CDM Constructors, Inc.

Armed Services Board of Contract Appeals·Decided October 24, 2018·No. ASBCA No. 60454, 60455, 60669·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) CDM Constructors, Inc. ) ASBCA Nos. 60454, 60455, 60669 ) Under Contract No. W912PL-12-C-0022 )

APPEARANCES FOR THE APPELLANT: Bret S. Wacker, Esq. Jeffrey M. Gallant, Esq. Emily J. Baldwin, Esq. Clark Hill PLC Detroit, MI

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney John F. Bazan, Esq. Gilbert H. Chong, Esq. Brian M. Choe, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Los Angeles

OPINION BY ADMINISTRATIVE JUDGE SWEET

Appellant CDM Constructors, Inc. (CDM) 1 appeals the decision of the contracting officer (CO) denying its request for an equitable adjustment (REA), and the deemed denial of an REA. All three appeals concern the design and construction of a water treatment plant (WTP). 2

ASBCA No. 60454 addresses the WTP's evaporation ponds (EPs), alleging that CDM is entitled to an equitable adjustment and delay damages. In particular, CDM alleges that the Army Corps of Engineers (Corps) constructively changed the contract by compelling it to include one backup EP, to use a three million gallon per day (mgd) average daily flow (ADF), and to use a 0.8 pan evaporation coefficient only if the maximum water depth was three feet or less. (App. br. at 44-53)3 The Corps argues

1 CDM Constructors, Inc. 's parent company was CDM Smith. CDM Smith was responsible for design, and CDM Constructors, Inc. was responsible for construction (tr. 1/38). We refer to CDM Constructors, Inc. and CDM Smith collectively as "CDM." 2 This decision only addresses entitlement. 3 The ASBCA No. 60454 complaint also alleges that there was a cardinal change, defective specifications, and breach of a covenant of good faith and fair dealing

I that the contract required those design elements (gov't br. at 22-24 ). For the reasons discussed below, the Corps is correct about the backup EP, but not the ADF, evaporation coefficient, and water depth. Therefore, CDM is entitled to an equitable adjustment for any increased costs incurred as a result of having to use the Corps' ADF, evaporation coefficient, and water depth, but not as a result of having to provide a backup EP.

ASBCA Nos. 60455 and 60669 address the standby generator (generator), alleging that CDM is entitled to an equitable adjustment under the Changes clause because the contract contained defective specifications. 4 In particular, CDM alleges that the Corps improperly rejected its design, which followed concept drawings in the contract. (App. br. at 53-58) The Corps responds that the contract did not require CDM to follow the concept drawings, which, in any event, were trumped by conflicting contract provisions. For the reasons discussed below, CDM is correct. Thus, CDM is entitled to an equitable adjustment for any increased costs incurred as a result of the defective specifications.

FINDINGS OF FACT

I. Facts Common to All Appeals

1. On May 24, 2012, the Corps issued Request for Proposal No. W912PL-12-R-0018 (0018 RFP), for the design and construction of a WTP at Fort Irwin, California (R4, tab 9; tr. 1/43, 4/126).

2. Under the 0018 RFP, it was CDM's responsibility to "design and construct the [WTP] as described in the Request For Proposal (RFP) Documents contained herein" (R4, tab 9 at 1, 729). 5 The RFP documents:

(60454, compl. ,r,r 53-66). However, CDM abandoned those allegations by failing to raise them in its post-hearing brief. United Launch Services, LLC, ASBCA No. 56850 et al., 16-1 BCA ,r 36,483 at 177,765 (failure to address allegations from pleadings in post-hearing brief equated to abandonment of the issue). 4 The ASBCA Nos. 60455, 60669 complaint also alleges that there was a non-disclosure of superior knowledge, mutual mistake, and breach of the covenant of good faith and fai,r dealing (60455, 60669, compl. ,r,r 41-63). However, CDM abandoned those allegations by failing to raise them in its post-hearing brief. United Launch, 16-1 BCA ,r 36,483 at 177,765. 5 Citations to the Rule 4 files are to the consecutively-numbered pages unless otherwise indicated.

2 1

[D]escribe[] the design work that shall not be changed, and shall be included in the construction documents. All remaining design work shall be performed by the Contractor based on the design criteria as required by the RFP. No deviations from the criteria will be allowed unless prior approval is obtained from the Contracting Officer's Representative.

(Id. at 1, 731-32) In particular, "General Design Requirements are contained in [section 01 10 10], with Specific Design Requirements .. .identified in" appendix A (id. at 1,729). Section O1 10 10 described "the requirements for appearance, function, materials, and types of construction in sufficient detail to enable engineering and design to be completed by the Contractor" (id. at 1,731). Appendix A "is intended to guide the completion of the design by establishing existing conditions, and desired character, appearance, and function of the new construction" (id. at 1,730). Thus, section 01 10 10 and appendix A "shall define the design and performance criteria" (id. at 1,732).

3. Appendix X contained for information only (FIO) concept drawings from CH2M Hill Constructors, Inc. (CH2M Hill)6 and Southern California Edison (SCE)7 (R4, tab 9 at 1,731, 6,679, 7,113), and stated:

Information in appendices below [including appendix X] that are noted for information only (FIO) represent studies, analyses, and designs previously developed for this project. This information is made available to the contractor for its use without any warranty of usefulness or suitability of purpose.... Drawings and designs included in FIO appendices shall NOT be considered "Drawings of Record" or "For Construction". As the designer of record, all design requirements are the responsibility of the contractor.

(Id. at 1,730) Similarly, appendix A stated that:

The concept drawings of Appendix A and this specification section indicate processes required by the DD1391 as well [as] additional requirements. These concept drawings indicate estimated relationships and approximate sizes of individual components for the treatment facility. Drawings have been provided for

6 CH2M Hill was the privatized water operator for Fort Irwin (tr. 1/47). 7 SCE was the electrical utility serving parts of Southern California, including Fort Irwin (tr. 2/10).

3 information only (FIO) from a 2009 partial design by CH2M HILL Constructors, Inc. of the process required that was based on a Design/Build/Operate business process. See Appendix X. The design and FIO drawings provided do not meet the full requirements of this solicitation. The actual sizing of the tanks, pumps, piping, buildings, etc. shall be determined by the Contractor during his design.

(R4, tab 10 at 9,773)

4. Section 01 10 10 stated that "[t]he drawings and details provided by SCE shall be utilized for pricing of this effort" (R4, tab 9 at 1,785).

5. Section 01 10 10 also contained the following Order of Precedence clause:

Where the various elements of the RFP are in conflict, the following priority shall be used to establish precedence, unless specifically noted otherwise: a. Appendices A - I and Technical Specifications, where furnished. b. Section 01 10 10 DESIGN REQUIREMENTS, GENERAL. c. Drawings.

(R4, tab 9 at 1,732)

6. On August 8, 2012, the Corps awarded Contract No. W912PL-12-C-0022 (0022 contract) to CDM based upon the 0018 RFP (R4, tab 7).

7.

Free access — add to your briefcase to read the full text and ask questions with AI

CDM Constructors, Inc., (asbca 2018).

CDM Constructors, Inc. (CDM Constructors, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Savantage Financial Services, Inc. v. United States
595 F.3d 1282 (Federal Circuit, 2010)
Hol-Gar Manufacturing Corp. v. The United States
351 F.2d 972 (Court of Claims, 1965)
Coast Federal Bank, Fsb v. United States
323 F.3d 1035 (Federal Circuit, 2003)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
McCormick-Selph v. United States
588 F.2d 808 (Court of Claims, 1978)