City of New Braunfels, Texas And YC Partners Ltd., D/B/A Yantis Company v. Carowest Land, Ltd.

578 S.W.3d 668
Court of Appeals of Texas·Decided May 16, 2019·No. 03-17-00696-CV·Published·Cited by 3 cases

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN

NO. 03-17-00696-CV

City of New Braunfels, Texas; and YC Partners Ltd., d/b/a Yantis Company, Appellants

v.

Carowest Land, Ltd., Appellee

FROM THE 22ND DISTRICT COURT OF COMAL COUNTY NO. C2017-0474A THE HONORABLE MARGARET G. MIRABAL, JUDGE PRESIDING

OPINION

The City of New Braunfels and YC Partners, Ltd., d/b/a Yantis Company appeal

district court orders denying each of their pleas to the jurisdiction asserted in a suit brought

against them by local property owner Carowest Land, Ltd. See Tex. Civ. Prac. & Rem. Code

§ 51.014(a)(8) (permitting interlocutory appeal of an order granting or denying a plea to the

jurisdiction). We will reverse the district court’s order denying the City’s plea to the jurisdiction

and will dismiss Yantis’s appeal.

This is the third appeal this Court has been called on to resolve in an ongoing

dispute among the City, Yantis, and Carowest. As a result, much of the background of this

controversy has been discussed in two earlier opinions, City of New Braunfels v. Carowest Land,

Ltd., 432 S.W.3d 501 (Tex. App.—Austin 2014, no pet.) (Carowest I), and City of New

Braunfels v. Carowest Land, Ltd., 549 S.W.3d 163 (Tex. App.—Austin 2017, pet. filed) (Carowest II). See also Carowest Land, Ltd. v. Y.C. Partners, Ltd., No. 03-11-00715-CV, 2012

Tex. App. LEXIS 3598 (Tex. App.—Austin, May 1, 2012, no pet.) (mem. op.) (granting

appellant Carowest’s unopposed motion to dismiss appeal); City of New Braunfels v. Carowest

Land, Ltd., No. 03-11-00211-CV, 2011 Tex. App. LEXIS 5039 (Tex. App.—Austin,

July 1, 2011, no pet.) (mem. op.) (granting appellant City’s unopposed motion to dismiss

appeal). In this latest appeal, the issue is whether the district court has subject-matter jurisdiction

to adjudicate the merits of a claim by Carowest seeking a declaratory judgment and attorney’s

fees as allowed by the Uniform Declaratory Judgments Act (UDJA). See Tex. Civ. Prac. &

Rem. Code §§ 37.004, .009. Accordingly, we take as true the facts alleged by Carowest in its

live pleadings or for which it has presented evidence except to the extent the City has presented

evidence sufficient to negate those facts. See, e.g., Texas Dep’t of Parks & Wildlife v. Miranda,

133 S.W.3d 217, 226 (Tex. 2004).

Carowest’s dispute with the City and Yantis

Carowest owns a 240-acre property in New Braunfels, a portion of which

Carowest voluntarily conveyed to the City to allow for construction of a drainage channel. The

City hired Yantis to construct the drainage channel. This project came to be called the South

Tributary Project, and it did not go smoothly. See Carowest I, 432 S.W.3d 507-12 (detailing the

facts of the underlying dispute). Eventually, in July of 2009, the City and Carowest entered into

a Letter Agreement in an attempt to “resolve issues related to the South Tributary Project.” The

Letter Agreement allowed Carowest to modify the location and design of the channel (the

Modification) in exchange for Carowest paying for certain costs related to the Modification.

Under the Letter Agreement, Carowest would receive all fill from the South Tributary Project.

2 The parties also agreed to work in good faith to complete the South Tributary Project, they

agreed Carowest would convey land to the City for certain other projects, and they agreed that

Carowest would receive 13,944 cubic yards of fill from another project—the North Tributary

Project—to compensate for the fill the City took from the South Tributary Project that was

supposed to have been given to Carowest. The City also hired Yantis as the contractor on the

North Tributary Project. The Letter Agreement also contained an indemnity clause under which

Carowest agreed:

to indemnify the City and hold the City harmless for any claims brought by The Yantis Company for any Modification Costs incurred by Yantis, such as delay costs, claimed by Yantis and directly attributable to the Modification (the “Yantis Claims”). Any invoices related to these Yantis Claims submitted to the City shall be promptly provided to Carowest. If either party disputes any claim, the claim shall be submitted to Halff and Pape-Dawson . . . .

Among the many continuing points of contention between the parties, Yantis ended up

submitting to the City a delay claim for $556,248 for work Yantis attributed to the Modification

on the South Tributary Project. Pursuant to the Letter Agreement’s indemnity provision, the City

submitted the claim to Carowest, and on May 13, 2010, the City directed Carowest “to negotiate

with Yantis and work out a payment, if any, for delay damages and obtain a release for the

benefit of the City.” However, in October 2009, unbeknownst to Carowest, the City and Yantis

had executed a change order containing language that Carowest says had already released all of

Yantis’s claims against the City for the Carowest portion of the South Tributary Project. In

addition, on May 31, 2010, Yantis applied to the City for a progress payment for Yantis’s work

on the South Tributary Project. As a condition of receiving that payment, Yantis executed a

“Partial Waiver and Release of Lien,” which stated, “Yantis hereby acknowledges complete

3 satisfaction of, and waives and releases, any and all claims of every kind against [the City], the

[South Tributary] Project and the property.” Despite these releases, Yantis resubmitted its delay

claim to the City in July 2010, this time seeking $276,270.80 in damages related to the Carowest

portion of the South Tributary Project. In October 2010, the City sent a letter to Yantis

containing the City’s “written response to Yantis’ delay claim against the City.” The letter stated

that “based on the execution of [the October 2009 change order], Yantis has waived ‘any and all

costs associated with or resulting from the change(s) ordered herein, including all impact, delays,

and acceleration costs’.” (Emphasis and punctuation in original.) Because Yantis did not

abandon its delay claim and the City did not rescind its request that Carowest handle Yantis’s

delay claim, Carowest sued Yantis and the City in November 2010. During the course of the

ongoing lawsuit, Carowest asserted multiple causes of action, including three sets of declaratory

claims. The City asserted counterclaims, including a breach-of-contract claim seeking monetary

damages for alleged breach of the Letter Agreement by Carowest. The City filed a plea to the

jurisdiction, asserting that Carowest’s claims were barred by sovereign immunity. The trial court

denied that plea and the City appealed. This Court resolved that interlocutory appeal in 2014 in

Carowest I, which is further discussed below. In 2015, the parties agreed to sever two of

Carowest’s three sets of declaratory judgment claims, which related to the North Tributary

Project, into a separate suit. The suit on the North Tributary Project declaratory claims

eventually formed the basis for Carowest II. The remaining set of declaratory judgment claims

related to the validity of Yantis’s delay claim and the parties’ corresponding obligations under

Free access — add to your briefcase to read the full text and ask questions with AI

City of New Braunfels, Texas And YC Partners Ltd., D/B/A Yantis Company v. Carowest Land, Ltd., 578 S.W.3d 668 (Tex. Ct. App. 2019).

578 S.W.3d 668 (City of New Braunfels, Texas And YC Partners Ltd., D/B/A Yantis Company v. Carowest Land, Ltd.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related