City of New Braunfels v. Carowest Land, Ltd.

549 S.W.3d 163
CourtCourt of Appeals of Texas
DecidedJune 29, 2017
DocketNO. 03-16-00249-CV
StatusPublished
Cited by20 cases

This text of 549 S.W.3d 163 (City of New Braunfels v. Carowest Land, Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of New Braunfels v. Carowest Land, Ltd., 549 S.W.3d 163 (Tex. Ct. App. 2017).

Opinion

Melissa Goodwin, Justice

The City of New Braunfels and Y.C. Partners, Ltd., d/b/a Yantis Company appeal from the trial court's declaratory judgment in favor of Carowest Land, Ltd., that included a declaration that a contract between the City and Yantis was void and an award of attorney's fees, costs, and expenses against the City and Yantis jointly and severally. For the following reasons, we vacate the trial court's judgment for lack of subject matter jurisdiction and remand the case to the trial court for further proceedings consistent with this opinion.

BACKGROUND

This case is among a series of cases between Carowest, the City, and Yantis.

*167Because the relevant facts that form the basis of Carowest's claims were recited in a prior opinion issued by this Court, we do not recite them here except to the extent necessary to describe the relevant background. See Tex. R. App. P. 47.1 ; see generally City of New Braunfels v. Carowest Land, Ltd. , 432 S.W.3d 501 (Tex. App.-Austin 2014, no pet.) ( Carowest I ).

The heart of the parties' dispute in this case concerns a rule 11 agreement between the City and Yantis that was filed in the 2010 lawsuit brought by Carowest against the City and Yantis as to the South Tributary flood-control project (STP). See Carowest I , 432 S.W.3d at 535 n.131. Counsel for the City and Yantis discussed and signed the rule 11 agreement on behalf of their clients during the day of May 9, 2011, the same day that the city council held its meeting in the evening in which it approved Yantis as the contractor for the North Tributary flood-control project. In the rule 11 agreement, Yantis agreed "to fully release the City of New Braunfels from Yantis' asserted delay claim on the South Tributary project if, after all proper and legal process is completed, Yantis is awarded the North Tributary contract (with alternate three) by the City of New Braunfels at the New Braunfels' City Council meeting scheduled for this evening." Alternate three was for the optional work of delivering a specified quantity of excavated land (fill) from the project to Carowest. The rule 11 agreement further provided: "If the contract is not awarded to Yantis this evening, this offer is hereby withdrawn." Yantis, the contractor on the STP, had submitted a sealed bid on April 29, 2011, seeking to be the contractor on the North Tributary project.

The agenda for the May 9, 2011, city council meeting included notice that the city council would discuss and consider the "approval of a contract with Yantis Company for construction services on the North Tributary Regional Flood Control Project." Immediately prior to consideration of the award of the North Tributary Contract during the city council meeting, the city council went into a closed meeting without announcing the basis for doing so. See Tex. Gov't Code § 551.101 (requiring announcement that closed meeting will be held and identification of "section or sections of this chapter under which the closed meeting is held").

After the closed meeting concluded and the open session was reconvened, the mayor began by stating that the "Executive Session caption under which we went under" was to "Item C, deliberate pending/contemplated litigation, settlement offers, and matters concerning privileged and unprivileged client information." See id. § 551.071(1) (authorizing closed meeting to consult with attorney about "pending or contemplated litigation" or "settlement offer"). The city council then discussed the award of the North Tributary Contract to Yantis without reference to the rule 11 agreement. The city engineer presented the bids that the City received on April 29, 2011, the range of those bids, and the time line for the project, and advised the city council that Yantis submitted the lowest bid with the recommended alternates. The city council members then discussed the bids for the North Tributary Contract and Yantis's bid in relation to actual cost and quality of work on the completed STP. Following this discussion, the city council voted to award the North Tributary Contract to Yantis with one city council member voting against the award.

The City provided a copy of the rule 11 agreement to Carowest the day after the city council's meeting. Carowest thereafter filed amended pleadings in the 2010 lawsuit, *168asserting claims under the Uniform Declaratory Judgments Act (UDJA), see Tex. Civ. Prac. & Rem. Code §§ 37.001B.011, including seeking declarations that the North Tributary Contract was void based on the City's alleged violations of the Texas Open Meetings Act (TOMA), see Tex. Gov't Code §§ 551.001 -.146, and competitive bidding requirements in the Texas Local Government Code, see Tex. Loc. Gov't Code § 252.043(a) (requiring contract to be awarded to "lowest responsible bidder"). Carowest asserted its standing to complain about the North Tributary Contract based on its status as a "property tax paying resident," see id. § 252.061(a), and a third party beneficiary of the North Tributary Contract. Carowest urged it was a third party beneficiary of the contract because the City had agreed to provide it with fill from the North Tributary project. The parties thereafter agreed to sever Carowest's UDJA claims related to the City's alleged TOMA violations and the validity and legality of the North Tributary Contract into a new cause number that is the subject of this appeal.

The jury trial in the severed case occurred in October 2015. The trial court granted a directed verdict on Carowest's declaratory judgment claim "related to the City's improper TOMA procedure," see Tex. Gov't Code § 551.101, and submitted other claims of Carowest to the jury. The jury found that:

• In awarding the North Tributary Contract to Yantis, the City "fail[ed] to award the contract to the lowest responsible bidder."
• In awarding the North Tributary Contract to Yantis, the City "fail[ed] to provide all bidders with the opportunity to bid on the same items on equal terms and have bids judged according to the same standards as set forth in the specifications."
• The City "allow[ed] Yantis to submit additional consideration for its bid for the North Tributary Contract after April 29, 2011 at 10:00 a.m."
• Yantis "provide[d] a release of the Delay Claims to the City in exchange for the City Council's vote to award it the North Tributary Contract on May 9, 2011."
• The City "consider[ed] the Rule 11 Agreement when judging Yantis'[s] bid for the North Tributary Project."

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marlonia Ivy v. Victor Garcia and Wanda Garcia
Court of Appeals of Texas, 2022
Rebecca Amador v. the City of Irving, Texas
Court of Appeals of Texas, 2020
Tarrant County, Texas v. Jeffrey D. Lerner
Court of Appeals of Texas, 2020
Town of Shady Shores v. Sarah Swanson
Texas Supreme Court, 2019
Schmitz v. Denton Cnty. Cowboy Church
550 S.W.3d 342 (Court of Appeals of Texas, 2018)
Craig v. Tejas Promotions, LLC
550 S.W.3d 287 (Court of Appeals of Texas, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
549 S.W.3d 163, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-new-braunfels-v-carowest-land-ltd-texapp-2017.