All Power, Inc. v. United States

60 Fed. Cl. 679, 2004 U.S. Claims LEXIS 127, 2004 WL 1161884
CourtUnited States Court of Federal Claims
DecidedMay 25, 2004
DocketNo. 03-564C
StatusPublished
Cited by2 cases

This text of 60 Fed. Cl. 679 (All Power, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
All Power, Inc. v. United States, 60 Fed. Cl. 679, 2004 U.S. Claims LEXIS 127, 2004 WL 1161884 (uscfc 2004).

Opinion

ORDER AND OPINION DENYING DEFENDANT’S MOTION FOR SUMMARY JUDGMENT

WILLIAMS, Judge.

In this action under the Contract Disputes Act, Plaintiff seeks an equitable adjustment to its contract to repair a fuel storage tank. Specifically, Plaintiff contends it encountered two differing site conditions: (1) large quantities of a free-flowing compound consisting of jet fuel and oil (free product) in the tank and (2) high lead content in the paint on the tank, requiring lead abatement.1 This matter comes before the Court on Defendant’s Motion for Summary Judgment.2 Because there are genuine issues of material fact, this action cannot be resolved on summary judgment. Accordingly, Defendant’s motion is denied.

[681]*681 Background 3

In response to solicitation number DACA05-00-R-0045, Plaintiff was awarded contract number DACA05-00-C-0024 on September 28, 2000. Pi’s App. at 5. A Notice to Proceed was issued on November 5. Pl.’s App. at 15,17.

The solicitation originally contemplated work on three fuel storage tanks — Tanks 10, 11 and 14, for “all work needed for the repair or replacement of domes, skylights, and seals on tanks 10 and 11, and replacement of tank 14 bottom and seal at the Bulk Fuel Storage Facility.” Pl.’s App. at 1. However, as awarded, the contract only included work on Tank 14. Pl.’s App. at 2,15.

Free Product

The contract described Tank 14 as a cylindrical storage tank 40 feet high with a diameter of 42.5 feet used by the Air Force for storing jet fuel. Pl.’s App. at 19. Section 01010, Summary of the Work, provided that “[t]he general scope and character of the work is indicated on the drawings.” Pl.’s App. at 24. Drawing C2, General Notes, No. 16 stated: “Tank 14 has been drained, cleaned and vapor freed. Tanks 10 and 11 contain JP-8 fuel.” Pl.’s App. 19. Drawing M2 depicted Tank 14 as having two bottoms — an “original bottom” that sits on the ground and a “current bottom” or second bottom that rests on a layer of sand sandwiched between the current and original bottoms. Pl.’s App. at 20. The contract directed Plaintiff to remove and replace the current bottom as well as the sand between the bottoms. Pl.’s App. at 20, 28.

The contract indicated that the sand was contaminated with jet fuel and oil. Section 01351, part 3.7.1.1 stated: “[t]he sand and soil bottom is anticipated to contain fuels from past and/or present fuels.” Def.’s App. at 4. Section 02100, part 3.03(B) provided that the “[sjand shall be considered contaminated with oil” and Drawing M2, Detail 1, provided that “existing sand is contaminated with oil and jet fuel.”4 Pl.’s App. at 20, 28.

Prior to doing any work, Plaintiff was required to drill a hole in the current bottom to test the Lower Explosive Limit (LEL) and oxygen content of the area underneath that bottom.5 Barnes Depo. at 23-24, Def.’s App. at 19-20; Section 02100, part 2.09, Pl.’s App. at 27. An LEL lower than 10% permitted hotwork, while any level above that required a nitrogen purge to reduce explosive levels to within acceptable limits before hotwork could be performed.6 Pl.’s App. at 27.

Plaintiff cut an 8'x8' hole or door sheet into the side of Tank 14 to enter the tank and planned to cut out the bottom using a cutting torch (hotwork). Barnes Depo. at 18-19, 23-24, Def.’s App. at 17-20. When Plaintiff drilled a test hole, free product “came spurting up” from the hole to a height of “about 18 inches” and continued spurting at that level for a couple of days. Barnes Depo. at 31, Def.’s App. at 23. The space beneath the current bottom was so full of free product that it was not possible to use the nitrogen purging procedure. As Plaintiffs site superintendent testified:

Q. And why couldn’t you do what you originally had planned? I can understand if there was sort of standing liquid on top, but I need you to explain to me if you could no longer do what you planned to do?
A. Specs called for us if there were LELs, to drill a series of holes in the [682]*682tank bottoms and inject it with nitrogen, use the nitrogen purge. You can’t purge a space that’s full of product because there’s no place for the purging to go. So you have to use a different procedure completely.
Q. And what different procedure would that have been?
A. You have to flow — you drill the series of holes like this — instead of using nitrogen, you drill bigger holes, and you put taps in there and pump water, Because you need to dilute it down to where your LELs are no longer combustible so you .can pump the water out.
Q. When you pump the water in, you also have to pump it out?
A. Yes.
Q. So to make sure I understand this right, the difference with the sort of free product in there is that — a gaseous way of inserting it wouldn’t work because there would be no space?
A. Correct.

Barnes Depo. at 37-38, Def.’s App. at 26-27.

Plaintiff hired a subcontractor, Foss Environmental Services (Foss), to remove the free product from between the tank bottoms and haul away the contaminated sand. Complaint H 13; Answer 1113.

Lead

Plaintiff also alleges a differing site condition based upon its discovery that the interi- or and exterior of Tank 14 was painted with lead-based paint, requiring lead abatement. Complaint HH 22, 40.

Section 01351, part 3.7 provided in pertinent part:

3.7 Site Description And Contamination Characterization
3.7.1 Project/Site Conditions
The following information is a record of site contaminants and a description of the site. This information is provided to assist in preparing the SSHP [Site Safety Health Plan]. Additional sources of information are available as listed below.
3.7.1.1 Site Information
The tanks for this project currently or most recently have contained JP-8 jet fuel. It has been estimated to be greater than 20 years since the last major repair on these tanks has occurred. As a result, the past contents of these tanks may be present, which may include organic lead and other additives.
The previous coatings on the tanks may have contained lead, cadmium, chromium, mercury, other metals, and potentially polychlorinated biphenyls (PCBs). New coatings are specified as containing organo-tin compounds, isocyanates, fluorinated polyurethane (PTFE), Methyl amyl ketone (MAK), and zinc (zinc base may contain small amounts of lead as a contaminant). In addition, mastics, seals, and gaskets may contain asbestos.

Def.’s App. at 3-4.

Paragraph 3.8.1 Site Tasks and Operations (Workplan) provided in pertinent part:

3.8.1 Site Tasks and Operations (Work-plan)
The SSHP shall include a comprehensive section that addresses the tasks and objectives of the site operations and the logistics and resources required to reach those tasks and objectives.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Extreme Coatings, Inc. v. United States
109 Fed. Cl. 450 (Federal Claims, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
60 Fed. Cl. 679, 2004 U.S. Claims LEXIS 127, 2004 WL 1161884, Counsel Stack Legal Research, https://law.counselstack.com/opinion/all-power-inc-v-united-states-uscfc-2004.