Stanwood Boom Works, LLC v. BP Exploration & Production, Inc.

476 F. App'x 572
CourtCourt of Appeals for the Fifth Circuit
DecidedApril 25, 2012
Docket11-20511
StatusUnpublished
Cited by2 cases

This text of 476 F. App'x 572 (Stanwood Boom Works, LLC v. BP Exploration & Production, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stanwood Boom Works, LLC v. BP Exploration & Production, Inc., 476 F. App'x 572 (5th Cir. 2012).

Opinion

PER CURIAM: *

The issue presented in this appeal is whether there was an enforceable contract between appellant and appellee. BP Exploration & Production, Inc. (“BP”) drafted a purchase order and sent it to Stan-wood Boom Works, LLC (“Stanwood”). Stanwood informed BP that Stanwood required BP’s signature prior to moving forward, and Stanwood added a signature block for BP. BP never signed it. The district court ruled that there was no contract and no claim for promissory estoppel. The district court further ruled that Stan-wood is not entitled to additional discovery to discern the intent of the parties. We AFFIRM.

Facts and Procedural History

A. Pre-Purchase Order Negotiations

In June 2010, BP began negotiating with Stanwood for the potential purchase of containment boom. Before BP even considered purchasing Stanwood’s containment boom, BP inspected and assessed Stanwood’s manufacturing processes. During this assessment, BP found that Stanwood’s boom did not meet BP’s typical requirements. By July 1, 2010, Stanwood requested that BP make an exception to its requirements. The next day — July 2, 2010 — Stanwood e-mailed BP its pricing per foot and its current capacity for production of boom. However, on July 5, 2010, BP rejected Stanwood’s price. Later that same day, Stanwood provided another quote to BP. Stanwood did not lower its price. Over the next two days, Stanwood and BP continued to negotiate a price. When the parties neared an agreement on price, Stanwood raised other terms to be discussed further. On July 7, 2010, Stanwood insisted on a purchase order before going forward, and BP reiterated that no deal had yet been approved. On July 8, 2010, Stanwood requested a conference call to negotiate the terms and conditions further, including terms regarding the warranty on product clause, the cancellation provision, the penalty fees clause, the delivery schedule and the re *574 newal portion. Stanwood communicated these changes to BP. BP replied that same day that the new terms needed to be approved by management. Stanwood then required either BP’s signature or money down as consideration for any future contract.

B. Purchase Order Negotiations

On July 8, 2010, BP first sent a purchase order — titled “BP-DIS-0022 Rev. 0” — to Stanwood. Upon review, Stanwood uncovered several objectionable terms that warranted more negotiations. Thus, Stan-wood refused to execute it.

On July 9, 2010, Stanwood and BP held another telephone conference. BP specifically informed Stanwood that it could not seek authority to enter into the purchase order until after Stanwood signed.

On July 10, 2010, BP emailed another purchase order — titled “BP-DIS-0022 Rev. 1” — to Stanwood. Stanwood signed the purchase order and wrote in a signature block for BP. Daniyal Siddiqui, a Purchasing Specialist at BP, responded that he did not have approval for the appropriate signatures from BP. BP never signed the purchase order.

On July 12, 2010 (four days after BP’s initial draft purchase order), BP emailed yet another purchase order — titled “BP-DIS-0022 Rev. 2” — to Stanwood. Again, Stanwood wrote in a signature block for itself and for BP, signed the document, and sent it back to BP. BP never signed the purchase order and never purchased boom from Stanwood.

C. Procedural History

Stanwood brought suit against BP asserting claims of breach of contract and promissory estoppel. The district court ordered the parties to agree on an exhibit list to use in summary judgment briefing. The district court placed no limitations or restrictions on this agreed exhibit list. Stanwood and BP chose the documents to support their respective summary judgment arguments. Stanwood and BP conferred and agreed on a list, which included email communications between the parties during their negotiations. Stanwood never raised any issues regarding the content of the record. After the parties filed cross motions for summary judgment, the district court granted summary judgment in favor of BP. Stanwood moved for reconsideration, requesting open-ended discovery, document production, and depositions about BP’s internal communications, policies, and handling of other purchase orders in its extensive business. The district court denied Stanwood’s motion. Stan-wood appealed.

Analysis

A. Standard of Review

This court reviews summary judgments de novo, and applies the same standards as the district court. Greater Houston Small Taxicab Co. Owners Ass’n v. City of Houston, Tex., 660 F.3d 235, 238 (5th Cir.2011). Summary judgment is proper if there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law. Id.; see also Fed.R.Civ.P. 56(a).

B. Contract Formation

“When reviewing written negotiations, the question of whether an offer was accepted and a contract was formed is primarily a question of law for the court to decide.” Scaife v. Associated Air Ctr. Inc., 100 F.3d 406, 410 (5th Cir.1996) (citing S & A Marinas, Inc. v. Leonard Marine Corp., 875 S.W.2d 766, 769 (1994)). “If an agreement has been reduced to writing, as it was in this case, an assent to the writing must be manifested. Manifes *575 tation of assent ‘commonly consists of signing and delivery.’” Scaife, 100 F.3d at 410-11. Scaife involved a proposed agreement to repair and renovate an aircraft. Id. The agreement “was revised at least three times and expressly contained signature blocks for the parties.” Id. at 411. The agreement was never signed, but Scaife nonetheless argued it was enforceable against the repair company. Id. The district court, “treating the formation of a binding contract as a legal issue for the court to decide,” granted summary judgment for the repair company. Id. at 409. This court affirmed, holding “that the parties contemplated the formation of a binding agreement to include the signatures of both parties.” Id. at 411. “No evidence” showed that the defendant “began work on the aircraft or acted in any affirmative manner to assent to the agreement notwithstanding the lack of delivery and formal execution of the contract.” Id. Thus, “no contract was ever formed and, as a result, summary judgment was appropriate in this case.” Id. The circumstances are fundamentally the same here, including the suspension of performance by the parties.

Contracts require mutual assent to be enforceable. Baylor Univ. v. Sonnichsen,

Related

Cite This Page — Counsel Stack

Bluebook (online)
476 F. App'x 572, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stanwood-boom-works-llc-v-bp-exploration-production-inc-ca5-2012.