Blum v. City of Hillsboro

183 N.W.2d 47, 49 Wis. 2d 667, 1971 Wisc. LEXIS 1151
CourtWisconsin Supreme Court
DecidedFebruary 2, 1971
Docket68
StatusPublished
Cited by18 cases

This text of 183 N.W.2d 47 (Blum v. City of Hillsboro) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blum v. City of Hillsboro, 183 N.W.2d 47, 49 Wis. 2d 667, 1971 Wisc. LEXIS 1151 (Wis. 1971).

Opinion

*670 Connor T. Hansen, J.

For the purposes of this appeal, it would appear from the pleadings that the parties entered into a contract to do the work on the dam and lake for $47,438.50, and that the contract was let pursuant to the provisions of sec. 62.15, Stats.

In paragraph four of the complaint, the plaintiff alleged that after acceptance of the contract, the defendant through its mayor and council members inquired whether the plaintiff would be willing to do additional lake bottom excavation at the bid price of 40¡é per cubic yard; that the plaintiff advised he was willing to do so; and that the defendant, through its mayor, city council members acting in their official capacity and through council action, outlined additional areas of the lake to be excavated, prepared a written map of the areas, and drew an amendment to the contract requiring the plaintiff to excavate the additional areas of the lake.

The complaint further alleges that the plaintiff performed all the services requested by the defendant pursuant to the contract, as modified and supplemented, and that the total amount of the services performed is $153,902.50; that defendant has made payment in the sum of $81,840, but refused to pay the balance of $72,062.50.

The defendant’s answer alleged that the services performed by the plaintiff under the contract total $47,438.50; and that it paid plaintiff $81,400, and counterclaims for $38,700, the amount paid the plaintiff in excess of the amount due under the contract.

The defendant does not deny that the procedure required by sec. 62.15, Stats., was followed with respect to the original contract, but alleges it was not followed in contracting for the extra work to be done by the. plaintiff. The issue raised on this appeal is whether a cause of action will lie against the city under theories of unjust enrichment, equitable estoppel, or promissory estoppel, for additional work done on a public works *671 contract which was not let in compliance with the statutory requirements relating to competitive bidding.

Unjust enrichment.

When sustaining the demurrer as to this alternative cause of action, the trial court correctly analyzed the law of this state. The object of statutory bidding requirements in connection with the letting of municipal contracts is to prevent fraud, collusion, favoritism, and improvidence in the administration of public business, as well as to insure that the municipality receives the best work or supplies at the most reasonable price practicable. 10 McQuillin, Mun. Corp. (1966 Rev. 3d ed.), p. 321, sec. 29.29. Thus recovery has been denied on the theory of unjust enrichment. This was because to permit recovery on principles of quasi contract would seriously impair the protection intended to be afforded by the bidding statutes.

However, there is a growing body of authority to the effect that to permit recovery on the theory of unjust enrichment would not lead to the evils once imagined. Although the majority of jurisdictions still deny quasi-contractual recovery, the trend is toward permitting recovery. It is now recognized that the limitation of a recovery under the theory of unjust enrichment to the value of the benefits conferred, while denying profits, will insure that the municipality receives the services at a reasonable price and prevent deliberate violations of the statute.

“. . . there are many well-reasoned cases permitting quasi-contract relief, and the trend of the law is clearly this way. . . .
“. . . It is suggested that quasi-contract recovery here is proper. The purpose of bid requirements is primarily to insure that municipal corporations receive goods at reasonable prices. Quasi-contractual recovery will impose upon a municipality no greater liability, and the *672 removal of profits will discourage repeated violations.” 1 Antieau, Municipal Corporation Law, pp. 755, 756, sec. 10.27.

It has also been stated that an effective remedy to protect the taxpayer has been established by the device of taxpayers’ actions to vindicate a public right; and that judicial remedies in equity are more likely to prevent injustice than delegation to the municipality of the discretionary power to pay moral claims.

