Appalachian Power Co. v. Public Service Commission

614 F. Supp. 64, 1985 U.S. Dist. LEXIS 22220
CourtDistrict Court, S.D. West Virginia
DecidedFebruary 28, 1985
DocketCiv. A. 85-0098
StatusPublished
Cited by3 cases

This text of 614 F. Supp. 64 (Appalachian Power Co. v. Public Service Commission) is published on Counsel Stack Legal Research, covering District Court, S.D. West Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Appalachian Power Co. v. Public Service Commission, 614 F. Supp. 64, 1985 U.S. Dist. LEXIS 22220 (S.D.W. Va. 1985).

Opinion

MEMORANDUM OPINION ON PRELIMINARY INJUNCTION ORDER

DENNIS R. KNAPP, Senior District Judge.

This case is presently before the Court on plaintiffs’ Motion for a Preliminary Injunction pursuant to Rule 65 of the Federal Rules of Civil Procedure.

Plaintiffs seek injunctive relief preliminarily to enjoin the Public Service Commission of West Virginia (PSC) and its individual commissioners from enforcing and implementing a portion of a PSC order entered on December 28, 1984, in Case No. 83-697-E-42T, which (1) requires Appalachian Power Company (Appalachian) to submit to the PSC for its approval under the provisions of W.Va. Code, 24-2-12, 1 a transmission equalization agreement among Appalachian and four of its affiliated companies, all of which are subsidiaries of American Electric Power Company, Inc., and plaintiffs in this action, and (2) denies Appalachian recovery from its customers in West Virginia of $1.6 million in costs to be incurred under that agreement commencing January 22, 1985, until after the PSC has approved the agreement and has found the costs resulting therefrom to be reasonable for inclusion in Appalachian’s rates.

The issues herein having been fully briefed and argued, the Court now makes its Findings of Fact and Conclusions of Law based upon the stipulation of facts signed by the parties and the testimony adduced at the hearing.

FINDINGS OF FACT

1. The American Electric Power System consists of a parent holding company, American Electric Power Company, Inc. (AEP), and various subsidiary companies wholly owned by AEP. AEP’s subsidiaries include, among others, five electric utility operating companies, Appalachian, Kentucky Power Company (KPC), Columbus and Southern Ohio Electric Company (C & SOE), Indiana & Michigan Electric Company (I & M), and Ohio Power Company (OPC) (collectively the “AEP System companies” or “members”). AEP and the System companies are the plaintiffs in this action.

2. Appalachian, a Virginia corporation, operates in the states of West Virginia and Virginia and is subject to regulation of its intrastate rates for retail electric service provided to customers in West Virginia by the defendant PSC.

3. AEP, KPC, C & SOE, I & M and OPC are, respectively, New York, Kentucky, Ohio, Indiana and Ohio corporations and none is subject to the regulatory jurisdiction of the defendant PSC. The four last-named companies operate as electric utilities exclusively in the states in which they are incorporated except that I&M also operates as an electric utility in Michigan. The AEP System operating companies, including Appalachian, supply electric energy to residential, commercial and industrial customers and public authorities collectively in seven states, including Appalachian in its twenty-one county service area in Southern West Virginia.

4. Defendant PSC was established by the Legislature of West Virginia with power to sue and be sued, and under the provisions of Chapter 24 of the Code of West Virginia has regulatory jurisdiction over the intrastate activities of Appalachian in West Virginia. Defendants Otis D. Casto and Michael D. Greer, the new Chairman of the PSC, are members of and presently constitute the PSC and were members of *67 the Commission at the time it issued its order of December 28, 1984, in PSC Case No. 83-697-E-42T. The third membership on the PSC was recently filled by Charlotte Lane.

5. The AEP System companies are parties to an Interconnection Agreement, dating back to July 6, 1951, which was designed to provide customers of members of the AEP System the benefits and advantages of large scale, coordinated operation and planning of electric supply facilities owned by, or available to, member companies. One of the features of this agreement is a primary capacity equalization charge. This charge fixes the rate at which AEP System companies purchase electric generating capacity from each other to supplement the generating capacity of their own systems to meet customer demands and reserve requirements. AEP System companies with generating capacity deficits make payments to those companies with surplus generating capacity in amounts in accordance with the methodology in the Interconnection Agreement. Thus, that Agreement essentially provides for an equalization of the AEP System companies’ investment in electric generation facilities.

6. The electric generation facilities and load centers of the AEP System companies are interconnected by means of an extensive interstate network of transmission lines. The interconnection of said generation facilities allows them to be planned and operated as a single, fully integrated electric system. This interstate network of transmission lines traverses the extensive geographic area in which the AEP System companies operate and stretches some 400 miles from the Illinois border in the west to the Pennsylvania border in the east, and some 500 miles from Southwest Michigan in the north to the North Carolina border in the south. Not only does this network of transmission lines tie together the various generating plants and load centers of the AEP System companies, but it also makes possible 142 interconnections with 25 unaffiliated utilities as of January 1, 1985.

7. Each of the five major AEP System companies owns and maintains that part of the AEP System interstate network of transmission lines that is physically located in its state or designated area, and with a single exception of one transmission line located in Indiana, the financial responsibility for each mile of this interstate network of transmission lines has been borne by the AEP System member in whose state or designated area the transmission facilities are located.

8. The disparity between the amount of investment made by each AEP System company in the Extra High Voltage (345 KV, 500 KV, and 765 KV) (EHV) transmission network and the usage of that network by each such company has grown in recent years and is expected to grow in the future. Because of the AEP System companies’ belief that fairness requires that they should begin to equalize the costs associated with ownership and operation of the AEP System interstate network of EHV transmission facilities by sharing the total cost of that System through appropriate monthly equalization payments under a concept of having its responsibility in proportion to its maximum load, similar to the equalization of the AEP System companies’ investment in electric generation facilities as embodied in the Interconnection Agreement, the AEP System members entered into a Transmission Agreement, dated April 1, 1984 (the “Transmission Agreement”).

9. The Transmission Agreement provides an equalization formula whereby each AEP System member having an investment in EHV transmission facilities (facilities operating at 765 KV, 500 KV or 345 KV) greater than its Member Load Ratio (MLR) 2 share of the total system EHV investment will be reimbursed for its “surplus” investment by those “deficit” members (including Appalachian) having an *68

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
614 F. Supp. 64, 1985 U.S. Dist. LEXIS 22220, Counsel Stack Legal Research, https://law.counselstack.com/opinion/appalachian-power-co-v-public-service-commission-wvsd-1985.