Aspic Engineering and Constr. v. Ecc Centcom Constructors LLC

913 F.3d 1162
CourtCourt of Appeals for the Ninth Circuit
DecidedJanuary 28, 2019
Docket17-16510
StatusPublished
Cited by47 cases

This text of 913 F.3d 1162 (Aspic Engineering and Constr. v. Ecc Centcom Constructors LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aspic Engineering and Constr. v. Ecc Centcom Constructors LLC, 913 F.3d 1162 (9th Cir. 2019).

Opinion

FOR PUBLICATION

UNITED STATES COURT OF APPEALS FOR THE NINTH CIRCUIT

ASPIC ENGINEERING AND No. 17-16510 CONSTRUCTION COMPANY, Plaintiff-Appellant, D.C. No. 4:17-cv-00224- v. YGR

ECC CENTCOM CONSTRUCTORS LLC; ECC INTERNATIONAL LLC, OPINION Defendants-Appellees.

Appeal from the United States District Court for the Northern District of California Yvonne Gonzalez Rogers, District Judge, Presiding

Argued and Submitted December 17, 2018 San Francisco, California

Filed January 28, 2019

Before: MILAN D. SMITH, JR. and JACQUELINE H. NGUYEN, Circuit Judges, and JANE A. RESTANI, * Judge.

Opinion by Judge Milan D. Smith, Jr.

* The Honorable Jane A. Restani, Judge for the United States Court of International Trade, sitting by designation. 2 ASPIC ENG’G & CONSTR. V. ECC CENTCOM CONSTRUCTORS

SUMMARY **

Arbitration

The panel affirmed the district court’s order vacating under the Federal Arbitration Act an arbitration award concerning the termination for convenience of two subcontracts for the construction of buildings and facilities in Afghanistan.

The subcontracts were in support of defendants’ prime contracts with the U.S. Army Corps of Engineers. The subcontracts incorporated by reference Federal Acquisition Regulation (“FAR”) clauses governing termination for convenience, and they contained a clause mandating that plaintiff, a local company, owed to defendants the same obligations that defendants owed to the U.S. government. Voiding parts of the subcontracts, the arbitrator awarded plaintiff some of its claimed costs despite plaintiff’s failure to comply with FAR requirements.

The panel held that, in finding that plaintiff need not comply with the FAR provisions, the arbitrator exceeded his powers and failed to draw the essence of the award from the subcontracts. The arbitrator’s award was “irrational” because he improperly based his conclusion not on past practices, but on his rationalization that to enforce the FAR clauses on plaintiff would be unjust.

** This summary constitutes no part of the opinion of the court. It has been prepared by court staff for the convenience of the reader. ASPIC ENG’G & CONSTR. V. ECC CENTCOM CONSTRUCTORS 3

COUNSEL

Walt Pennington (argued), Pennington Law Firm, San Diego, California, for Plaintiff-Appellant.

Joseph G. Martinez (argued), Dentons US LLP, Denver, Colorado; Andrew S. Azarmi, Dentons US LLP, San Francisco, California; for Defendants-Appellees.

OPINION

M. SMITH, Circuit Judge:

In this opinion, we review the award to Aspic Engineering and Construction Company (Aspic) following arbitration between Aspic and ECC Centcom Constructors, LLC and ECC International, LLC (together, ECC). ECC and Aspic entered into arbitration to resolve how much money ECC owed Aspic after ECC terminated for convenience two subcontracts it had awarded to Aspic. The arbitrator awarded Aspic just over $1 million, but ECC sought successfully to vacate the award in the district court. We affirm the district court’s vacation of the arbitration award.