“. . . At the time the first decisions precluding quasi-contractual recovery in these cases were handed down, taxpayers’ actions to vindicate a public right were practically unknown, and no injunctive remedy was available to an individual unless his own special rights were or would be injuriously affected. The jurisdiction of courts of equity to grant injunctive relief in such cases, which has been extended either by judicial decision, or by statute, has created an effective machinery to protect the taxpayer. Where these equitable remedies have been supplemented by a proper administrative control over local finances, there would seem to be no reason why a municipal corporation should not be held to respond upon principles of quasi-contract for services rendered or materials furnished under invalid contracts intra vires the corporation. Such a judicial remedy to prevent injustice would be far superior to the common recourse to statutory validation, or to a delegation to the local legislative body of the discretionary power to pay ‘moral claims.’ ” Tooke, Quasi-Contractual Liability Of Municipal Corporations, 47 Harv. L. Rev. (1934), 1143, 1171.

Therefore, this decision will result in a modification of case law of this state as it applies to what Mr. Chief Justice Rosenberry referred to as proposition (2) in Shulse v. Mayville (1937), 223 Wis. 624, 629, 271 N. W. 643:

“(2) A municipality does not become liable for money, services, or goods upon principles of unjust enrichment where it is prohibited from contracting in any other than a specified way, as, for instance, with the lowest bidder. . . .”

*673 We here conclude that when work has been performed for a municipality under a contract which is malum :prohibitum and not malum in se, which contract is entered into in good faith and is devoid of any bad faith, fraud or collusion, and where the statute imposes no penalty, a cause of action based upon the equitable doctrine of unjust enrichment can be maintained. This is upon the principle that courts will always try to do justice between parties where they can do so consistently with adherence to law. Equity would favor the placing of the parties in the positions that they occupied prior to the carrying out of their engagements. However, it would appear from the pleadings in this case that such would be impossible. If the facts are as alleged, both parties are guilty of failing to respect the mandate of the bidding statute. When a municipality has received the benefits of work performed, or materials furnished, in good faith, it is not just to permit the municipality to retain those benefits without paying the reasonable value thereof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Western Corrections Group, Inc. v. Tierney
96 P.3d 1070 (Court of Appeals of Arizona, 2004)
Power Sytems Analysis, Inc. v. City of Bloomer
541 N.W.2d 214 (Court of Appeals of Wisconsin, 1995)
Fond Du Lac County v. Town of Rosendale
440 N.W.2d 818 (Court of Appeals of Wisconsin, 1989)
Schmidt v. Town of Alvin
429 N.W.2d 541 (Court of Appeals of Wisconsin, 1988)
Washer v. Clatsop Care & Rehabilitation District
741 P.2d 493 (Oregon Supreme Court, 1987)
Opinion No. Oag 43-87, (1987)
76 Op. Att'y Gen. 182 (Wisconsin Attorney General Reports, 1987)
Opinion No. Oag 59-81, (1981)
70 Op. Att'y Gen. 234 (Wisconsin Attorney General Reports, 1981)
City of Merrill v. Wenzel Brothers, Inc.
277 N.W.2d 799 (Wisconsin Supreme Court, 1979)
Sturzl Construction Co. v. City of Green Bay
276 N.W.2d 771 (Wisconsin Supreme Court, 1979)
Village of McFarland v. Town of Dunn
263 N.W.2d 167 (Wisconsin Supreme Court, 1978)
Grams v. Melrose-Mindoro Joint School District No. 1
254 N.W.2d 730 (Wisconsin Supreme Court, 1977)
Nelson Inc. v. Sewerage Comm. of Milwaukee
241 N.W.2d 390 (Wisconsin Supreme Court, 1976)
Aqua-Tech, Inc. v. Como Lake Protection & Rehabilitation District
239 N.W.2d 25 (Wisconsin Supreme Court, 1976)
Village of Excelsior v. FW Pearce Corporation
226 N.W.2d 316 (Supreme Court of Minnesota, 1975)
Gottschalk Bros. v. City of Wausau
203 N.W.2d 140 (Wisconsin Supreme Court, 1973)
Fattore Co. v. Metropolitan Sewerage Commission
324 F. Supp. 354 (E.D. Wisconsin, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
183 N.W.2d 47, 49 Wis. 2d 667, 1971 Wisc. LEXIS 1151, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blum-v-city-of-hillsboro-wis-1971.