Fattore Co. v. Metropolitan Sewerage Commission

324 F. Supp. 354, 1971 U.S. Dist. LEXIS 14215
CourtDistrict Court, E.D. Wisconsin
DecidedMarch 15, 1971
DocketNo. 69-C-420
StatusPublished
Cited by1 cases

This text of 324 F. Supp. 354 (Fattore Co. v. Metropolitan Sewerage Commission) is published on Counsel Stack Legal Research, covering District Court, E.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fattore Co. v. Metropolitan Sewerage Commission, 324 F. Supp. 354, 1971 U.S. Dist. LEXIS 14215 (E.D. Wis. 1971).

Opinion

DECISION and ORDER

MYRON L. GORDON, District Judge.

This contract action was tried to the court, sitting without a jury. Post-trial briefs were submitted by the parties. The court must determine whether certain increased costs incurred during the construction in question are chargeable to the defendant.

The plaintiff urges that it is entitled to additional compensation under the “changed conditions” clause of the contract and also that it is entitled to recovery under theories of misrepresentation and breach of warranty. The defendant denies these claims and alleges that the plaintiff is barred under the “final payment” provision of the contract.

I. FINAL PAYMENT

The defendant advanced the final payment defense in a motion considered before trial, but the court rejected the motion in order to have an opportunity to hear all the facts surrounding the transaction. Article 7 of the contract contains the following provision:

“ARTICLE 7. CONTRACTOR PRECLUDED FROM SUING OWNER— The acceptance by the Contractor of the final payment by the Owner shall be and shall operate as a release to the Owner from all claims and liabilities to the Contractor for anything done or furnished for, or relating to the work, or for any act, neglect, fault or default of the Owner or of any person relating to or affecting the work.” (exhibit 22cc)

I find that monthly estimate no. 38 (exhibit 17) constitutes a final statement of the account. It shows that the job was completed and computes the amount due as a balance. The contract required periodic monthly payments; the last payment made by the commission was made following the completion and acceptance of the work. The defendant persuasively urges that exhibit 17 “represents a proper closeout of the contract.” It contains a final accounting, showing the amount of the previous payments, a computation of certain liquidated damages (agreed to by Mr. Fat-tore), and disclosing the balance of $273,744. The check in such amount paid by the defendant to Fattore Company in accordance with the summation in [357]*357exhibit 17 must reasonably be construed to constitute a “final payment” under the contract.

The contract price was $2,946,822, and exhibit 17 shows as the “total value of work to date” the figure of $2,956,678. Previous payments of $2,660,986 had been made, leaving a final balance (with certain small adjustments which are not in issue) of $273,774, which sum was paid to the plaintiff.

The plaintiff points out that in the defendant’s worksheet pertaining to estimate no. 38 (exhibit 18), the word “final” was pencilled out. The record does not establish who did such striking ; its probative value as an admission on the part of the defendant is scant since under Wisconsin law, a principal may not be bound by the admission of an agent unless it appears that the agent had authority to act. Rudzinski v. Warner Theaters, Inc., 16 Wis.2d 241, 114 N.W.2d 466 (1962). In the case at bar, we have a word stricken out, but the record is barren as to the circumstances attending such act. We do not know if it was authorized or unauthorized.

The plaintiff also argues that in certain other contracts of this defendant, the word “final” affirmatively appeared in connection with the final payment. In my opinion, the plaintiff’s contention that this established the “uniform practice” of the defendant has not been adequately established.

Mr. Fattore testified that he talked with Mr. Leary about withholding “a token amount, so we wouldn’t have a misunderstanding because I knew there was a clause about final payment, and he reassured me there was no problem”. Although this testimony was not contradicted, Mr. Leary’s statement to Mr. Fattore that “there was no problem” falls short, in my opinion, of constituting a waiver of the defendant’s rights under Article 7 of the contract. If the defendant is to be charged with having forsaken its protection under the formal contract between the parties, proof thereof should be clearer than that presented by Mr. Fattore’s interpretation of the rather broad and precatory expression attributed to Mr. Leary. In addition, it has not been shown that Fattore Company relied on such waiver.

The plaintiff urges that before the acceptance of the June 18, 1964 payment, Mr. Fattore wrote two letters to the defendant which reserved the plaintiff’s right to maintain this law suit. The letter of February 25, 1964 provides in part:

“Payment by the Sewerage Commission pursuant to the foregoing request and acceptance of such payment by Fattore Company Inc. is not to be construed as acceptance of final payment under the provisions of Article 7 of the Contract between the Sewerage Commission and Fattore Company Inc.”

On May 6, 1964, Mr. Fattore wrote another letter to the defendant which reads:

“It is, however, expressly understood and agreed that Fattore Co., Inc. does not waive its right to present a claim for extra payment on its contract because of unusual and unexpected conditions encountered on the job. Rather, Fattore Co., Inc. expressly reserves to itself the right to present such a claim to the Commission and to pursue its legal remedies.”

These two letters clearly recognize that a final payment was being offered and were written in an effort to avoid the consequence of Article 7 of the contract. Under Wisconsin law, however, a contract cannot be modified without the consent of all parties to the contract. Nelsen v. Farmers Mutual Automobile Ins. Co., 4 Wis.2d 36, 54, 90 N.W.2d 123 (1958); Jost v. Wolf, 130 Wis. 37, 40, 110 N.W. 232 (1906). Mr. Fattore was aware of the problem concerning the final payment at the time he retained the check. His unilateral effort to relieve his company of the impact of Article 7 does not nullify that provision.

[358]*358No substantial evidence has been presented in this case which would warrant my concluding that the defendant acceded to a waiver of the final payment clause or consented to the plaintiff’s present interpretation of the June 18, 1964 payment. None of the facts surrounding the transaction was sufficient, in my view, to destroy the last payment’s being “final”.

The Fattore letters, considered r in light of all the circumstances surrounding the present case, persuade me that the plaintiff’s disclaimer did not entitle it to retain the check and to avoid, at the same time, the burden of its constituting a final payment. Chandler v. State Highway Board of Georgia, 61 F.2d 601, 604 (5th Cir. 1932). See also Everlite Mfg. Co. v. Grand Valley Machine & Tool Co., 44 Wis.2d 404, 413, 171 N.W.2d 188, 192 (1969).

The defendant having met its burden of proof in establishing its defense of “final payment” under the contract, it should follow that the plaintiff’s complaint must be dismissed. However, I believe it desirable for the court to pass upon the other principal contentions advanced in this case.

II. CHANGED CONDITIONS

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
324 F. Supp. 354, 1971 U.S. Dist. LEXIS 14215, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fattore-co-v-metropolitan-sewerage-commission-wied-1971.