Benjamin Jones v. James T. Lynn

477 F.2d 885, 3 Envtl. L. Rep. (Envtl. Law Inst.) 20358, 5 ERC (BNA) 1169, 1973 U.S. App. LEXIS 10941, 5 ERC 1169
CourtCourt of Appeals for the First Circuit
DecidedMarch 22, 1973
Docket73-1057
StatusPublished
Cited by81 cases

This text of 477 F.2d 885 (Benjamin Jones v. James T. Lynn) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Benjamin Jones v. James T. Lynn, 477 F.2d 885, 3 Envtl. L. Rep. (Envtl. Law Inst.) 20358, 5 ERC (BNA) 1169, 1973 U.S. App. LEXIS 10941, 5 ERC 1169 (1st Cir. 1973).

Opinions

COFFIN, Chief Judge.

This appeal, expedited to accommodate all of the parties and interests involved, presents the issue whether a complex area renewal project covering a substantial sector of Boston, the Symphony Area part of the Fenway Urban Renewal Project, the basic planning and federal financial commitment for which had been approved in 1967, but which is yet substantially incomplete, is subject in any way to the requirements of the sub[887]*887sequently enacted National Environmental Policy Act of 1969 (NEPA), 42 U.S. C. § 4331 et seq.

Appellants, residents of the area, sought to enjoin further demolition and construction in the area until an environmental statement is issued in accordance with NEPA. Appellees are the Department of Housing and Urban Development (HUD), the source of federal financial assistance; the Boston Redevelopment Authority (BRA), the municipal agency in charge of the project; and the First Church of Christ, Scientist, a prominent occupant of the area and source of much of the planning.1 The district court denied injunctive relief, finding that “major federal action” terminated with the signing of the HUD-BRA Loan and Grant Contract in 1967, that HUD’s continuing role was minor since it was powerless to alter future courses of action, and that NEPA was not intended to be applied retroactively.

I. Facts

Some appreciation of the past history and present status of the project is necessary to recognize the grey zone in which we endeavor to strike a just and practicable balance.

In the early 1960’s the Church, desirous of establishing an International Center on its present location and of developing the adjacent Symphony Area, commissioned the preparation of a master plan which incorporated these ideas with others calling for residential and commercial development. The Church plan was submitted to BRA and included in BRA’s larger proposed effort for development of the Fenway Area which was thereafter to consist of the Museum Area, Medical Center Area and the Symphony Area, all three sub-areas being of somewhat equal size and totalling 506 acres. Only questions relevant to the Symphony Area are before us. The entire Fenway Urban Renewal Plan, dated November 1, 1965, was approved by BRA on November 24, 1965; by the Boston City Council on December 20, 1965; by the Mayor of Boston on December 23, 1965; and by the Massachusetts Department of Commerce and Development on April 26, 1967 after the required public hearings. On December 22, 1967 HUD and BRA executed a Loan and Capital Grant Contract to provide federal assistance to this project pursuant to the Housing Act of 1949, 42 U. S.C. § 1450 et seq., which allows for a contractual relationship between a local public agency, here BRA, and the United States. The availability of federal assistance had been certified in compliance with the Housing Act only after HUD review of the program established that BRA had presented a “Workable Program for Community Improvement”.

While the 1967 contract authorized BRA to sell project loan notes up to $14,488,759, a relocation grant of $719,-804 and a capital grant of $8,651,134, these sums were subsequently increased. On August 28, 1968 an amendatory contract added a rehabilitation grant of $12,000. More relevant here were an authorized increase in the amount of interest to be paid on temporary loan notes to be sold by BRA, the result of a June 24, 1970 amendment to the original contract; and an increased relocation grant to $5,660,424 and an increased [888]*888current temporary loan authorization to $19,441,374, both the result of an August 11, 1972 amendment. Currently, approximately $1,866,000 out of an approved budget, exclusive of relocation funds, of some $13,769,000 — which includes the original federal capital grant of over eight million dollars with the remainder coming from state and local funds — remains unexpended or unencumbered. Approximately $4,675,000 of the federally-provided relocation grant is similarly at BRA’s disposal.

