Building Structures, Inc. v. Young

883 P.2d 1308, 131 Or. App. 88, 1994 Ore. App. LEXIS 1545
CourtCourt of Appeals of Oregon
DecidedOctober 26, 1994
Docket90-9-141; CA A71758
StatusPublished
Cited by10 cases

This text of 883 P.2d 1308 (Building Structures, Inc. v. Young) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Building Structures, Inc. v. Young, 883 P.2d 1308, 131 Or. App. 88, 1994 Ore. App. LEXIS 1545 (Or. Ct. App. 1994).

Opinions

[90]*90LANDAU, J.

Plaintiff Building Structures, Inc. (BSI) brought this action seeking damages arising out of the construction of a commercial structure. The claims included breach of contract, quantum meruit and fraud. A jury found for BSI on the breach of contract and fraud claims,1 and the trial court granted defendants’ motion for a new trial on the fraud claim. We reverse on BSI’s appeal and affirm on defendants’ cross-appeal.

Defendants Gary Young (Young) and Melody Young are principals of defendant Young Equipment Sales Co., Inc. (Young Equipment), a company engaged in the manufacture and sale of semi-trailer units. BSI had been in nonresidential construction for 17 years, building projects on a design-built or negotiated basis in which project specifications determined the costs. Typically, BSI consults with its customers in order to balance the design specifications against cost.

In early 1990, defendants contacted BSI regarding construction of a new building. On March 28, Young met with Larry and Jeff Smith of BSI. They discussed whether BSI’s services could be used to meet Young Equipment’s needs. The Smiths indicated that they would be interested in the project only if they could do both the design and construction. They told Young that they were only interested in negotiating, not bidding on, the project, and they explained how they would generate the cost figure. The parties signed a one-page “Agreement” which provides, in its entirety:

“The purpose of this agreement is to establish the use of Building Structures, Inc., (BSI) by Gary Young, for construction of Young Equipment and/or other related sitework to he located at Sandy, Oregon.
“Building Structures is to act as Project Manager/ General Contractor and will retain the architect and engineers and coordinate the design services and obtain all permits. At the time of actual construction, a contract based on maximum not-to-exceed costs will be negotiated. Any monies paid to BSI under this agreement will he included in the construction contract and credited to owner’s account.
[91]*91“Gary Young will compensate Building Structures based on actual cost, not including taxes, plus ten percent for general overhead, plus five percent for fee. Payments will be made on a monthly progress basis. Any applicable taxes will be paid by owner in addition to the above.”

The agreement was signed and BSI made preliminary drawings. In early May, Young and the Smiths negotiated over the price and scope of the projected construction. On June 15, BSI presented a “construction estimate printout” based on revisions and deletions from the original design. Young objected to the price of $245,126. BSI did not know that Young had been in touch with other contractors, one of whom had quoted a price of $200,000.

On May 24, at the design review meeting, Young introduced BSI as the project builders. The City of Sandy approved BSI’s design, and, after the meeting, BSI told Young that it would proceed with the construction drawings and request building permits. Young agreed. On June 25, defendants entered into a contract with another business for the construction of the building. Young told BSI about that contract after BSI personnel discovered the other builder working at the site. The completed building was substantially the same as the one designed by BSI.

BSI then brought this action, asserting that defendants had wanted BSI to perform only preliminary design work on the project and, although representing otherwise, had never intended to have BSI construct the building. Defendants admitted liability under the quantum meruit theory for the value of the design work, but denied liability for breach of contract and fraud. The jury returned a verdict for BSI on the breach of contract claim and awarded damages of $23,450. The jury also found defendants hable for fraud and returned a verdict form reading:

“What is the amount of [BSI’s] damages as a result of defendants’ fraud?
“Answer $ -0- (General Damages)
“Answer $51,550.00 (Punitive Damages)”

Neither party objected and the jury was dismissed. Judgment was entered and defendants filed timely motions for judgment notwithstanding the verdict and for a new trial [92]*92on both claims. The trial court denied the motions as to the breach of contract claim. It also denied the motion for judgment notwithstanding the verdict on the fraud claim but allowed the motion for a new trial on the fraud claim. The trial court held that, as a matter of law, the award of punitive damages was erroneous, because the jury failed to award compensatory damages. The court entered an amended judgment.2

BSI assigns error to the grant of defendants’ motion for a new trial on the fraud claim. The parties recognize that punitive damages are not recoverable in the absence of proof of actual damages. Crouter v. United Adjusters, Inc., 259 Or 348, 364, 485 P2d 1208 (1971). BSI contends, however, that the rule does not apply here, because defendants waived any objection to the verdict by failing to challenge it before the jury was discharged. BSI argues that case law shows that the aggrieved party must object to any irregularity or ambiguity of a verdict before it is received. See Fischer v. Howard, 201 Or 426, 463-64, 271 P2d 1059 (1954); Marquam Investment Corp. v. Myers, 35 Or App 23, 27, 581 P2d 545, rev den 284 Or 341 (1978). BSI contends that defendants were the aggrieved party and that a timely objection here would have allowed the jury to correct the verdict.

Defendants argue that, although generally an aggrieved party must object to a defective verdict before it is received, in this case it is plaintiff who was the aggrieved party. Accordingly, they conclude, they waived nothing when they stood mute as the jury returned the defective verdict.

The general rule, as stated in Mullins v. Rowe et ux, 222 Or 519, 524, 353 P2d 861 (1960), is:

“(1) The time to object to a defective verdict, if it is defective, is while the jury is still on hand so that the trial court can resubmit the matter with proper instructions.
“(2) An objection not taken when the verdict is returned into court is waived.
“(3) The only correct procedure to follow is to resubmit the matter to the same jury.”

[93]*93In Smith v. J. C. Penney Co., 269 Or 643, 525 P2d 1299 (1974), the Supreme Court applied that rule to facts not entirely dissimilar to those in this case. The jury returned a verdict for the plaintiff that was internally inconsistent. The defendant said nothing until after the jury was dismissed. The defendant then moved for judgment n.o.v., on the ground that the jury verdict was inconsistent, that is to say, legally insufficient. The Supreme Court said that

“if no objection is raised to a faulty verdict at the time it is returned, a party is foreclosed from subsequently attacking the verdict.” 269 Or at 653.

Similarly, in Marquam Investment Corp. v. Myers, supra, the jury returned an inconsistent verdict in favor of the plaintiff, to which the defendant entered no objection.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
883 P.2d 1308, 131 Or. App. 88, 1994 Ore. App. LEXIS 1545, Counsel Stack Legal Research, https://law.counselstack.com/opinion/building-structures-inc-v-young-orctapp-1994.