Bigge Crane & Rigging Co. v. Workers' Compensation Appeals Board

188 Cal. App. 4th 1330, 116 Cal. Rptr. 3d 153, 75 Cal. Comp. Cases 1089, 2010 Cal. App. LEXIS 1705
CourtCalifornia Court of Appeal
DecidedOctober 4, 2010
DocketA127136
StatusPublished
Cited by3 cases

This text of 188 Cal. App. 4th 1330 (Bigge Crane & Rigging Co. v. Workers' Compensation Appeals Board) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bigge Crane & Rigging Co. v. Workers' Compensation Appeals Board, 188 Cal. App. 4th 1330, 116 Cal. Rptr. 3d 153, 75 Cal. Comp. Cases 1089, 2010 Cal. App. LEXIS 1705 (Cal. Ct. App. 2010).

Opinion

Opinion

BANKE, J.

Introduction

Respondent Paul Hunt was injured while assisting with the dismantling of a truck crane used during a shutdown operation at a refinery. Hunt had been helping on another crane at the jobsite, and, along with two ironworkers on the rigging crew, was told by the general foreman to help with the dismantling. Hunt was injured when a section of the boom fell eight inches to the ground and onto his lower leg and ankle. The Workers’ Compensation Appeals Board (Board) sustained an award of additional compensation to Hunt under Labor Code section 4553, 1 concluding his injuries were caused by the “serious and willful misconduct” of the operator of the crane and the general foreman, both of whom were determined to be “managing officers” of petitioner Bigge Crane and Rigging Co. (Bigge Crane). Bigge Crane challenges the award, contending (a) the operator of the crane was not a “managing officer” of the company within the meaning of section 4553 and therefore his conduct cannot support an award of additional compensation and (b) the general foreman, even assuming he qualifies as a “managing officer,” did not engage in “serious and willful misconduct.” We agree with both points and annul the award of additional compensation.

Factual and Procedural Background

On the day of the accident, Mark Mom was told to disassemble (“rig out”) a truck crane he had been operating for approximately six weeks at the Chevron Oil refinery in Richmond, California. Mom had worked around or on cranes for more than 30 years, first as an oiler (who assists the operator of a “two-man” crane) and, beginning in 1980, as an operator. As an oiler, Mom *1337 was directed by the crane operator to do such things as checking and maintaining the level of machine fluids, cleaning and moving the crane, and setting up the crane at the jobsite. When he became an operator, he, in turn, gave such directions to the oiler when he worked on a “two-man” crane. The customer, jobsite superintendent or foreman would tell Mom what task he was to perform with the crane; however, Mom was in charge of the actual functioning of the crane. He would, for example, determine how to enter a jobsite to avoid obstacles and power lines, where to locate the crane and how loads would be hoisted and put in place. He would start and stop the crane as he believed necessary. When he was directed to disassemble a crane, he both performed that task (often by himself or with only the oiler) and gave directions to anyone who helped him. He was responsible for doing crane work as safely as possible.

Mom began working periodically for Bigge Crane in the mid-1990’s. By 1998, he was a certified and licensed crane operator, which required both written and practical tests. In January 2002, he was hired by Bigge Crane to operate a 90-ton Peck & Hiller truck crane at the Chevron refinery jobsite. Prior to the work at the refinery, he attended site-specific training provided by Chevron covering safety procedures, personal protection, emergency procedures and job duties of the personnel onsite. The training also reviewed safety procedures and protocols for the cranes.

Mom was assigned to the night shift. At the start of the shift, the entire Bigge Crane work crew gathered at the job shack to stow their personal gear and attend a preshift meeting. The 10- to 15-minute meeting was conducted by the Bigge Crane general foreman, who would tell the crew what they would be doing and with whom they would be working. The crew would then go to their assignments. Mom would go to the Peck & Hiller crane with his oiler, Jason Strode, and often would be working with ironworkers, all of whom were part of the Bigge Crane rigging crew, and who would, among other things, secure the loads hoisted by the crane.

On the day of the accident, Mom was called in for the day shift, and was told by Curtis Embry, the general foreman and supervisor for that area of the jobsite on that shift, to disassemble the crane. Embry, in turn, had been told by Chevron’s supervisor on the job to have the crane dismantled. Embry had been trained in rigging safety and, as the general foreman, was responsible for seeing that rigging operations were conducted safely. Typically, after assigning operators and workers to their tasks, Embry would hold a safety meeting reviewing concerns and precautions in connection with the specific tasks.

*1338 Mom had disassembled hundreds of one-man cranes and more than 30 “two-man” cranes while working at Bigge Crane, and he and his oiler, Strode, had reviewed the dismantling process for the Peck & Hiller crane. Strode, however, was not dispatched to the refinery that day, so Chevron’s rigging department told Mom he could have whomever he wanted to work as the oiler. Mom asked for Dave McGarry, another experienced operator and oiler. McGarry joined Mom at the crane after Mom had already brought it off the blocks. McGarry turned the crane, counterweights were set, Mom let the boom down so it touched the ground, the ball and block and jib lines were unhooked, and the jib strut was lowered.

In the meantime, Embry told the operator of another crane (an 80-ton truck crane) and Hunt, who was working as the oiler, to go and assist Mom. He also told two ironworkers, who were part of the rigging crew assisting with the crane work, including disassembly, to help Mom. Embry also went over to help. Mom continued with the dismantling process, giving instructions to those assisting. Embry did not stop the work, or ask Mom to do so, for a safety meeting. Embry viewed the task as “just another job” over the course of the day.

McGarry was then called away to operate another crane, and Hunt took over as the oiler. At one point, while Mom was in the cab of the crane, he called out to Embry that the ironworkers were performing work out of sequence, specifically, starting to remove the tip of the boom, and needed to stop momentarily. Embry stopped the workers, and Mom explained several other tasks needed to be done first. The tasks were accomplished, the work continued, and the tip was removed without incident.

Before the tip was removed, Embry was called away to another area by Chevron’s supervisor. At the time he left, Embry saw there were “at least 16” “cribbing” blocks (six-by-eight-inch wooden blocks, four feet long) “available to be used.” He knew the blocks were for use under the boom sections, and also knew blocks had already been placed under the tip of the boom as it was removed.

The disassembly of the crane continued. When the ironworkers started hammering several pins out of the next boom section, Mom again exited the cab of the crane, walked over to where they were working and had them stop until blocks were placed. An assist crane that had been brought over lifted the *1339 boom, and Mom placed two blocks under the section. Instead of returning to the cab to tighten the bridle (for cantilever support), Mom walked over to where Hunt was standing, told the two ironworkers to stand back, called for everyone to have their feet out of the way and pounded a bottom pin. Mom thought his feet were sufficiently out of the way and did not look to see if Hunt’s feet were also clear.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

(PC) Gelazela v. United States
E.D. California, 2025
CLP Resources v. WCAB (Mora) CA1/1
California Court of Appeal, 2013
Karty v. DePhilippis CA4/1
California Court of Appeal, 2013

Cite This Page — Counsel Stack

Bluebook (online)
188 Cal. App. 4th 1330, 116 Cal. Rptr. 3d 153, 75 Cal. Comp. Cases 1089, 2010 Cal. App. LEXIS 1705, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bigge-crane-rigging-co-v-workers-compensation-appeals-board-calctapp-2010.