Bateman Construction, Inc. v. Haitsuka Bros., Ltd.

889 P.2d 58, 77 Haw. 481, 1995 Haw. LEXIS 3
CourtHawaii Supreme Court
DecidedJanuary 9, 1995
Docket17745
StatusPublished
Cited by31 cases

This text of 889 P.2d 58 (Bateman Construction, Inc. v. Haitsuka Bros., Ltd.) is published on Counsel Stack Legal Research, covering Hawaii Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bateman Construction, Inc. v. Haitsuka Bros., Ltd., 889 P.2d 58, 77 Haw. 481, 1995 Haw. LEXIS 3 (haw 1995).

Opinion

*482 RAMIL, Justice.

To capsulize the intent behind Hawai'i Revised Statutes (HRS) Chapter 658, Arbitration and Awards, we have stated that by-agreeing to arbitration “it was [the arbitrator’s] judgment [the parties] bargained for, not a court’s.” Morrison-Knudsen Co. v. Makahuena Corp., 66 Haw. 663, 670, 675 P.2d 760, 766 (1983). In this arbitration matter, Respondent/Counter-Claimant-Appellant Haitsuka Brothers, Limited (Haitsu-ka) and Claimant/Counter-Respondent-Ap-pellee Bateman Construction, Inc., (Bate-man) submitted contract disputes to the American Arbitration Association (AAA) for arbitration. After the arbitration commenced and three pre-hearing conferences were held, the arbitrator ruled upon and rejected Haitsuka’s proposed arbitration schedule. Haitsuka then filed an action with the circuit court requesting orders (1) to postpone an already ongoing arbitration and (2) to consolidate two other ongoing arbitra-tions. The circuit court refused because it lacked subject matter jurisdiction. We agree and affirm the circuit court’s order denying Haitsuka’s motion to postpone arbitration and to consolidate all four arbitrations.

I. FACTS

Haitsuka, a general contractor, entered into four different subcontract agreements with Bateman. Under the contracts, Bate-man agreed to perform construction work on four projects located in Salt Lake, Mililani, Waahila, and on the Hickam Air Force Base.

All four contracts contained the following arbitration clause:

ELEVENTH: If at any time any controversy should arise between the Contractor and the Subcontractor regarding anything pertaining to this agreement ..., then the written orders of the Contractor shall be followed and said controversy shall be decided by arbitration upon completion of the work.

(Emphasis added.)

Haitsuka and Bateman proceeded to perform the above contracts when disputes developed on the Salt Lake and Mililani projects. Pursuant to the arbitration agreement, Bateman filed two separate demands for arbitration—one for each contract. On the Salt Lake contract, Bateman claimed damages for differing subsurface site conditions, which consisted of hard rock instead of easily removable soil. On the Mililani contract, Bateman claimed damages for work performed beyond the scope of the contract and resulting construction delays. Haitsuka, in turn, filed two separate answers denying any and all liability to Bateman and included two separate counterclaims alleging, inter alia⅜ multiple breaches of the Salt Lake and Mililani contracts.

Before the arbitration process began, Bateman and Haitsuka stipulated: (1) that Bateman’s claim and Haitsuka’s counterclaims regarding the Salt Lake contract should be arbitrated; (2) that the above dispute should be decided in the tribunal of the AAA and under its rules; and (3) that William A. Stricklin would be appointed as the AAA Arbitrator.

Three pre-hearing conferences were scheduled. At the first pre-hearing conference on November 9, 1993, Bateman asked the Arbitrator to schedule arbitration hearings on the Salt Lake controversy as soon as possible. Haitsuka, on the other hand, asked the Arbitrator to postpone hearings until the end of June 1994.

Haitsuka argued that the claims and counterclaims were not presently “arbitrable” because creditors and suppliers were still filing claims against Haitsuka for monies that Bateman failed to pay. Haitsuka asserted, among other reasons, that it could -not present a defense or quantify its counterclaims until the end of June 1994, following the deadline for suppliers and subcontractors to file their claims on the Salt Lake project.

The Arbitrator decided that “ ‘timeliness’, ‘ripeness’, and/or ‘arbitrability’ ” were issues for arbitration. The Arbitrator determined that Haitsuka’s challenge was not substantive but procedural; therefore, he found that the scheduling of the initial hearings was a procedural issue to be determined by him rather than by the courts. Despite Haitsuka’s claims to the contrary, the Arbitrator concluded that Bateman’s claim was ripe for *483 arbitration and scheduled the initial hearings for December 1993 and January 1994.

