CDM Constructors Inc.

CourtArmed Services Board of Contract Appeals
DecidedOctober 29, 2020
DocketASBCA No. 62026, 62088, 62089
StatusPublished

This text of CDM Constructors Inc. (CDM Constructors Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CDM Constructors Inc., (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) CDM Constructors Inc. ) ASBCA Nos. 62026, 62088, 62089 ) Under Contract No. W912PL-12-C-0022 )

APPEARANCES FOR THE APPELLANT: Bret S. Wacker, Esq. Emily J. Baldwin, Esq. Jeffrey M. Gallant, Esq. Clark Hill PLC Detroit MI

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney John F. Bazan, Esq. Gilbert H. Chong, Esq. Brian M. Choc, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Los Angeles

OPINION BY ADMINISTRATIVE JUDGE SWEET

These quantum appeals relate to our entitlement decision in CDM Constructors, Inc., ASBCA No. 60454 et al., 18-1 BCA ¶ 37,190 (CDM I). In CDM I, we held that the Army Corps of Engineers (Corps) constructively changed a contract to design and build a water treatment plant (WTP) at Fort Irwin, California when it compelled appellant CDM Constructors, Inc. (CDM) to size the WTP’s evaporation ponds (EPs) using a three million gallon per day (mgd) average daily flow (ADF), and a 0.8 pan evaporation coefficient only if the maximum depth was three feet or less (collectively, EP changes). Id. at 181,013-14. However, we held that the Corps did not constructively change the contract when it compelled CDM to provide a standby EP. Id. at 181,012-13. In CDM I, we also held that the Corps provided defective specifications regarding a standby generator. Id. at 181,014-15. Finally, we returned the appeals to the parties for a determination of quantum. Id. at 181,016.

After the parties proved unable to resolve the issue of quantum, CDM filed these quantum appeals. 1 In these appeals, CDM attempts to calculate its equitable adjustment for the EP changes by using the revised 100 percent design to establish the reasonable costs of

1 ASBCA No. 62026 addresses the EPs. ASBCA Nos. 62088 and 62089 address the generator. performing the contract’s requirements without the EP changes. However, that attempt fails because CDM has not met its burden of showing that the revised 100 percent design complied with all of the contract’s requirements—particularly its standby EP requirement.

Regarding the generator, the parties stipulate that CDM is entitled to a $318,684.46 equitable adjustment for the defective generator specifications. Moreover, CDM has met its burden of showing that it is entitled to an additional $7,367.54 for its increased general conditions costs due to the increased complexity caused by the defective generator specifications. Therefore, CDM is entitled to an equitable adjustment of $326,052 for the defective generator specifications.

FINDINGS OF FACT

1. On August 8, 2012, the Corps awarded Contract No. W912PL-12-C-0022 (0022 Contract) to CDM for the design and construction of a WTP at Fort Irwin, California. CDM I, 18-1 BCA ¶ 37,190 at 181,005.2

I. Facts Unique to the Evaporation Ponds Appeal (ASBCA No. 62026)

A. Contract Requirements

2. The 0022 Contract did not require CDM to use any particular ADF, or any particular evaporation coefficient for any particular water depth. CDM I, 18-1 BCA ¶ 37,190 at 181,008.

3. However, the 0022 Contract required CDM to provide “2 + 1 STANDBY” EPs. Id. at 181,007. A standby EP is an EP that is operational, but, for an indefinite time period, need not be used to prevent operational overflows—i.e., inflows exceeding net evaporation—except in an emergency. Id. at 181,007-08, 181,017 n.12; see also (app. post-hearing br. at 37; app. post-hearing reply at 17-18). While the Corps concedes that a standby EP may be used while cleaning in-service EPs, it may not be used to prevent operational overflows (tr. 2/132-33, 2/136; app. supp. R4, tab 2016 at 20,300; app. post-hearing br. at 37; app. post-hearing reply at 17-18). The uncontroverted evidence establishes that a reasonable time-period for cleaning EPs was about two months. Therefore, an EP that is used for about two months may qualify as a standby EP that only is being used while cleaning an in-service EP. However, an EP that is used for longer than two months does not qualify as a standby EP because that use constitutes use to prevent operational overflows. (Tr. 2/155, 2/157, 2/203; gov’t supp. R4, tab 1048 at 2,753-56)

