ARCO National Construction, LLC v. MCM Management Corp.

CourtDistrict Court, D. Maryland
DecidedSeptember 4, 2024
Docket1:20-cv-03783
StatusUnknown

This text of ARCO National Construction, LLC v. MCM Management Corp. (ARCO National Construction, LLC v. MCM Management Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ARCO National Construction, LLC v. MCM Management Corp., (D. Md. 2024).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

ARCO NATIONAL CONSTRUCTION, LLC, f/k/a ARCO NATIONAL CONSTRUCTION COMPANY, INC.,

Plaintiff, Civil No.: 1:20-cv-03783-JRR

v.

MCM MANAGEMENT CORP.,

Defendant.

MEMORANDUM OPINION Plaintiff ARCO National Construction, LLC f/k/a ARCO National Construction Company, Inc. (“ARCO”) initiated this breach of contract action against Defendant MCM Management Corp. (“MCM”). (ECF No. 1; the “Complaint”). Pending now before the court is MCM’s Motion to Compel Arbitration (ECF No. 57; the “Motion”). The court has reviewed all papers; no hearing is necessary. Local Rule 105.6 (D. Md. 2023). For the reasons that follow, by accompanying order, the Motion will be granted. I. BACKGROUND This action arises out of a contract dispute between a general contractor, ARCO, and one of its subcontractors, MCM. The court incorporates the extensive background set forth in its memorandum opinion on the parties’ cross motions for summary judgment. (ECF No. 48 at p. 1– 6.) At the center of the parties’ dispute are two contracts—a subcontract for work on a construction project and a subsequently executed settlement agreement. On or about August 10, 2015, the parties entered into a subcontract agreement (the “Subcontract”) pursuant to which MCM agreed to perform excavation and utility installation services on the FedEx Ground-Sparrows Point project in Baltimore, Maryland (the “Project”). (ECF Nos. 1-1.) The Subcontract contains an arbitration provision that provides: “Any controversy or claim arising out of or relating to this contract, or the breach thereof, shall be finally resolved by arbitration administered by the American Arbitration Association under its

Construction Industry Arbitration Rules . . . .” (ECF No. 1-1 ¶ 4.9; the “Arbitration Provision”). During the course of the Project, a dispute arose between the parties pertaining to the balance ARCO owed MCM under the Subcontract. (ECF No. 9.) On May 9, 2017, the parties executed a “Settlement Agreement” resolving the disputes regarding the Project.1 Id. The Settlement Agreement incorporates by reference Change Order #25-S (“CO 25-S”) (ECF No. 9 ¶ 2 and at p. 7), which provided for an adjustment of the “Subcontract Sum” and added to MCM’s “Scope of Work” under the Subcontract. Id. A. The Michigan Litigation Prior to ARCO’s institution of the present action, MCM filed a complaint against ARCO in the Circuit Court for Wayne County, Michigan (Case No. 20-009960-CB) on August 5, 2020

(the “Michigan Litigation”). (ECF No. 58-1; “Michigan Litigation Compl.”) MCM advanced three claims in the Michigan Litigation—tortious interference with contract, tortious interference with prospective economic advantage, and for declaratory relief. Id. The tortious interference claims both arose from ARCO’s interference in MCM’s contract and relationship with another entity. Id. The declaratory relief claim sought declaratory judgment related to MCM’s obligations under CO 25-S, specifically that it was not required to perform where there was a dispute of whether “ARCO prevented and refused to allow MCM to perform under [CO 25-S],” and thus

1 “MCM and ARCO have now agreed to settle their dispute in connection with the Project, the Subcontract and the Lawsuits.” (ECF No. 9 ¶ H.) relieving MCM’s duty of performance. Id. ¶¶ 48–50. In the Michigan Litigation Complaint, MCM also asserted, inter alia, the following allegations: 8. MCM and Arco entered into a Subcontract Agreement dated August 10, 2015, and subsequent Change Orders numbered 1-25 (collectively, the “Subcontract”), wherein MCM agreed to provide excavation and utility installation services for the construction of a sorting facility on property located in Baltimore, MD, commonly known as “Sparrow’s Point” (the “Project”) . . . .

13. On May 14, 2017, MCM and Arco executed Change Order #/25- S (“CO #25-S”) in connection with certain landfill clean-up work to be performed on the Project, specifically at the Scannell FedEx Ground site (“Scannell Site”).

14. Under the terms of CO #25-S, if MCM completed the removal of certain materials at the Scannell site, MCM would receive a $50,000.00 increase to its payment under the Subcontract.

15, Pursuant to CO #25-S, if the MCM did not complete the work at the Scannell site by a date certain and/or the Owner did not accept MCM’s performance, MCM and Arco agreed that MCM would not be entitled to the $50,000.00 increase to MCM’s payment under the Subcontract and there would be “...no further change order or action by either party,” and MCM and Arco would go their separate ways . . . .