FACTUAL AND PROCEDURAL BACKGROUND

I. The Subcontracts

In support of its prime contracts with the United States Army Corps of Engineers (USACE), ECC awarded Aspic two subcontracts for the construction of various buildings and facilities in Afghanistan. The first was to be performed in Badghis province (the Badghis Subcontract). The second required the construction of a training facility in Sheberghan province (Sheberghan Subcontract). 4 ASPIC ENG’G & CONSTR. V. ECC CENTCOM CONSTRUCTORS

The Badghis Subcontract and the Shebergan Subcontract (together, the Subcontracts) contained terms and conditions “applicable to all U.S. Government subcontracts.” Specifically, the Subcontracts incorporated many Federal Acquisition Regulation (FAR) 1 clauses by reference, or in haec verba. These clauses included FAR 49.2 through 49.6, which govern termination for convenience. The Subcontracts also contained the following clause mandating that Aspic owe to ECC the same obligations that ECC owed to the United States government, as set forth in the FAR clauses: “The obligations of [ECC] to the Government as provided in said clauses shall be deemed to be the obligations of Subcontractor to [ECC].”

USACE eventually terminated ECC’s prime contract for convenience on the Badghis project. Days later, ECC notified Aspic that it was terminating the Badghis Subcontract for convenience. Understandably, Aspic sought payment for its expenses. On February 9, 2014, Aspic submitted its termination settlement proposal for the Badghis project to ECC. After review, ECC informed Aspic that the corroborative documents it had submitted in support of its settlement proposal were inadequate, and Aspic admitted it did not have many of the required materials. Nevertheless, ECC eventually submitted its termination settlement proposal to USACE, and included Aspic’s claim for $229,915 in termination costs within that proposal.

Upon receipt of the termination settlement proposal, USACE notified ECC that it would not pay any of ECC’s subcontractor termination costs—including the money Aspic claimed it was owed—until the Defense Contract

1 Title 48 of the Code of Federal Regulations contains the FAR regulations. ASPIC ENG’G & CONSTR. V. ECC CENTCOM CONSTRUCTORS 5

Audit Agency had conducted an audit. Following that audit, USACE informed ECC that it had overpaid Aspic for its performance under the Badghis Subcontract. In light of that determination, USACE refused to pay any of Aspic’s claimed termination costs.

USACE also terminated ECC’s contract for the Sheberghan project for convenience. Two days later, ECC terminated the Sheberghan Subcontract for convenience.

Aspic again submitted a termination settlement proposal to ECC, this time requesting $1,032,462. ECC, however, did not present these claimed costs to the USACE. USACE eventually issued a no-cost termination settlement between USACE and ECC—a settlement in which USACE claimed that the money previously paid to ECC and its subcontractors, including Aspic, constituted adequate compensation.

II. Prior Proceedings

Aspic believed it deserved more money for its efforts under the Subcontracts. In August 2015, it submitted a settlement demand for $652,000 on the Sheberghan Subcontract. ECC refused to pay, so Aspic filed for arbitration. Aspic again tried to settle the dispute—issuing settlement offers of $830,000 to ECC Centcom Constructors and $150,000 to ECC International—but ECC did not accept either of these offers.

In accordance with the Subcontracts, the parties proceeded to arbitration. 2 The Arbitrator issued a Partial 2 Part A “General Terms and Conditions” of the Subcontracts contained provisions requiring arbitration for disputes arising from the contracts and the application of California law. 6 ASPIC ENG’G & CONSTR. V. ECC CENTCOM CONSTRUCTORS

Final Award, awarding Aspic $1,072,520.90 and holding ECC Centcom Constructors and ECC International jointly and severally liable for the total amount. Aspic then sought attorneys’ fees and costs. Contemporaneously, ECC moved to reduce the Partial Final Award by Aspic’s waived damages, and opposed Aspic’s request by arguing that each party ought to bear its own attorneys’ fees. The Arbitrator’s Final Award (the Award) incorporated the Partial Final Award, denied attorneys’ fees and costs, and awarded Aspic half of the administrative fees and expenses.

Aspic filed a petition in the Superior Court for San Mateo County, California seeking to confirm the Award. Aspic also sought to reverse the Arbitrator’s determination that it was not entitled to attorneys’ fees.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
913 F.3d 1162, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aspic-engineering-and-constr-v-ecc-centcom-constructors-llc-ca9-2019.