Gottschalk Bros. v. City of Wausau

203 N.W.2d 140, 56 Wis. 2d 848, 1973 Wisc. LEXIS 1640
CourtWisconsin Supreme Court
DecidedJanuary 15, 1973
DocketNo. 266
StatusPublished

This text of 203 N.W.2d 140 (Gottschalk Bros. v. City of Wausau) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gottschalk Bros. v. City of Wausau, 203 N.W.2d 140, 56 Wis. 2d 848, 1973 Wisc. LEXIS 1640 (Wis. 1973).

Opinions

Robert W. Hansen, J.

This case resembles a jigsaw picture puzzle, or, more accurately, the pieces of three jigsaw puzzles jumbled together. Until it is determined how the work done that is involved in this dispute fits into the picture, the pieces cannot be put together. It is not possible to locate the law or apply the appropriate legal conclusions unless or until the nature of the work done is determined. Once that is decided — what the work done constituted in relation to the contract — the picture puzzle is easily completed.

We see three, not two, possible answers to describing, legally, how the work done and not paid for relates to the contract involved.

(1) Extra work. If item number 13 (the only section of the contract here involved) was a contract for providing 16,000 cubic yards of fill-borrow materials, with an added provision for extra work to be done at the same unit price, then the work necessitated by the grade problems in the rock cut area was extra work. If it is such a contract containing such provision for such extra work, sec. 62.15 (lc), Stats., permits the increase in the quanti[853]*853ty of work that was done under the contract, but only to the extent of 15 percent of the cost of the original contract. (See: Blum v. Hillsboro (1971), 49 Wis. 2d 667, 183 N. W. 2d 47.)

(2) New contract. Another view of the situation would see two contracts here involved. Under the written agreement between the parties (awarded in compliance with sec. 62.15, Stats.) the parties proceeded to operate until they encountered the rock cut. At that point, under the contract, the city had the right to stop the filling, excavate or contract with someone else to excavate. The city stopped the work, but then, under its option, directed a fill operation, one not contemplated or provided for in the written contract. So viewed, a second contract should have been let in compliance with sec. 62.15. Under this view, the parties proceeded under a malum pro-hibitum oral agreement, entered into in complete good faith but not in compliance with the applicable statutory requirements. The sole recourse of the plaintiff then would be to seek to recover, not on the unit price basis set forth in the contract, but on the basis of unjust enrichment, for “. . . an amount which represents the actual cost to the plaintiff, without allowing profits including overhead expense, and ... in no event [to] exceed the unit cost of the original contract. . . .” (See: Blum v. Hillsboro, supra, at page 674.)

(3) Contract work. The third possible categorization of the work performed under item number 13 is that it was not extra work, and not work performed outside the contract^ but work contemplated and provided for in the contract. This would hold item number 13 to be not a contract to provide fill-borrow materials up to a contract specified figure of 16,000 cubic yards, but as a “unit priced” provision, providing that the contractor was to be paid a specified amount for every unit of needed and designated work that he performs. (See: Justin Sweet, Legal Aspects of Architecture, Engineering, [854]*854and the Construction Process (1970), page 816, for a discussion of the “unit pricing” type of construction contract. See also: Probst v. Menasha (1944), 245 Wis. 90, 94, 13 N. W. 2d 504, stating, “There is no limitation upon the amount of sidewalk that the contractor might be required to do, his bid being on a unit basis.”)

Narrowing consideration and conclusion to this one provision (item number 13) of this particular contract under these special circumstances, we find three facts or factors in this record that compel the conclusion that this was not “extra work,” nor work for which a new contract was required, but rather was work provided for and performed pursuant to the written contract between the parties on a “unit price” basis. These three facts or factors are:

(1) Approximation of quantity. Item number 13 states the quantity of fill-borrow materials to be furnished only as an approximation. That the qualifying word, “approximately,” reflected an understanding that the quantity was expected to be varied by conditions encountered is clear from the surrounding circumstances. Some variation from original plans is expected in almost all major construction projects. But here more than a usual leeway is involved. To save some thirty or so days, the city made no survey of conditions existing. Nor did it have a survey made. Instead it accepted information from the insurance company owner of a nearby building. The use of the company’s layout or sketches, prepared for the owner of an adjacent building for the use of such owner, strengthens the conclusion that the stated approximation of quantity was not intended to be exact, or even close to that target.
(2) Existence of option. That the contract attaches only slight weight to the approximation as to quantity is made clear by the inclusion in item number 13 of an option given to the city to stop filling and substitute excavating at its own expense, in place of continued filling by the plaintiff, to establish the required grade level. [855]*855If no more than usual slight variances were anticipated, it seems unlikely that the city would put into the contract a right for it to stop all filling at any stage and substitute excavating, either doing the excavating itself or contracting with someone else for its being done. It developed that the city engineer, who under the contract had “general supervision and direction of all work,” and was to “decide all questions which may arise relative to the . . . execution of the plans,” determined that excavation would be more costly to the city than having the plaintiff do the filling beyond the 16,000 cubic yard expectation. The city engineer had the authority to stop the work, decide the question and determine that the plaintiff was to proceed with the filling. When he did just that, he acted pursuant to the contract, and his right so to do and the existence of the option he exercised indicates that, as to item number 13, it was the unit price, not the estimation of “approximate” quantity, which was the primary consideration.
(3) Stipulation of the parties. In this case the city and the plaintiff stipulated that no written change order was required from the board of public works or board of education for the work performed under item number 13. The contract provided such prior written authorization before performing any “extra work.” In fact, the contract provided that plaintiff was not to be paid for any unauthorized “extra work.” Not only the stipulation, but the agreement, the understanding of the parties and their acts strongly indicate neither “extra work” nor unauthorized work was here involved. It was work performed under item number 13, for which no additional authorization or “change order” was required by the contract.

Putting together the approximation only as to quantity in item number 13, the existence of the option to excavate rather than fill if extreme undulations in grade were encountered, and the stipulation that no change order or special authorization was required for the work per[856]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blum v. City of Hillsboro
183 N.W.2d 47 (Wisconsin Supreme Court, 1971)
Probst v. City of Menasha
13 N.W.2d 504 (Wisconsin Supreme Court, 1944)
Victora v. Village of Muscoda
279 N.W. 663 (Wisconsin Supreme Court, 1938)
Thomsen-Abbott Construction Co. v. City of Wausau
100 N.W.2d 921 (Wisconsin Supreme Court, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
203 N.W.2d 140, 56 Wis. 2d 848, 1973 Wisc. LEXIS 1640, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gottschalk-bros-v-city-of-wausau-wis-1973.