Chandler v. State Highway Board

61 F.2d 601, 1932 U.S. App. LEXIS 4349
CourtCourt of Appeals for the Fifth Circuit
DecidedNovember 8, 1932
DocketNo. 6648
StatusPublished
Cited by3 cases

This text of 61 F.2d 601 (Chandler v. State Highway Board) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chandler v. State Highway Board, 61 F.2d 601, 1932 U.S. App. LEXIS 4349 (5th Cir. 1932).

Opinion

WALKER, Circuit Judge.

■ This was an action brought September 30, 1930, by the appellant to recover amounts alleged to be due under two contracts entered into between him and the appellee whereby the former contracted to do work and furnish materials in constructing two described connecting public roads, one referred -to as project 39A-B in Whitfield county, Ga., and the other referred to as project 394-C in Catoosa county, Ga. The amount claimed included an amount claimed for work called for by the first mentioned contract alone, two amounts claimed to be due under the other contract alone, and two amounts which were the aggregate of amounts claimed to be due under both the contracts. The amount claimed to be due under the first-mentioned contract alone was for work done by appellant in clearing and preparing for use a chert pit pursuant to directions given/and authorized to be given by appellee’s engineer, which pit said engineer, thereafter refused to permit appellant to use. The two amounts claimed to be due under the other contract were for the alleged value of extra work done by the appellant in hauling chert a greater distance than that indicated in the plan and specifications of the work referred to in that contract, and for the alleged difference between the cost of a rubble masonry wall called for by that contract and the greater cost of making that wall of concrete pursuant to' the direction of appellee’s engineer. The amounts claimed under both the contracts were for interest, based on the alleged failure of the appellee, during the progress of the work under the contracts, to make payments when due, and for the alleged amount of profits appellant would have realized in installing guard rails called for by each of the contracts, which work appellant was not permitted to do; the construction of such guard rails being let to another contractor. The appellee pleaded accord and satisfaction of the elaims of the appellant based upon the contracts mentioned, that defense as tó claims under the first-mentioned contract being based on the alleged fact “that on or about November 28th, 1928, defendant tendered plaintiff the sum of $8,906.18 as full and final payment of all that plaintiff was due from defendant on account of said contract covering what is referred to in plaintiff’s petition as Project 394-B, and plaintiff at that time accepted said amount subject to said condition.” The defense of accord and satisfaction with reference to the elaims asserted by the suit in so far as they were alleged to have grown out of the contract covering what was referred to in plaintiff’s petition as project 394r-C was based upon a similar allegation with reference to the acceptance by plaintiff of the sum of $13,276.30, on or about March 19,1929, tendered by the defendant to plaintiff as a full and final payment of all that plaintiff was due from defendant under the last-mentioned contract. Each of the contracts mentioned contained the following provisions:

“Pinal Inspection: Whenever the work provided and contemplated by the contract shall have been satisfactorily completed and the final cleaning up performed the Engineer shall, within ten days unless otherwise provided, make the ‘Pinal Inspection.’ ”

“Termination of Contractor’s Responsibility : This Contract will be considered complete when all work has been completed, and the Pinal Inspection made, the work accepted by the Engineer, and the final estimate paid. The Contractor will then be released from further obligation except as set forth in his bond.”

[603]*603“Acceptance and Final Payment: Whenever the work provided for by the contract shall have been completely performed on the part of the Contractor, and all parts of the work have been approved by the Engineer and the Final Inspection made, a final estimate showing the value of the work done will be prepared by the Engineer as soon as the necessary measurements may he made. The amount of this estimate, less any sums that may have been deducted in accordance with the provisions of the contract, and less all previous payments, will, be paid to the Contractor within 30 days after the final estimate has been approved by the Engineer.”

“Final settlement: The Contractor shall give public notice that final settlement is to be made by advertisement for four consecutive weeks in the recognized official newspaper. The advertisement shall state that full settlement has been made for all labor and materials, and that all claims for nonpayment or damage must be presented to the Engineer on or before the date of final settlement.”

Evidence showed the following: In September, 1928, appellant gavei notice by publication in a newspaper that he had completed project 394-B, Whitfield county, Ga., and project 394-C, Catoosa county, Ga., and that those two pieces of road had been accepted as completed by appellant. Correspondence between the parties with reference to the publication of that advertisement shows that such publication was made following the giving of written notice by the appellee’s engineer to appellant that appellee would not submit final statements “on 394-B Whitfield County, and 394-C” until appellee had received copy of such advertisement. After that publication was made, appellee’s engineer made inspections of the work on both the projects, and made estimates showing the value of the work done, the caption of such estimate as to project 394-B being, “Statement No. 12— Final, Project No. 394-B, ptate Aid Road, Whitfield County”; that estimate on project 394-B showing the amount due on that project to be $8,906.18; and the caption on such estimate as to project 394-C being, “Monthly Statement No. 15 Final. Project No. 394^C. State Aid Road, Catoosa County,” and that estimate showing the amount due on that project to be $13,270.32. By written instrument appellant transferred and assigned to the Fulton National Bank of Atlanta, Ga., all his right, title, and interest in the sum of $8,906.18 due from appellee to him under the project 394-B contract, and directed appel-lee to pay that sum to that hank. The ap-pellee issued the following instrument:

“H. D. 218. No. 808.

“State Highway Board of Georgia.

“Nov. 24, 1928.

“Est. No. 12 Final — Project 394-B— Whitfield — Voucher.

“No. 1048 of T. W. Chandler. $8,906.18

“Pay to the order of Fulton National Bank, $8,906.18, S. H. Board of Georgia $8,-906 and 18 cts. Dollars.

“State Highway Board of Georgia. “Correct:

“T. M. McLain,

“Chief Clerk.

“John N. Holder,

“Chairman State Highway Board.

“To Fulton National Bank, Atlanta, Georgia, “(Project Account.)”

On the back of that instrument is a stamp as follows: “Paid Loan Discount Teller of Fulton National Bank, November 28, 1928.” The appellee issued the following instrument:

“H. D. 218. No. 1313.

“Mar. 19, 1929.

“Vou. 420 — Est. 15 — Final. Proj. 394-C,

Catoosa Co. $13,270.32

“Pay to the order of T. W. Chandler & Southern Surety Company, $13,270.32, S. H. Board of Georgia, $13,270 and 30 cts. Dollars.

“Chief Clerk. “John N. Holder,

“To Fulton National Bank, Atlanta, Georgia, “Project Account.

“Indorsed: Paid 3-25-29. 64.7.”

On the hack of that instrument are the indorsements: “Southern Surety Company by T. A. Long, Attorney in Fact,” and “T. W. Chandler,” and stamped indorsements as follows: Citizens’ Bank of Virgilina, by T. L.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fattore Co. v. Metropolitan Sewerage Commission
313 F. Supp. 208 (E.D. Wisconsin, 1970)
Nemitz v. Norfolk and Western Railway Co.
287 F. Supp. 221 (N.D. Ohio, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
61 F.2d 601, 1932 U.S. App. LEXIS 4349, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chandler-v-state-highway-board-ca5-1932.