Natural Resources Defense Council, Inc., and the State of New York, Intervenor-Appellant v. Howard H. Callaway, as Secretary of the Army

524 F.2d 79
CourtCourt of Appeals for the Second Circuit
DecidedSeptember 9, 1975
Docket916, Docket 75-7048
StatusPublished
Cited by171 cases

This text of 524 F.2d 79 (Natural Resources Defense Council, Inc., and the State of New York, Intervenor-Appellant v. Howard H. Callaway, as Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Natural Resources Defense Council, Inc., and the State of New York, Intervenor-Appellant v. Howard H. Callaway, as Secretary of the Army, 524 F.2d 79 (2d Cir. 1975).

Opinions

MANSFIELD, Circuit Judge:

The Natural Resources Defense Council, Inc., Environmental Defense Fund, Inc., The Long Island Sound Taskforce, The Fishers Island Civic Association, Inc., along with other environmental and citizen groups, brought this action in the District of Connecticut against the Secretary of the Army, the Secretary of the Navy and other related federal officials seeking declaratory and injunctive relief against further dumping by the United States Navy of highly polluted dredged spoil at the New London Dumping Site in Long Island Sound.1 The complaint charges violations of the National Environmental Policy Act of 1969, 42 U.S.C. [82]*82§ 4321 et seq. (“NEPA”), and the Federal Water Pollution Control Act Amendments of 1972, 33 U.S.C. § 1251 et seq. (“FWPCA”). The State of New York has been allowed to intervene as an appellant.

The action arises out of a project undertaken by the United States Navy at New London, Connecticut. In order to accommodate a new class of submarine, the SSN 688 class, at the Navy’s Submarine Base in Groton, Connecticut, the Navy has determined that it is necessary to dredge the Thames River from Long Island Sound to the north boundary of Groto.n, a distance of 7.5 miles. The new class of submarine is larger and requires a greater depth of water for operations than previous classes and the Navy is accordingly widening and deepening the existing Thames River Channel. This dredging operation requires the removal from the Thames River bottom and disposal of approximately 2.8 million cubic yards of highly polluted material containing volatile solids, industrial wastes and Kjeldahl nitrogen.

The dredging project began on August 19, 1974, and the first phase of dredging, involving the lower reaches of the river, is now complete. The second phase, involving the upper portion of the channel, is scheduled to commence in March 1976 and is to be completed before the arrival of the new submarines at Groton, scheduled for later in 1976. The parties agree that the material to be dredged in the second phase contains considerably larger quantities of pollutants than the material already dredged.

Plaintiffs and intervenors do not object to the dredging project itself, choosing to restrict their legal challenge to the Navy’s use of the New London Dumping Site as the disposal area. All parties agree that, because the polluted material is likely to cause great harm to the ocean ecosystem if allowed to disperse after being dumped, it is important that if it is dumped in the ocean it be deposited at a “containment site,” an area of the ocean floor where currents and other water movement will not cause it to move or disperse. The underlying disagreement between plaintiffs and the government defendants is over the relative merits of the New London Dumping Site as a containment site and the existence of more suitable sites for disposal both in the ocean and on land. Plaintiffs adduced substantial evidence that because of the shallow depth of the site, the fact that the bottom currents there were higher than at some alternative sites, and the prospective impact of storms, the sludge dumped at the New London Dumping Site, although it would remain in place for a while, would eventually break up and disperse to the northwest where it would contaminate and destroy the first nurseries and marine resources on the coast.

Plaintiffs raised three principal claims before the district court: 1) that the Army Corps of Engineers issued a dumping permit to the Navy in violation of § 404 of FWPCA, 33 U.S.C. § 1344, 2) that the Navy and the Corps failed to comply with NEPA in reaching the decision to dump at New London in that a) the Corps, not the Navy, was the proper party required to prepare the necessary Environmental Impact Statement (“EIS”), b) the EIS inadequately discussed other dumping projects and alternative dumping sites, e) the NEPA decision-making procedures were shortcircuited, and d) there were errors in the EIS, and 3) that the substantive decision by the Navy to use the New London site was arbitrary and capricious. In a thorough and carefully considered opinion the district court, M. Joseph Blumenfeld, Judge, rejected all of these contentions, holding that it lacked jurisdiction under FWPCA, that the Navy was the proper EIS author and that the EIS was adequate in all respects.2 The plaintiffs-appellants now take issue with all of the district court rulings except those dealing with the alleged errors in the EIS.

