ARCO National Construction, LLC v. MCM Management Corp.

CourtDistrict Court, D. Maryland
DecidedSeptember 10, 2021
Docket1:20-cv-03783
StatusUnknown

This text of ARCO National Construction, LLC v. MCM Management Corp. (ARCO National Construction, LLC v. MCM Management Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ARCO National Construction, LLC v. MCM Management Corp., (D. Md. 2021).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

ARCO NATIONAL CONSTRUCTION, LLC f/k/a ARCO NATIONAL COMPANY, INC. Plaintiff, Civil Action No. ELH-20-3783

v.

MCM MANAGEMENT CORP. Defendants.

MEMORANDUM OPINION

This breach of contract case pits a general contractor, plaintiff ARCO National Construction, LLC f/k/a ARCO National Company, Inc. (“ARCO”), against its subcontractor, defendant MCM Management Corp. (“MCM”). ECF 1 (the “Complaint”). ARCO asserts that MCM failed to complete “landfill clean up” services as required under a contract as well as a subsequent “Settlement Agreement.” Id. ⁋ 8, 18. According to ARCO, as a result of MCM’s breach of contract, ARCO will be required to complete work that MCM was contractually obligated to perform, resulting in damages “in the amount of at least $650,000.00, plus attorney’s fees and other costs.” Id. ⁋ 19. Plaintiff has appended to the Complaint a copy of the original Subcontract (ECF 1-1), the Change Orders associated with the Subcontract (ECF 1-2), and the parties’ Settlement Agreement (ECF 1-3; ECF 9).1

1 Plaintiff initially filed a notice with the Complaint (ECF 1-3), indicating that it would file a document under seal. It subsequently docketed the Settlement Agreement under seal at ECF 4- 1. On January 4, 2021, I ordered plaintiff to submit a redacted version, appropriate for the public docket, or, alternatively, to explain why the Settlement Agreement should remain under seal. ECF 7. On January 20, 2021, ARCO docketed the Settlement Agreement, with minor redactions. See ECF 9. Therefore, I shall grant ECF 3, plaintiff’s unopposed Motion to Seal. Throughout this opinion, I shall cite to the Settlement Agreement at ECF 9. MCM has moved to dismiss the Complaint, pursuant to Fed. R. Civ. P. 12(b)(1) and Fed. R. Civ. P. 12(b)(6), or, in the alternative, for summary judgment, pursuant to Fed. R. Civ. P. 56. ECF 10. The motion is supported by a memorandum of law (ECF 10-1) (collectively, the “Motion”) and two exhibits. ECF 10-2; ECF 10-3. Plaintiff opposes the Motion (ECF 12; ECF 12-1) (collectively, the “Opposition”), accompanied by an affidavit from one of its officers (ECF

12-3). MCM has replied. ECF 13 (the “Reply”). No hearing is necessary to resolve the Motion. See Local Rule 105.6. For the reasons that follow, I shall deny the Motion. I. Factual Background

In August 2015, ARCO entered into a contract (“Subcontract”) with MCM, wherein MCM agreed to provide excavation and utility installation services for the construction of a sorting facility, known as the “FedEx Ground – Sparrows Point” (the “Project”), located in Baltimore. ECF 1, ⁋ 5; ECF 1-1 at 1. Under the terms of the Subcontract, ARCO agreed to pay MCM $220,590 for the work, as well as further compensation for all agreed upon change orders. ECF 1, ⁋ 6; ECF 1-1 at 1. The Subcontract ultimately reached a total of $10,105,908.23. ECF 1, ⁋ 6; ECF 9 at 7; see generally ECF 1-2. At some point before May 2017, a dispute arose between ARCO and MCM pertaining to an alleged outstanding payment MCM claimed it was owed, over and above the terms of the Subcontract. ECF 1, ⁋ 7. In May 2017, ARCO and MCM reached an agreement resolving their dispute, the terms of which were memorialized in the “Settlement Agreement.” Id.; ECF 9. The Settlement Agreement expressly provides that MCM and ARCO “settled their dispute in connection with the Project, the Subcontract, and the Lawsuits.” ECF 9 at 1. Notably, the Settlement Agreement incorporates Change Order #25-S (“Change Order”), which “provides for” an upward “adjustment of the aggregate Subcontract Sum” in the amount of $150,000, and “adds work to the Subcontract Scope of Work to be performed by MCM.” ECF 9 at 2, ⁋ 2(b). Affirming MCM’s outstanding obligations, the Subcontractor Final Payment Affidavit, Release, and Waiver of Liens, an exhibit incorporated in the Settlement Agreement,

provides that MCM “completed all of its work on the Project, except for the work described in Change Order #25-S.” Id. at 14, ⁋ 1(a). The Change Order specifies that ARCO would pay $100,000 to MCM “pursuant to the Settlement Agreement,” as well as an additional $50,000 for “Landfill clean up” services, if those services were completed by May 26, 2017, and to the satisfaction of the project owner, Tradepoint Atlantic, LLC (“TPA”). Id. at 7.2 If TPA failed to accept the work by the completion date, however, the Change Order provides that the “Subcontract Sum” would be “automatically reduced” by $50,000. Id. 3

