes in Newcourt’s understanding of the job specifications, issued from Newcourt to Crest Ridge. These add-ons increased Newcourt’s price quote to $760,000.

On November 7, 1990, Crest Ridge sent Newcourt a completed credit application form reciting that Crest Ridge had been established in 1985 and listing one banking and four trade references. That same day, Newcourt contacted Crest Ridge’s banking reference and discovered that Crest Ridge had opened an account early in 1990 bearing an average balance of $5000. Newcourt also contacted Crest Ridge’s trade references. One wrote back on November 20, stating, “No knowledge of this aceount-perhaps we dealt with them under a different name.” On December 3, a second responded, “No a/c. Please supply a/c #.” Newcourt did not hear from the other references.

Newcourt began investigating other methods of guaranteeing payment. The record includes contradictory information regarding the results of this investigation. In January, 1991, Newcourt contacted an attorney in New Jersey about the possibility of placing a lien on the Liberty Science Center. Calvin Court, president of Newcourt, testified that in January or February of 1991, he knew that Newcourt could place a lien on the prop[149]*149erty. In contrast, a letter from Newcourt to Crest Ridge dated February 8, 1991 stated that the property search “raised questions.” This letter reiterated a request made on January 25 for either a copy of a payment bond protecting Newcourt or sufficient information allowing Newcourt to secure a copy of such a bond on its own. One month later, Crest Ridge faxed Newcourt the name and address of Crest Ridge’s bonding company. Newcourt did not contact the bonding company. John Brower testified that Crest Ridge sent Newcourt a copy of a bond guaranteeing Taylor Woodrow’s payment to Crest Ridge late in 1990, but Crest Ridge did not introduce a copy of this correspondence or the bond into evidence. In early March, New-court contacted American Credit Indemnity Company and was unable to purchase accounts receivable insurance from that company. The record includes no information about the specifics of this communication between American and Newcourt.

Meanwhile, the parties continued to exchange information. On January 4, 1991, Crest Ridge issued a purchase order to Newcourt quoting a price of $760,000 and referencing Neweourt’s original price quotation and its two add-ons. The record includes a flurry of letters from October, 1990 to March, 1991 between Crest Ridge and Newcourt concerning the details of the project. Newcourt supplied samples of its wall paneling material, job specifications and calculations, three revisions of shop drawings, and final drawings showing where each panel would be placed at the Center. Crest Ridge and Newcourt had extended discussions over coils and over the strength of wall paneling fasteners. Newcourt was to make the first shipment of wall paneling later in 1991.

Testimony at the trial established certain customs and practices in the construction industry. First, the industry considered a purchase order issued in response to a price quotation as a binding event. Second, construction companies presumed that a supply contract without payment terms would proceed pursuant to a standard schedule. According to this schedule, the supplier billed the subcontractor by the 25th of the month and could expect payment by the tenth of the second month thereafter. This 45-day interval allowed a bill to travel from the subcontractor to the general contractor to the owner, and for payment to return from the owner to the general contractor to the subcontractor to the supplier.

On March 25, 1991, Newcourt wrote to Crest Ridge suspending all further work on the wall paneling project and demanding payment in full by April 5. The letter did not mention credit problems; it gave as Newcourt’s reasons for demanding full payment “the encumbering and confusing progress and lack of receiving pertinent data necessary to satisfy the requirements on the above-referenced project.”1 In response to the March 25 demand letter, Crest Ridge attempted several times to contact Newcourt, but Newcourt did not respond. Crest Ridge then cancelled its order with Newcourt and covered by obtaining paneling from Alply, Inc. at a higher price. Newcourt never shipped any paneling to Crest Ridge.

Crest Ridge sued Newcourt for breach of contract in New Jersey state court. Newcourt removed the action to federal court, alleging diversity of citizenship. The New Jersey federal court transferred the case to the Eastern District of Texas, where it was tried to a jury. At the close of the plaintiffs case, Newcourt moved for judgment as a matter of law, citing the “subject to credit department approval” phrase in its price quotation and arguing that no contract could have existed because Crest Ridge never obtained the approval of Neweourt’s credit department. The district court denied the motion, which Newcourt did not renew either at the close of all the evidence or after the jury’s verdict.

The district court instructed the jury regarding the definition of a contract and the nature of contract formation. Neither party objected to the charge. In response to the [150]*150three interrogatories put to it, the jury found that a contract existed between Crest Ridge and Newcourt, that Neweourt breached the contract, and that Crest Ridge’s damages totaled $70,214.28.

II

The sole issue on this appeal is whether the evidence was sufficient to support the jury’s verdict that a contract existed between Neweourt and Crest Ridge and that Newcourt breached the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kenisha Boyd v. TDCJ
Fifth Circuit, 2019
J.D. Fields & Co. v. Eng'rs
391 F. Supp. 3d 698 (S.D. Texas, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
78 F.3d 146, 1996 WL 82626, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crest-ridge-construction-group-inc-v-newcourt-inc-ca5-1996.