In a letter dated November 23,1993, Bate-man asked the Arbitrator to consolidate the Hickam and Waahila contracts with the Salt Lake arbitration. Bateman argued that consolidation of these three projects into a single hearing would be more efficient because common questions of law and fact existed in all three projects. However, Bateman stated that the Milliard contract should not be consolidated because the questions of law and fact were different. Bateman explained that while construction on the other projects was still ongoing, construction on the Mililani contract was complete.

In a response letter dated November 29, 1993, Haitsuka argued that the Hickam and Waahila contracts should not be consolidated into a single hearing with the Salt Lake contract. Haitsuka asserted that each contract was “unique” and that consolidation was inappropriate. Haitsuka, however, proposed that the Arbitrator could possibly consolidate all four projects into a single arbitration after June 1994 when all claims against Bateman and Haitsuka would toll. Haitsuka maintained that arbitration after June 1994 would be the best way to provide a full and fair hearing on all damages between the parties.

On December 13, 1993, the Arbitrator granted Bateman’s request to consolidate the Salt Lake, Hickam, and Waahila contracts into a single hearing. As a result, the Arbitrator scheduled all three eases to be arbitrated at once with hearings to start in December 1993.

Meanwhile, Haitsuka filed a motion in the circuit court to postpone the December hearing and to consolidate all four arbitrations into a single hearing. Haitsuka contended that: (1) the circuit court should postpone the December hearing pursuant to HRS § 658-9 1 because Haitsuka presented good cause to postpone; and (2) the court then should consolidate all four arbitrations because no prejudice existed to Bateman.

Bateman subsequently filed a memorandum opposing Haitsuka’s motion. Bateman contended that this motion should be denied based on principles of estoppel or res judica-ta since Haitsuka already submitted the issues of scheduling and consolidation to the Arbitrator and lost. In addition, Bateman argued that circuit court lacked jurisdiction to intervene in an uncompleted arbitration.

On December 14, 1993, the circuit court held a hearing on the motion to postpone and consolidate. On the postponement issue, Ha-itsuka argued that: (1) the court had jurisdiction pursuant to HRS § 658-9 as well as § 658-3; 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McClurg v. Caulfield
558 P.3d 253 (Hawaii Intermediate Court of Appeals, 2024)
Moloaa Farms LLC v. AOAO of Moloaa Hui I
553 P.3d 922 (Hawaii Intermediate Court of Appeals, 2024)
In Re United Pub. Workers, Afscme, Loc. 646
244 P.3d 609 (Hawaii Intermediate Court of Appeals, 2010)
BlueEarth Biofuels, LLC v. Hawaiian Electric Co.
235 P.3d 310 (Hawaii Supreme Court, 2010)
Mikelson v. United Services Automobile Ass'n
227 P.3d 559 (Hawaii Intermediate Court of Appeals, 2010)
Swift Securities Limited v. Yau
201 P.3d 628 (Hawaii Intermediate Court of Appeals, 2009)
Vickery v. Hastert
201 P.3d 628 (Hawaii Intermediate Court of Appeals, 2009)
Douglass v. Pflueger Hawaii, Inc.
135 P.3d 129 (Hawaii Supreme Court, 2006)
Fireman's Fund Insurance Co. v. AIG Hawai'i Insurance Co.
126 P.3d 386 (Hawaii Supreme Court, 2006)
Ueoka v. Szymanski
114 P.3d 892 (Hawaii Supreme Court, 2005)
Seretta Const., Inc. v. Great American Ins. Co.
869 So. 2d 676 (District Court of Appeal of Florida, 2004)
Tatibouet v. Ellsworth
54 P.3d 397 (Hawaii Supreme Court, 2002)
Bronster v. United Public Workers, AFSCME, Local 646
975 P.2d 766 (Hawaii Supreme Court, 1999)
Moss v. American International Adjustment Co.
947 P.2d 371 (Hawaii Supreme Court, 1997)
Brown v. KFC National Management Co.
921 P.2d 146 (Hawaii Supreme Court, 1996)
Mathewson v. Aloha Airlines, Inc.
919 P.2d 969 (Hawaii Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
889 P.2d 58, 77 Haw. 481, 1995 Haw. LEXIS 3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bateman-construction-inc-v-haitsuka-bros-ltd-haw-1995.