A survey of the state of the real estate is more understandable than a financial analysis of monies unexpended. There are 27 parcels and sub-parcels in the part of the project which is before us. From the documents in evidence, we distill the following status, which we list for further reference in groups:

Group Number of Parcels Present Status
I 4 —development wholly or nearly completed (Nos. 2, 11, 16A, 16B-1); no Injunction sought as to these parcels.
II 1 —site cleared; developer tentatively selected; planned for residence for the elderly; no Injunction sought as to parcel (No. 5). HUD will subject It to a modified environmental clearance procedure.
III 3 —site cleared; developers not selected for two parcels (Nos. 6, 16B — 2); selected for the other (No. 3). As to this site HUD will submit It to a modified clearance procedure. No. 6 has no final planned purpose (except that It Is to be part residential and part commercial); No. 16B-2 Is planned for a park; No. 3 Is planned for middle income housing with HUD financing.
IV 5 —sites where no demolition has yet occurred (Nos. 7, 9, 12, 13, 15 2). Nos. 7 and 15 are tentatively planned to be rehabilitated. Nos. 9, 12, and 13 are planned for low and middle Income housing, with HUD financing for at least Nos. 9 and 13.
V 14 —no plans for acquisition or use (Nos. 1, 4, 8, 10, 14, ' 17, 18, 19, 19A, 19B, 20, 21, 22, 23).

It is apparent that the parcels in groups IV and V and some or all of those in group III, a total of from 19 to 22 of the project’s 27 parcels, fall in the early stages of planning. Nevertheless, the entire project has been in the planning stage for some seven years and has been subject to numerous hearings and deliberations at various levels.

II. General Applicability of NEPA to Previously Planned Projects.

It is against this factual background that we endeavor to assess whether NEPA, enacted subsequent to the basic Loan and Capital Grant Contract, can be the source of any present obligation. We do not start with tabula rasa. The slate has been written on for some years. The question is whether there is at this time any requirement for a NEPA environmental statement — not the unrestricted analysis that might otherwise be expected if the project had not yet been launched, but a statement taking as a given those things which have been done in reliance on a preexisting plan.

We dispose without difficulty of appellees’ contention that Congress intended to exempt from the application of NEPA pertinent projects simply because they had been previously decided upon. An environmental disturbance is no less consequential because of the date of its planning. If appellees are correct, the federal government is in a position [889]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fund for Animals v. Mainella
283 F. Supp. 2d 418 (D. Massachusetts, 2003)
Robert Conran v. State
Court of Appeals of Texas, 1997
Strahan v. Linnon
967 F. Supp. 581 (D. Massachusetts, 1997)
Zarrilli v. Weld
875 F. Supp. 68 (D. Massachusetts, 1995)
Puerto Rico Conservation Foundation v. Larson
797 F. Supp. 1074 (D. Puerto Rico, 1992)
Stop 3 Association v. Dole
870 F.2d 1419 (Ninth Circuit, 1989)
Save Our Dunes v. Pegues
642 F. Supp. 393 (M.D. Alabama, 1985)
Township Of Springfield v. Drew Lewis
702 F.2d 426 (Third Circuit, 1983)
Weinberger v. Romero-Barcelo
456 U.S. 305 (Supreme Court, 1982)
Pacific Legal Foundation v. Cecil B. Andrus
657 F.2d 829 (Sixth Circuit, 1981)
Carlos Romero-Barcelo, Etc. v. Harold Brown
643 F.2d 835 (First Circuit, 1981)
Aertsen v. Landrieu
488 F. Supp. 314 (D. Massachusetts, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
477 F.2d 885, 3 Envtl. L. Rep. (Envtl. Law Inst.) 20358, 5 ERC (BNA) 1169, 1973 U.S. App. LEXIS 10941, 5 ERC 1169, Counsel Stack Legal Research, https://law.counselstack.com/opinion/benjamin-jones-v-james-t-lynn-ca1-1973.