Boulder Plaza Residential, LLC v. Summit Flooring, LLC

198 P.3d 1217, 2008 Colo. App. LEXIS 619, 2008 WL 1746059
CourtColorado Court of Appeals
DecidedApril 17, 2008
Docket06CA1269
StatusPublished
Cited by19 cases

This text of 198 P.3d 1217 (Boulder Plaza Residential, LLC v. Summit Flooring, LLC) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boulder Plaza Residential, LLC v. Summit Flooring, LLC, 198 P.3d 1217, 2008 Colo. App. LEXIS 619, 2008 WL 1746059 (Colo. Ct. App. 2008).

Opinion

Opinion by

Judge J. JONES.

Plaintiff, Boulder Plaza Residential, LLC (BPR), appeals the district court's judgment in favor of defendant, Summit Flooring, LLC (Summit), on BPR's contractual indemnity claim. We affirm, and remand the case for further proceedings.

I. Background

In 2000, BPR contracted with McCrerey & Roberts Construction Company, Inc. (MeCrerey) for McCrerey to act as the general contractor on a residential condominium construction project known as One Boulder Plaza (the project). MeceCrerey subsequently entered into a subcontract with Summit for Summit to install hardwood floors in the project's residential units. The subcontract outlined the seope of Summit's obligations, and, as relevant here, included various indemnity and insurance provisions.

Shortly after Summit completed the installation of the hardwood floors, BPR's representatives noticed some cupping, disbanding, panelizing, and splitting of the floor boards. BPR notified McCrerey of the alleged de-feets, and McCrerey then contacted Summit. McCrerey and Summit attempted to repair the floors, but were largely unsuccessful.

On August 30, 2004, BPR filed a lawsuit against McCrerey, McCrerey's principal, Summit, and Summit's principal, asserting numerous causes of action arising from the alleged defective installation of the hardwood floors. Summit filed a counterclaim against BPR for payment under the subcontract, and a similar cross-claim against McCrerey. MceCrerey filed cross-claims against Summit *1219 on a variety of theories, and a counterclaim against BPR for payment under the contract.

On September 30, 2005, One Boulder Plaza Management Company, the entity responsible for managing the project's residential units, acting as an agent for 1801 Canyon Condominium Association (the homeowners association), filed a separate lawsuit against BPR, MeCrerey, McCrerey's owner, Summit, and Summit's owner seeking compensation for the same alleged defects in the hardwood floors. The homeowners association was subsequently substituted as the plaintiff. Because the second lawsuit involved essentially the same claims as the suit brought by BPR, the court consolidated the two cases.

Prior to trial, McCrerey and McCrerey's owner settled with BPR, on its own behalf and as assignee of the claims of the homeowners association. In return for a release from BPR, McCrerey agreed to pay BPR $800,000 in cash, release all other claims against BPR relating to this litigation, and assign all of its claims against Summit, Summit's owner, and Summit's liability insurance carrier to BPR.

The case was tried to a jury on three claims by BPR, namely, common law indemnity, contractual indemnity, and breach of contract; Summit's counterclaim against BPR for breach of contract; and Summit's cross-claim against McCrerey for breach of contract. The court instructed the jury that in order to find in BPR's favor on BPR's indemnity claims it would have to find, among other things, that Summit was negligent or breached the subcontract. The jury found that Summit was not negligent and did not breach the subcontract, and accordingly found in Summit's favor on all of BPR's claims. The jury found in BPR's favor on Summit's counterclaim, but found in Summit's favor on its cross-claim against McCrerey.

On appeal, BPR challenges only the judgment against it on its contractual indemnity claim.

IL Discussion

BPR's sole contention on appeal is that the district court erred in interpreting the subcontract to require a showing of fault-either negligence or breach of contract-by Summit to trigger Summit's contractual obligation to indemnify McCrerey, and in so instructing the jury. We are not persuaded.

A. Preservation of Issue for Appeal

Summit argues that BPR's appeal should be dismissed because it failed to preserve its objection to the jury instructions in the district court, and because BPR invited any error in those instructions. We disagree.