2 There appears to be some confusion over TPA’s role in the Project. In its Complaint, ARCO identified TPA as the Project’s owner. ECF 1, ⁋ 9. Defendant also identified TPA as the owner. ECF 10-1 at 1; ECF 13 at 2. However, the terms of the Settlement Agreement and plaintiff’s Opposition indicate that TPA was instead the Project’s landlord, while another party, Scannell Properties #191, LLC (“Scannell”), is the Project’s owner. ECF 12-1 at 2, ⁋⁋ 1-2; ECF 9 at 10, 14. 3 Change Order #25-S states, in part, as follows, ECF 9 at 7: YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THIS SUBCONTRACT

Item # Phase Description Amount 1 02-1100 Settlement amount payable pursuant to Settlement $100,000.00 Agreement dated May 2017 between Contractor and Subcontractor.

2 02-1100 Landfill clean-up – Removal of all visible and/or known $50,000.00 rock, brick, concrete, and debris larger than 6”. Removal ARCO asserts, and MCM does not dispute, that MCM failed to meet the deadline contemplated by the Change Order. ECF 1, ⁋ 10. The Complaint alleges that, “following the issuance of CO #25S, MCM made representations to ARCO that the work was being performed, and /or that it was negotiating with the Owner to revise the agreed scope of work.” Id. Further, ARCO claims that during the ensuing three years, and as late as January 2019, TPA communicated

several confirmations to ARCO that “MCM was continuing to perform its work” and that the work would soon be completed. Id. ⁋ 10-11. However, on July 24, 2020, ARCO “was formally informed by [TPA] that [MCM’s] work was never completed and that MCM now refuses to complete its scope of work,” as required by the Change Order. Id. ⁋ 12. Therefore, ARCO asserts that it “will be required to complete the work that MCM is contractually obligated to perform, at significant cost to ARCO . . . .” Id. Thereafter, on December 30, 2020, ARCO filed this suit. Jurisdiction is founded on diversity of citizenship. See 28 U.S.C. § 1332(a).

of all wood, railroad ties and other material that cannot be processed as part of any future soil remediation. All material to be hauled to an MCM controlled location or other mutually agreed to location with TPA. As part of this Scope of Work, MCM will secure a letter of approval from TPA acknowledging that the landfill clean-up work is complete. Upon receipt of this letter of approval, ARCO will release payment for the landfill clean-up. This work will be completed and accepted in writing by TPA no later than May 26, 2017 (Completion Date). If this landfill clean-up scope is not completed by the Completion Date, or if Contractor has not received written acceptance from TPA of this work by the Completion Date, then the Subcontract Sum will be automatically reduced by $50,000 without further change orders or action by either party.

Total $150,000.00 MCM, for its part, alleges that it was “immediately ready, willing, and able to perform the work called for” in the Change Order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tapscott v. MS Dealer Service Corp.
77 F.3d 1353 (Eleventh Circuit, 1996)
Strawbridge v. Curtiss
7 U.S. 267 (Supreme Court, 1806)
McNutt v. General Motors Acceptance Corp.
298 U.S. 178 (Supreme Court, 1936)
Saint Paul Mercury Indemnity Co. v. Red Cab Co.
303 U.S. 283 (Supreme Court, 1938)
Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Hanna v. Plumer
380 U.S. 460 (Supreme Court, 1965)
Papasan v. Allain
478 U.S. 265 (Supreme Court, 1986)
Kokkonen v. Guardian Life Insurance Co. of America
511 U.S. 375 (Supreme Court, 1994)
Swierkiewicz v. Sorema N. A.
534 U.S. 506 (Supreme Court, 2002)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
ROBB EVANS & ASSOCIATES, LLC v. Holibaugh
609 F.3d 359 (Fourth Circuit, 2010)
McBurney v. Cuccinelli
616 F.3d 393 (Fourth Circuit, 2010)
JTH Tax, Inc. v. Frashier
624 F.3d 635 (Fourth Circuit, 2010)
Glassman v. Arlington County, VA
628 F.3d 140 (Fourth Circuit, 2010)
Kendall v. Balcerzak
650 F.3d 515 (Fourth Circuit, 2011)
In Re Kunstler.
914 F.2d 505 (Fourth Circuit, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
ARCO National Construction, LLC v. MCM Management Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/arco-national-construction-llc-v-mcm-management-corp-mdd-2021.