Ballard Concrete, LLC v. CDE Global, ID

CourtSuperior Court of Delaware
DecidedNovember 3, 2025
DocketN25C-06-142 FJJ
StatusPublished

This text of Ballard Concrete, LLC v. CDE Global, ID (Ballard Concrete, LLC v. CDE Global, ID) is published on Counsel Stack Legal Research, covering Superior Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ballard Concrete, LLC v. CDE Global, ID, (Del. Ct. App. 2025).

Opinion

IN THE SUPERIOR COURT OF THE STATE OF DELAWARE

BALLARD CONCRETE, ) ) Plaintiff, ) ) C.A. No.: N25C-06-142 FJJ v. ) ) CDE GLOBAL, ID, ) ) Defendants. )

Submitted: October 21, 2025 Decided: November 3, 2025

OPINION AND ORDER On Defendant’s Motion to Dismiss Plaintiff’s Complaint

GRANTED, in part, and DENIED, in part.

William B. Larson, Esquire and Jalen S. Frantal, Esquire, Manning Gross & Massenburg, LLP, Wilmington, Delaware, Attorneys for Plaintiff.

Elizabeth S. Fenton, Esquire and Brittany M. Giusini Tsoflias, Esquire, Barnes & Thornburg, LLP, Wilmington, Delaware, Attorneys for Defendant.

Jones, J. Ballard Concrete, LLC (“Ballard” or “Plaintiff”) is an Alabama limited

liability company with a principal place of business is located in Alabama.1 CDE

Global (“CDE” or “Defendant”) is a Delaware Corporation with a principal place

of business is located in Texas.2 In late 2022, the parties engaged in negotiations

surrounding a custom sand and gravel plant (“Plant”) CDE would build for

Ballard.3 The parties ultimately entered into a contract for CDE to build Ballard

the Plant. Work commenced and problems arose between the parties. This lawsuit

follows.

In the Complaint filed with this court on June 12, 2025, Ballard asserted the

following claims against CDE: 1) fraudulent inducement; 2) fraudulent

misrepresentation; 3) breach of contract; 4) breach of the implied covenant of good

faith and fair dealing; 5) breach of express warranty (6 Del. C. §2-313); 6) breach

of implied warranty of merchantability (6 Del. C. §2-314); 7) breach of the implied

warranty of fitness for a particular purpose (6 Del. C. §2-315); 8) anticipatory

repudiation; and 9) a declaratory judgement.4 Ballard further alleges damages of

at least $5,168,650.56, with additional damages of $25,890 being incurred each

1 Docket Item (“D.I.”) 1, ¶ 1. 2 D.I. 1, ¶ 2. 3 D.I. 1, ¶ 6; D.I. 10, p. 2. 4 See generally D.I. 1.

2 day.5 In response, CDE filed a motion to dismiss claims I, II, IV, VI, VII, VIII,

and IX on August 8, 2024.6 This is the Court’s decision on that motion.

STANDARD OF REVIEW

When reviewing a Motion to Dismiss under Superior Court Rule 12(b)(6),

the Court (1) accepts all well-plead factual allegations as true, (2) accepts even

vague allegations as well-plead if they give the opposing party notice of the claim,

(3) draws all reasonable inferences in favor of the non-moving party, and (4) only

dismisses a case where the plaintiff would not be entitled to recover under any

reasonably conceivable set of circumstances.7 “Dismissal is warranted where the

plaintiff has failed to plead facts supporting an element of the claim, or that under

no reasonable interpretation of the facts alleged could the complaint state a claim

for which relief might be granted.”8

FACTUAL AND PROCEDURAL OVERVIEW

When the facts are taken from the Complaint, viewed in a light most

favorable to Ballard, they reveal the following.

In late 2022, the parties engaged in negotiations surrounding a custom sand

and gravel plant (“Plant”) CDE would build for Ballard.9 The rough price estimate

5 D.I. 1, ¶ 107-108, 176. 6 See generally D.I. 10. 7 ET Aggregator, LLC v. PFJE Asset Co Holdings LLC, 2023 WL 8535181, at *6 (Del. Super. Ct. Dec. 8, 2023). 8 Hedenberg v. Raber, 2004 WL 2191164, at *1 (Del. Super. Ct. Aug. 20, 2004). 9 D.I. 1, ¶ 6; D.I. 10, p. 2.

3 was provided by Defendant on February 9, 2023.10 After multiple meetings and

discussions as to price and expectations, on March 12, 2023, the parties agreed on

a price of $2,026,450.00 for the design, shipment, and installation of the custom

Plant.11 The Order Agreement (“OA”), which outlined warranties, payment dates,

and building timelines, was reviewed and signed by Ballard’s President on March

24, 2023.12

On March 31, 2024, Ballard paid the initial 30% deposit ($607,935.00) as

required by the OA.13 On October 31, 2023, Ballard paid another 20% of the price

($419,477.05) to “facilitate the start of Final Assembly and Testing of Products.”14

In December of 2023 and January of 2024, disagreements arose as to the

fulfillments of the parties’ duties in relation to product delivery and payment.15 To

resolve these disputes, the parties agreed to amend the original OA and payment

structure (hereinafter referred to as the “Resolution”) on January 24, 2024,

supplementing it with new delivery dates and letters of credit that would be

released upon successful delivery and assembly of the Plant and it’s parts.16 The

Resolution also required Ballard to pay another 30% ($668,937.27) immediately,

10 D.I. 1, ¶ 9; D.I. 10, p. 2. 11 D.I. 1, ¶ 9-16; D.I. 10, p. 2-3. 12 D.I. 1, ¶ 16-20; D.I. 10, p. 3. 13 D.I. 1, ¶ 21; D.I. 10, p. 3. 14 D.I. 1, ¶ 24; D.I. 10, p. 3. 15 D.I. 1, ¶ 21-31; D.I. 10, p. 3. 16 D.I. 1, ¶ 34; D.I. 10, p. 3-4.