We hold that jurisdiction exists under FWPCA and that the discussion in the [83]*83EIS of other dumping projects and alternative dump sites was inadequate under NEPA. Accordingly, we reverse and remand as to those issues. Since there is a substantial risk that additional amounts of highly polluted spoil will be dredged and dumped in non-compliance with the FWPCA and NEPA we direct that the Navy be enjoined from such activity until it has satisfied the requirements of these laws. In all other aspects we affirm the district court’s opinion.

DISCUSSION

1. Jurisdiction Under FWPCA.

Under § 404 of FWPCA, 33 U.S.C. § 1344, the disposal of dredged material at the New London site requires a permit from the Army Corps of Engineers.3 Appellants argued below that the permit for this dumping was issued in violation of § 404(b) of FWPCA because it was not, as required by that section, issued in accordance with dumping guidelines developed by the Administrator of the Environmental Protection Agency (“EPA”). The district court never reached the merits of this contention, however, as it held that it lacked jurisdiction under § 505(a) of FWPCA, 33 U.S.C. § 1365(a), which authorizes citizen suits for violation of the statute. Section 505(b) places certain restrictions on the bringing of lawsuits under § 505(a), including the requirement that no suit or action be commenced “prior to sixty days after the plaintiff has given notice of the alleged violation” to the EPA and other interested parties. Such notice was given by the plaintiffs herein on July 15, 1974, but the action was commenced on September 3, 1974, less than 60 days later. The district court reasoned that the 60-day waiting period is a jurisdictional prerequisite to suit and therefore dismissed the claim.

As conceded by the government, the district court’s dismissal of the FWPCA count on this ground turns out, by reason of our later decision in Conservation Society of Southern Vermont, Inc. v. Secretary of Transportation, 508 F.2d 927, 938-39 & n. 62 (2d Cir. 1974) petition for certiorari filed 43 U.S.L.W. 3648 (U.S., May 9, 1975) (No. 74-1413), to have been in error. We there held that the 60-day notice provision is not an absolute bar to earlier suits by private citizens under FWPCA. Aside from the issue of whether less than 60 days will satisfy § 505(b) so as to permit a suit to be brought under § 505(a), it was held in Natural Resources Defense Council, Inc. v. Train, 510 F.2d 692

Free access — add to your briefcase to read the full text and ask questions with AI

Related

San Luis & Delta-Mendota Water Authority v. Salazar
686 F. Supp. 2d 1026 (E.D. California, 2009)
Sierra Club v. Flowers
423 F. Supp. 2d 1273 (S.D. Florida, 2006)
Fund for Animals v. Norton
365 F. Supp. 2d 394 (S.D. New York, 2005)
Natural Resources Defense Council v. Evans
254 F. Supp. 2d 434 (S.D. New York, 2003)
City of Ridgeland v. National Park Service
253 F. Supp. 2d 888 (S.D. Mississippi, 2002)
Texas Committee on Natural Resources v. Van Winkle
197 F. Supp. 2d 586 (N.D. Texas, 2002)
Ohio Valley Trail Riders v. Worthington
111 F. Supp. 2d 878 (E.D. Kentucky, 2000)
Citizens of Goleta Valley v. Board of Supervisors
801 P.2d 1161 (California Supreme Court, 1990)
Elliott v. United States Fish & Wild Life Service
747 F. Supp. 1094 (D. Vermont, 1990)
Roe v. Wert
706 F. Supp. 788 (W.D. Oklahoma, 1989)
McClellan Ecological Seepage Situation v. Weinberger
707 F. Supp. 1182 (E.D. California, 1988)
Moran v. Vaccaro
684 F. Supp. 1201 (S.D. New York, 1988)
Sierra Club v. Penfold
664 F. Supp. 1299 (D. Alaska, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
524 F.2d 79, Counsel Stack Legal Research, https://law.counselstack.com/opinion/natural-resources-defense-council-inc-and-the-state-of-new-york-ca2-1975.