CDM Constructors Inc.

CourtArmed Services Board of Contract Appeals
DecidedApril 7, 2021
DocketASBCA No. 62026, 62088, 62089
StatusPublished

This text of CDM Constructors Inc. (CDM Constructors Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CDM Constructors Inc., (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of - ) ) CDM Constructors Inc. ) ASBCA Nos. 62026, 62088, 62089 ) Under Contract No. W912PL-12-C-0022 )

APPEARANCES FOR THE APPELLANT: Bret S. Wacker, Esq. Emily J. Baldwin, Esq. Jeffrey M. Gallant, Esq. Clark Hill PLC Detroit, MI

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney John F. Bazan, Esq. Gilbert H. Chong, Esq. Brian M. Choc, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Los Angeles

OPINION BY ADMINISTRATIVE JUDGE SWEET

On December 3, 2020, appellant CDM Constructors, Inc. (CDM) moved for reconsideration (motion) of our decision on quantum in CDM Constructors, Inc., ASBCA No. 62026 et al., 20-1 BCA ¶ 37,721 (CDM II). In CDM Constructors, Inc., ASBCA No. 60454 et al., 18-1 BCA ¶ 37,190 at 181,013 (CDM I)—the entitlement decision—we held that, even though the Army Corps of Engineers had constructively changed the contract by imposing certain requirements related to evaporation ponds (EPs), the government did not constructively change the contract when it required CDM to include a standby EP. Moreover, as discussed in far greater detail in CDM II (with which we presume the reader is familiar), we held in CDM II that CDM had failed to prove quantum because it did not show that its revised 100 percent design— which CDM sought to use as a baseline with which to compare the contractual change—did not include a standby EP. Below, we find that the arguments CDM brings to this motion for reconsideration have been waived, and thus are not appropriate bases for reconsideration, because CDM did not raise those arguments in the initial quantum appeal. In any event, those arguments are meritless. Therefore, we deny the motion. I. CDM Waived the Arguments that it Raises in its Motion, and Those Arguments are not Appropriate Bases for Reconsideration

CDM waived the arguments that it raises in its motion, and thus those arguments are not appropriate bases for reconsideration. Motions for reconsideration are only appropriate if they are based upon newly discovered evidence, mistakes in the findings of fact, or errors of law. Green Valley Co., ASBCA No. 61275, 18-1 BCA ¶ 37,044 at 180,330. “Motions for reconsideration do not afford litigants the opportunity to take a ‘second bite at the apple’ or to advance arguments that properly should have been presented in an earlier proceeding.” Dixon v. Shinseki, 741 F.3d 1367, 1378 (Fed. Cir. 2014) (citations and quotations omitted). As a result, in our discretion, we may find that arguments not raised in an opening post-hearing brief have been waived. Becton Dickinson & Co. v. C.R. Bard, Inc., 922 F.2d 792, 800 (Fed. Cir. 1990).

Here, while CDM’s motion for reconsideration is not entirely clear, we understand CDM’s primary arguments 1 to be that: (1) the Board should not rely upon the water balance analysis because it merely provided an estimate (mot. at 9-15); (2) we should pro-rate CDM’s costs (id. at 28-30); (3) the relevant design did not need the purported standby EP to prevent operational overflows (id. at 27-28); (4) the original operating scenario did not use the purported standby EP to prevent operational overflows, and merely diverted flow to the purported standby EP while cleaning an in-service EP (id. at 30-33); (5) under res judicata or the law of the case doctrine, CDM I precludes a finding that two months was a reasonable time to clean an EP (id. at 21-27); (6) the testimony of CDM’s quantum EP expert (William B. O’Neil) established that the alternative operating scenario showed that the relevant design included a standby EP (id. at 18-21, 33-37); (7) CDM’s request for equitable adjustment (REA) did not concede that the relevant design needed to use the purported standby EP to prevent operational overflows (id. at 37-39); and (8) our qualifying the Corps’s quantum expert (Antonia Ortiz) as an expert caused unfair surprise and undue prejudice (id. at 15-18). Because CDM already had the opportunity to—and properly should have—advanced those arguments earlier, CDM merely seeks a second bite at the apple. Therefore, CDM waived those arguments, those arguments are not an appropriate bases for reconsideration, and we deny the motion.

1 To the extent CDM raises other minor arguments, we find that it waived those arguments, and they are meritless. 2 II. CDM’s Arguments are Meritless

In the alternative, we deny the motion because CDM’s arguments are meritless.

A. Water Balance Analysis

1. CDM’s Argument that the Board Should not Reply Upon the Water Balance Analysis is Meritless

CDM’s argument that the Board should not rely upon the water balance analysis because it merely provided an estimate is meritless (mot. at 9-15). As CDM II properly held, while the water balance analysis is only an estimate, that analysis is a relevant and reliable method for determining if a design includes a standby EP2—i.e., if it is necessary to use a purported standby EP for net evaporation to balance inflows—because Ms. Ortiz, Mr. O’Neil, and CDM’s entitlement EP expert (Dr. Beth Gross) all agreed that the determination of whether net evaporation balances inflows should start with a water balance analysis (finding ¶ 6). Indeed, CDM’s continued attempts to minimize the usefulness of the water balance analysis in determining if net evaporation balances inflows is not persuasive in light of the fact that its entitlement EP expert relied upon a water balance analysis for that precise purpose (findings ¶¶ 6-8).

2. CDM’s Argument that the Board Should Pro-Rate Costs is Meritless

CDM argues, in the alternative, that we should pro-rate its costs by 1.3 percent to reflect the 1.3 percent increase in the required surface area and depth that CDM II purportedly found the water balance analysis showed was needed in the relevant design for net evaporation to balance inflows (mot. at 28-30). That argument assumes that the deficiency that CDM II found in the relevant design was that it lacked 1.3 percent standby capacity. However, as we held in CDM I, the 0022 Contract did not require standby capacity, but a standby EP. Thus, the problem with the fact that the required surface area exceeded the available surface area at the maximum depth by 1.3 percent was not that that fact showed a 1.3 percent lack of standby capacity. Rather, the problem with that fact was that it showed that the purported standby EP was not a standby EP because the relevant design—which CDM made the litigation decision to rely upon exclusively as its baseline on the assumption that it had a standby EP—needed to use the purported standby EP to prevent operational overflows. As a result, we cannot simply pro-rate costs to reflect a purported lack of standby capacity.

2 We continue to use terms as defined in CDM II. Further, all citations to “finding” are to the findings of fact in CDM II. 3 In any event, it cannot be inferred from CDM II’s finding that the required surface area was 1.3 percent greater than the available surface area at the maximum depth that the required surface area and depth only would need to have been 1.3 percent larger in order for net evaporation to balance inflows. That inference assumes that the water balance analysis would show that net evaporation would balance inflows if the required surface area equaled the available surface area at the maximum depth.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Becton Dickinson and Company v. C.R. Bard, Inc.
922 F.2d 792 (Federal Circuit, 1990)
Dixon v. Shinseki
741 F.3d 1367 (Federal Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
CDM Constructors Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/cdm-constructors-inc-asbca-2021.