2 CDM I presents the facts in greater detail, and we presume familiarity with CDM I. 2 B. Relevant Design

4. After the Corps rejected several EP designs, CDM submitted a revised 100 percent design and a May 17, 2013 design memorandum (collectively, relevant design). CDM I, 18-1 BCA ¶ 37,190 at 181,009. It is undisputed that the relevant design used a 2.25 mgd ADF, used a 0.8 evaporation coefficient for a water depth greater than three feet, and had three EPs. Id. at 181,009. Rather, the central dispute in ASBCA No. 62026 is whether one of those EPs was a standby EP (app. post-hearing br. at 4; gov’t post-hearing br. at 27).

5. In an attempt to show that the relevant design lacked a standby EP, the Corps presented testimony from Antonia Ortiz—the Corps’ project engineer and an expert in the sizing of ponds for outflows to balance inflows (tr. 2/119). In an attempt to show that the relevant design included a standby EP, CDM presented testimony from William B. O’Neil—CDM’s designer of record, and an EP expert (tr. 1/109-10; app. witness list (Feb. 5, 2020); gov’t objections to app.’s evidence (Feb. 12, 2020)).

6. Ms. Ortiz, Mr. O’Neil, and Dr. Beth Gross—CDM’s EP expert at the entitlement hearing—agreed that the determination of whether a design includes a standby EP should start with a water balance analysis, which estimates whether net evaporation balances inflows (gov’t supp. R4, tab 1001 at 10-11, tab 1003 at 33-35; app. supp. R4, tab 2018a at 20,550-51; ASBCA No. 60454 app. supp. R4, tab 59 at 183; tr. 2/164-65, 2/172, 3/35-36).3 Mr. O’Neil asserted that additional modeling should be performed (CDM’s Model) to provide a more accurate determination of whether net evaporation balances inflows (gov’t supp. R4, tab 1001 at 10-11; tr. 3/35-36).

1. Water Balance Analysis

7. Ms. Ortiz, Mr. O’Neil, and Dr. Beth Gross all agree that the basic equation to calculate the average surface area required for net evaporation to balance inflows (required surface area) under a water balance analysis is to divide the average inflows by the average net evaporation rate (gov’t supp. R4, tab 1003 at 33; app. supp. R4, tab 2018a at 20,550; ASBCA No. 60454 app. supp. R4, tab 59 at 183). Using that equation, both Ms. Ortiz and Mr. O’Neil agree that the relevant design’s required surface area was greater than the available surface area of its two in-service EPs at their maximum five-foot depth (app. supp. R4, tab 2018a at 20,550-51; see also tr. 2/172, 3/84).4

3 Unless otherwise indicated, all citations to the R4 files are to the R4 files in the quantum appeals. Citations to the R4 files in the entitlement appeals start with “ASBCA No. 60454.” 4 Ms. Ortiz and Mr. O’Neil calculate slightly different required surface areas of

4.7 acres and 4.48 acres respectively based upon different treatment of 3 8. As CDM’s own expert Dr. Gross opined at the entitlement phase, the required surface area is an average, and “the ponds are not continuously operated at maximum or greater depths to provide the required pond surface area” (ASBCA No. 60454 app. supp. R4, tab 59 at 183; see also tr. 2/172-73). Ms. Ortiz agreed that “there’s no way the maximum can be the average depth because you can’t exceed the maximum depth” (tr. 3/84). Therefore—as Dr. Gross conceded in addressing a different design and as Ms.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Becton Dickinson and Company v. C.R. Bard, Inc.
922 F.2d 792 (Federal Circuit, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
CDM Constructors Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/cdm-constructors-inc-asbca-2020.