4 which it paid on the same day.17 Pursuant to the Resolution, after the first shipment

arrived on February 11, 2024, Ballard signed and executed two letters of credit to

CDE on April 27, 2024, valued at $327,436.20 and $109,145.40, respectively. 18 A

second shipment was completed on July 2, 2024, and a third followed on July 8,

2024.19

With the completion of these shipments, CDE executed, and received

payment of, the first letter of credit ($327,436.20).20 Issues arose with the

construction of the Plant from August to October of 2024.21 CDE commissioned

the Plant on September 30, 2024.22 The final shipment of parts for construction

were delivered on October 20, 2024.23 On October 21, 2024, CDE sent Ballard a

“Commissioning Report” noting the completion and commission of the Plant.24

Disagreements ensued regarding the payment of the final letter of credit, the final

outstanding amount under the OA, totaling $109,145.40.25

Ballard sent a demand letter to CDE outlining issues with the Plant,

contractual disputes, and other claims on November 1, 2024.26

17 D.I. 1, ¶ 35; D.I. 10, p. 3-4. 18 D.I. 1, ¶ 36-43; D.I. 10, p. 3-4. 19 D.I. 1, ¶ 45, 47; D.I. 10, p. 4. 20 D.I. 1, ¶ 51-53; D.I. 10, p. 4. 21 D.I. 1, ¶ 48-65; D.I. 10, p. 4. 22 D.I. 1, ¶ 58, 65, 72; D.I. 10, p. 4. 23 D.I. 1, ¶ 65, 68; D.I. 10, p. 4. 24 D.I. 1, ¶ 71-72; D.I. 10, p. 4. 25 D.I. 1, ¶ 74; D.I. 10, p. 4. 26 D.I. 1, ¶ 79; see also Exhibit G.

5 ANALYSIS

I. Count I and Count II, the Fraudulent Inducement and Fraudulent Misrepresentation Claims, Meet the Pleading Requirements.

In Counts I, II, and III, Plaintiff asserts claims of fraudulent inducement,

fraudulent misrepresentation, and breach of contract, respectively.27 Count I, the

fraudulent inducement claim, is based on alleged statements defendant made

regarding the processing capabilities of the Plant and the support CDE would

provide to Ballard.28 Count II, fraudulent misrepresentation, again raises the issue

of the Plant’s processing power, in addition to alleged misrepresentations about

when the Plant would be completed, the support and warranty services Ballard

would receive, and the Plant’s compliance with regulatory standards.29 Defendant

argues the first two counts should be dismissed because: 1) they are not plead with

the required particularity; 2) they are duplicative under the economic loss

doctrine; and 3) the claims rely on alleged extracontractual statements.30

A. Required Particularity.

I first address whether the claims meet the requirements of Superior Court

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Airborne Health, Inc. v. Squid Soap, LP
984 A.2d 126 (Court of Chancery of Delaware, 2009)
H-M Wexford LLC v. Encorp, Inc.
832 A.2d 129 (Court of Chancery of Delaware, 2003)
Dunlap v. State Farm Fire & Casualty Co.
878 A.2d 434 (Supreme Court of Delaware, 2005)
Kronenberg v. Katz
872 A.2d 568 (Court of Chancery of Delaware, 2004)
Sheehan v. Hepburn
138 A.2d 810 (Court of Chancery of Delaware, 1958)
Chamison v. HealthTrust, Inc.-Hosp. Co.
735 A.2d 912 (Court of Chancery of Delaware, 1999)
Danforth v. Acorn Structures, Inc.
608 A.2d 1194 (Supreme Court of Delaware, 1992)
E.I. DuPont De Nemours & Co. v. Pressman
679 A.2d 436 (Supreme Court of Delaware, 1996)
Wilgus v. Salt Pond Investment Co.
498 A.2d 151 (Court of Chancery of Delaware, 1985)
Abry Partners V, L.P. v. F & W Acquisition LLC
891 A.2d 1032 (Court of Chancery of Delaware, 2006)
Nemec v. Shrader
991 A.2d 1120 (Supreme Court of Delaware, 2010)
CitiSteel USA, Inc. v. CONNELL LIMITED PARTNERSHIP
758 A.2d 928 (Supreme Court of Delaware, 2000)
Gilbert v. El Paso Co.
490 A.2d 1050 (Court of Chancery of Delaware, 1984)
Lecates v. Hertrich Pontiac Buick Co.
515 A.2d 163 (Superior Court of Delaware, 1986)
Lord v. Souder
748 A.2d 393 (Supreme Court of Delaware, 2000)
In Re IAC/InterActive Corp.
948 A.2d 471 (Court of Chancery of Delaware, 2008)
FdG Logistics LLC v. A&R Logistics Holdings, Inc.
131 A.3d 842 (Court of Chancery of Delaware, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Ballard Concrete, LLC v. CDE Global, ID, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ballard-concrete-llc-v-cde-global-id-delsuperct-2025.