During trial, the district court heard arguments on BPR's contention that Summit had a contractual obligation to indemnify McCrerey (BPR's assignor) regardless of whether Summit was at fault. The court refrained from ruling on that issue at the time, and indicated it would do so after the jury rendered its verdict. The court then suggested that the parties prepare instructions and verdict forms for BPR's contractual indemnity claim incorporating all questions that could potentially be asked of the jury, encompassing both BPR's and Summit's theories. That way, the court explained, if it ultimately ruled that a finding of fault is required, the issue of fault would have been determined by the jury, obviating the need for further proceedings. The parties' counsel agreed to that suggestion. BPR's counsel prepared instructions that included fault by Summit (either negligence or breach of contract) as an element of the contractual indemnity claim.

Before the jury began deliberations, the court ruled against BPR and in favor of Summit on the interpretation of the contractual indemnity provisions, concluding that BPR was required to show fault on Summit's part. BPR's counsel then participated with Summit's counsel and the court in preparing verdict forms consistent with the court's ruling.

Summit argues essentially that BPR's compliance with the court's directions and ruling resulted in a failure to preserve its objection to the instructions and verdict forms. We do not agree. °

*1220 In submitting the draft instructions and verdict form, BPR did not concede that Summit's fault was an element of the contractual indemnity claim, nor did it thereby abandon its argument that Summit's fault was not required to impose liability under the indemnity provisions of the subcontract. BPR consistently maintained its position throughout the trial, and only presented instructions and a verdict form contrary to its position in response to a specific request by the court and the court's ruling on the legal issue. The court's initial decision to defer ruling on the meaning of the indemnity provisions of the subcontract until after the jury rendered its verdict left BPR with little choice but to craft its proposed instructions in the manner it did. Likewise, onee the court ruled against BPR on the issue (before the jury began deliberations), BPR had little choice but to participate in crafting verdict forms consistent with the court's ruling. Accordingly, we conclude BPR preserved its claim of error and did not invite the alleged error. See Vista Resorts, Inc. v. Goodyear Tire & Rubber Co., 117 P.3d 60, 65 (Colo.App.2004) ("The invited error doctrine prevents a party from inducing an erroneous ruling and then seeking to benefit by appealing that error.").

B. Interpretation of the Subcontract

The subcontract between Summit and McCrerey included three separate provisions containing indemnity language. Those three provisions read as follows:

Subcontractor agrees to the following:

1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peo in Interest of SS
Colorado Court of Appeals, 2026
Marriage of Makooi
Colorado Court of Appeals, 2026
Insight Surgery v. WSi Healthcare
Colorado Court of Appeals, 2025
Peo in Interest of AMI
Colorado Court of Appeals, 2025
Peo in Interest of LAB
Colorado Court of Appeals, 2025
Marriage of Wroten
Colorado Court of Appeals, 2025
Brown v. Smith
Colorado Court of Appeals, 2024
Fontanari v. Snowcap
Colorado Court of Appeals, 2024
Gold Medal v. Byers Peak
Colorado Court of Appeals, 2022
v. Burlingame
2019 COA 17 (Colorado Court of Appeals, 2019)
Rich v. Ball Ranch Partnership
2014 COA 6 (Colorado Court of Appeals, 2015)
Martin v. Essrig
277 P.3d 857 (Colorado Court of Appeals, 2011)
Bledsoe Land Co. v. Forest Oil Corp.
277 P.3d 838 (Colorado Court of Appeals, 2011)
Constable v. NORTHGLENN, LLC
248 P.3d 714 (Supreme Court of Colorado, 2011)
Lafarge North America, Inc. v. K.E.C.I. Colorado, Inc.
250 P.3d 682 (Colorado Court of Appeals, 2010)
Yeiser v. Ferrellgas, Inc.
214 P.3d 458 (Colorado Court of Appeals, 2009)
Boulder Plaza Residential, LLC v. Summit Flooring, LLC
198 P.3d 1213 (Colorado Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
198 P.3d 1217, 2008 Colo. App. LEXIS 619, 2008 WL 1746059, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boulder-plaza-residential-llc-v-summit-flooring-llc-coloctapp-2008.