17. An issue arose between Arco and the Owner, which had no bearing on MCM’s ability to perform the work at the Scannell site.

18. The work to be performed by MCM at the Scannell site was within Arco’s scope of work in its contract with the Owner, and Arco demanded that the Owner provide Arco a release for the work to be performed by MCM.

19. Because of its issue with the Owner, Arco refused to allow MCM to perform the work at the Scannell site . . . .

23. On information and belief, another dispute arose between the Owner and Arco regarding the Scannell site when the Owner refused to release certain retained funds it withheld from Arco on the Project, in part because Arco never performed the work at the Scannell site and never authorized MCM to perform the work it agreed to perform. 24. Arco made materially false statements to the Owner, blaming MCM for not performing the work at the Scannell site.

25. Arco knew that its statements to the Owner were false when they were made because CO #25-S expressly provided that if the Owner did not accept MCM’s performance, there would be no further change order or action by either MCM or Arco, and it was Arco that prevented MCM from performing according to the terms of CO #25- S.

26. Arco’s false statements caused the Owner to withhold retained funds owed to MCM under the Owner Contract, in addition to withholding funds owed to Arco for the Project.

(Michigan Litigation Compl., ECF No. 58-1 ¶¶ 8, 13–15, 17–19, 23–26.) “Subcontract Sum” and “Scope of Work” are terms defined by the Subcontract. Subcontract Sum is defined under Article 2, Subcontract Sum and Progress Payments of the Subcontract. Article 2 of the Subcontract defines Subcontract Sum, and sets out other obligations of the parties not contained in the Settlement Agreement, including ARCO’s “Right to Withhold Payment & Other Remedies.” (ECF No. 1-1 ¶ 2.6.) B. The Present Action ARCO initiated this action against MCM on December 30, 2020, asserting one breach of contract claim based on allegations related to the Subcontract and Settlement Agreement. (ECF No. 1.) MCM moved to dismiss the Complaint, offering substantive arguments about the amount in controversy, the statute of limitations, the Subcontract being subsumed by the Settlement Agreement, and failure to state a claim. (ECF No. 10-1.) MCM also asserted that “[t]he Subcontract contains an arbitration clause, which is yet another reason this Court should dismiss Plaintiff’s claims as they relate to the Subcontract,” and that ARCO’s Complaint was facially deficient because, inter alia, ARCO “ignored the [A]rbitration [P]rovision in the Subcontract.” Id. at p. 9 n.1, 12. In response to MCM, ARCO “concede[d]” that the Settlement Agreement subsumed the Subcontract. (ECF No. 12-1 at p. 13.) Thereafter, Judge Hollander (then presiding) issued a decision, denying the motion and noting:

In its Opposition, ARCO “concedes” that the Subcontract is no longer the operative agreement. It explains that “the Settlement Agreement subsum[ed] the Subcontract.” Therefore, plaintiff contends that it relies on the terms of the Settlement Agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prima Paint Corp. v. Flood & Conklin Mfg. Co.
388 U.S. 395 (Supreme Court, 1967)
United States v. Olano
507 U.S. 725 (Supreme Court, 1993)
Allied-Bruce Terminix Cos., Inc. v. Dobson
513 U.S. 265 (Supreme Court, 1995)
Green Tree Financial Corp.-Alabama v. Randolph
531 U.S. 79 (Supreme Court, 2000)
Abramson v. Wildman
964 A.2d 703 (Court of Special Appeals of Maryland, 2009)
RTKL Associates, Inc. v. Four Villages Ltd. Partnership
620 A.2d 351 (Court of Special Appeals of Maryland, 1993)
Bargale Industries, Inc. v. Robert Realty Co.
343 A.2d 529 (Court of Appeals of Maryland, 1975)
Commonwealth Equity Services, Inc. v. Messick
831 A.2d 1144 (Court of Special Appeals of Maryland, 2003)
Charles J. Frank, Inc. v. Associated Jewish Charities of Baltimore, Inc.
450 A.2d 1304 (Court of Appeals of Maryland, 1982)
Redemptorists v. Coulthard Services, Inc.
801 A.2d 1104 (Court of Special Appeals of Maryland, 2002)
Stauffer Construction Co. v. Board of Education
460 A.2d 609 (Court of Special Appeals of Maryland, 1983)
Chertkof v. Southland Corp.
371 A.2d 124 (Court of Appeals of Maryland, 1977)
Cunningham v. Feinberg
107 A.3d 1194 (Court of Appeals of Maryland, 2015)
Cain v. Midland Funding, LLC
156 A.3d 807 (Court of Appeals of Maryland, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
ARCO National Construction, LLC v. MCM Management Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/arco-national-construction-llc-v-mcm-management-corp-mdd-2024.