City of New Haven v. Chandler

446 F. Supp. 925, 11 ERC 1426, 8 Envtl. L. Rep. (Envtl. Law Inst.) 20475, 11 ERC (BNA) 1426, 1978 U.S. Dist. LEXIS 19573
CourtDistrict Court, D. Connecticut
DecidedFebruary 14, 1978
DocketCiv. N-77-406
StatusPublished
Cited by6 cases

This text of 446 F. Supp. 925 (City of New Haven v. Chandler) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of New Haven v. Chandler, 446 F. Supp. 925, 11 ERC 1426, 8 Envtl. L. Rep. (Envtl. Law Inst.) 20475, 11 ERC (BNA) 1426, 1978 U.S. Dist. LEXIS 19573 (D. Conn. 1978).

Opinion

MEMORANDUM OF DECISION

DALY, District Judge.

The City of New Haven (the City) has requested that this Court permanently enjoin the construction of three electrical transmission towers being built by the defendant United Illuminating Company (the Company) in New Haven Harbor alongside the Quinnipiac Bridge (Interstate 95) under a permit issued by the defendant U. S. Army Corps of Engineers (the Corps). 1 The City argues that the permit is invalid and that the construction should therefore be enjoined because the Corps violated § 102 of the National Environmental Policy Act of 1969 (NEPA) 2 by I) failing to file an envi *928 ronmental impact statement (EIS) as required by 42 U.S.C. § 4332(2)(C), II) not considering adequately the alternatives to the proposed project in contravention of 42 U.S.C. § 4332(2)(E), and III) neglecting to develop standards for the evaluation of aesthetics in violation of 42 U.S.C. § 4332(2)(B). For the reasons discussed below, the relief requested by the plaintiff is denied.

I. BACKGROUND

The present dispute began in the nineteen-sixties, when the Company held discussions with the City regarding the construction of a transmission line connecting downtown New Haven with the 345,000 kv New England electrical grid and the proposed New Haven Harbor Station on the opposite, eastern side of the harbor. The line was to extend along nineteen towers, three of which were to stand in the harbor. In August of 1969, the Company applied to the Corps for a permit to construct three 115 kv overhead transmission towers and lines pursuant to § 10 of the River and Harbor Act of 1899, 33 U.S.C. § 403. The Corps issued a public notice regarding the application, and received over 100 objections focusing primarily on aesthetics. This application was withdrawn before a decision was rendered.

Negotiations between the Company and the City continued, as a result of which the Company agreed to modify the proposed route of the transmission line and the pole design. In 1971 the Connecticut Public Utilities Commission approved construction of the entire line after extensive hearings, and in 1974 the Connecticut Supreme Court upheld the PUC decision. 3 Within weeks of the PUC approval, the Company filed a new application with the Corps. The Company also applied to the Connecticut Department of Environmental Protection for permission to construct the three towers in the harbor. In October of 1972, the state Commissioner of Environmental Protection denied the construction permit, citing the potential aesthetic impact of the project. Because of this negative decision by the state, the Corps returned the Company’s application. The City then appealed the Commissioner’s decision, and won. The Superior Court Judge concluded that the decision had been based on legislation not applicable to the construction project. 4 In March of 1975, the succeeding Commissioner approved the proposal on the basis of the hearing examiner’s report. 5

On April 23, 1975 the Company reapplied to the Corps for a permit to construct three 180 feet electrical transmission towers in New Haven Harbor. The application was followed in September by an environmental report from the Company’s consultant. The Corps then prepared an environmental assessment. In November of 1975 the Corps issued a public notice announcing that it had reached a preliminary determination that an EIS was not required because the environmental impact of the transmission line would not be “significant.” The assessment concentrated on the water quality and land-fill questions and barely dealt with aesthetics. In response to the widely-circulated notice, those opposing the project contacted the Corps, including the City, local organizations, political leaders, and private citizens. Other federal agencies also responded. The National Ma *929 rine Fisheries service informed the Corps that it “reluctantly” offered no objection to the project. The U.S. Fish and Wildlife Service reported that no significant adverse effects were expected. The U.S. Environmental Protection Agency had no comment.

As a result of the many objections to the project, the Corps held a public hearing on August 12, 1976 at which those concerned with the construction project were allowed to present their views and ask questions. A Company spokesman began the hearing. He was followed by state legislators, the Mayor of New Haven, other local political' leaders, and the head of New Haven’s development program, all in opposition to the project. A representative of the local Chamber of Commerce then spoke in favor of the project. Various neighborhood and environmental groups sent speakers to oppose the construction, and local citizens contributed their views. Written statements were also submitted. The National Marine Fisheries Service submitted a supplemental letter specifying the agency’s concern with the impact of altered turbidity levels on the nearby oyster beds. The Corps also solicited the advice of the Department of Housing and Urban Development as to the impact of transmission lines upon urban renewal programs, and whether there were guidelines concerning such construction. HUD responded that aesthetics were an important element in urban decay, and that the towers and lines were “generally in conflict with the goals and objectives” of the local urban renewal effort. The Corps also sought further information from the Company regarding utility rates and the manner in which the Company intended to absorb the long-term costs of the project.

During the summer of 1977, the Corps attempted to reach a compromise between the opponents of the project and the Company by proposing the issuance of a permit for only 10 years, to be followed by a reevaluation of the project. The City rejected the proposal. On September 20,1977 the Corps issued the construction permit subject to full review “[i]f at any time it is demonstrated that this action has caused impacts which adversely effect New Haven’s redevelopment potential or are not in the overall public interest . . . .” The Corps accompanied the permit with a formal environmental assessment and findings of fact. In a letter to the Mayor of New Haven, the Division Engineer, Colonel Chandler, noted that the decision was “truly one of the two or three most difficult regulatory decisions to face us in New England.” On October 21, 1977 the City filed this suit. 6 The general issue, raised in a variety of contexts, is whether in issuing the permit to construct the three transmission towers the Corps acted arbitrarily, capriciously, in abuse of discretion, or otherwise not in accordance with law. Administrative Procedure Act, § 10(e), 5 U.S.C. § 706(2)(A);

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hogan v. Brown
507 F. Supp. 191 (W.D. Arkansas, 1981)
Sierra Club v. Alexander
484 F. Supp. 455 (N.D. New York, 1980)
Get Oil Out, Inc. v. Andrus
477 F. Supp. 40 (C.D. California, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
446 F. Supp. 925, 11 ERC 1426, 8 Envtl. L. Rep. (Envtl. Law Inst.) 20475, 11 ERC (BNA) 1426, 1978 U.S. Dist. LEXIS 19573, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-new-haven-v-chandler-ctd-1978.