Aldrich v. ADD Inc.

437 Mass. 213
CourtMassachusetts Supreme Judicial Court
DecidedJune 21, 2002
StatusPublished
Cited by47 cases

This text of 437 Mass. 213 (Aldrich v. ADD Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aldrich v. ADD Inc., 437 Mass. 213 (Mass. 2002).

Opinion

Spina, J.

The plaintiffs, trustees of the Seal Harbor III Condominium Trust (trust), brought this action against ADD Inc., an architectural firm (architect), to recover damages for the negligent design of the Seal Harbor III Condominium (condominium). The architect moved for summary judgment on the ground that the plaintiffs’ claim was barred by the economic loss rule. A judge in the Superior Court denied that motion. A second judge granted the architect’s subsequent motion for summary judgment on the ground that the plaintiffs’ claim was time barred by the three-year limitation set forth in G. L. c. 260, § 2B. A third judge denied the plaintiffs’ motion for leave to amend their complaint to add a claim for breach of express warranty. We granted the parties’ joint application for direct appellate review. The issues now before us are whether (1) the second judge erred in concluding that the plaintiffs were the successor in interest to the owner of the property on which the condominium was built and, therefore, were subject to an expired contractual time limitation governing a cause of action between such owner and the architect; (2) the first judge erred in concluding that the plaintiffs’ tort claim against the architect was not barred by the economic loss rule; and (3) the third judge erred in denying the plaintiffs’ motion for leave to amend their complaint. We vacate the allowance of summary judgment based on the theory of successorship, affirm the denial of summary judgment based on the economic loss rule, and remand the case for further proceedings consistent with this opinion.

1. Background. The condominium, located on a peninsula in Winthrop, is a ten-story building containing 117 residential condominium units and approximately 153 parking spaces in an underground garage. As of 1984, a developer, Dolphin Real Estate Corporation (Dolphin), owned the land on which the condominium was to be situated. Dolphin retained the architect to provide design services in connection with the construction of the condominium, which was to be built by Sanford Construction Company, Inc. (contractor).

In late 1984, Dolphin and the architect entered into a standard form of agreement between owner and architect (owner-architect [215]*215as promulgated by the American Institute of Architects. Pursuant to this agreement, the basic services to be provided by the architect included (1) review and evaluation of the project, including the preparation of schematic design documents illustrating the scale and relationship of project components; (2) refinement of the building and site design generated in the schematic design phase; (3) preparation of drawings and specifications for construction that fully complied with all applicable Federal, State, and local laws, ordinances, and codes; and (4) administration of the construction contract between Dolphin and the contractor, including site inspection visits. The architect’s obligations under the owner-architect agreement terminated when final payment to the contractor was due, or sixty days after the date of substantial completion of the work, whichever came first. Dolphin was responsible for such activities as paying construction costs, compensating the architect, and furnishing all legal, accounting, and insurance services as may be necessary.

Construction of the condominium began in the spring of 1986. On July 28, 1987, Dolphin filed a master deed in the Suffolk County registry of deeds, pursuant to G. L. c. 183A, § 2. The master deed identified several entities connected with the condominium: (1) the “Sponsor,” defined as Dolphin and its “successors and assigns”; (2) the trust which, through the plaintiffs, would manage and regulate the condominium; and (3) the unit owners. Dolphin, for itself and its successors and assigns, reserved certain rights and easements to complete construction of the condominium and develop the surrounding land. The architect, with the agreement of Dolphin and the contractor, signed a certificate of substantial completion, designating August 11, 1987, as the date when construction of the condominium would be substantially complete.3 Dolphin began to sell units in the condominium in late August or early [216]*216September, 1987. The final certificate for payment was issued on November 2, 1987.

Starting from the time of completion, there were structural problems in the condominium. During storms, water would penetrate the windows, sliding glass doors, walls, and ceilings. Water also seeped into the underground garage, causing damage to its concrete roof deck and to cars parked below it. The plaintiffs were forced to expend significant sums of money to repair water-damaged common areas.

On July 29, 1993, the plaintiffs filed a complaint against the architect alleging that it had been negligent in designing or selecting materials for use in the construction of the condominium.4 The plaintiffs sought to recover damages for the defective portions of the common areas.5

On November 23, 1994, the architect filed a motion for summary judgment specifically alleging that the plaintiffs’ claim was barred by the economic loss rule. A judge in the Superior Court initially allowed the motion, concluding that the plaintiffs had “not submitted evidence that the defects in the design of the Condominium ‘created a dangerous condition posing a risk of accidental injury to persons or to property other than the physical deterioration attributable solely to the failure of the products of the construction themselves, and ha[d] not claimed any damages other than . . . economic loss, i.e., the cost of repair to the [defective portions of the Condominium common areas], for which there is no recovery in negligence.’ ” Lake Placid Club Attached Lodges v. Elizabethtown Bldrs., Inc., 131 A.D.2d 159, 162 (N.Y. 1987). Following discovery with other parties, the plaintiffs filed a motion pursuant to Mass. R. Civ. P. 54 (b), 365 Mass. 820 (1974), to revise and vacate the judge’s order. The judge allowed the plaintiffs’ motion, stating that newly discovered evidence suggested that the negligent acts of the architect had caused physical harm, primarily the result of [217]*217rain penetration, to common areas of the building, individual units, and cars parked in the garage. The summary judgment record further suggested a possible risk of personal injury from structural or material failure. The judge concluded that the plaintiffs’ claim was not barred by the economic loss rule because the architect’s alleged negligence had caused physical harm to the condominium, for which the plaintiffs had a right to recover.

On September 12, 1997, the architect filed another motion for summary judgment on the grounds that the plaintiffs were Dolphin’s successor under art. 12 of the owner-architect agreement6 and that, consequently, their claim was barred by the applicable three-year limitation, G. L. c. 260, § 2B,7 as contractually refined by such agreement.8 By memorandum of decision and order, a Superior Court judge allowed the architect’s motion. He agreed that the plaintiffs were Dolphin’s “successor,” merely stepping into Dolphin’s shoes with respect to the work contracted for with the architect. As such, the plaintiffs were bound by the provisions of the owner-architect agreement, and their cause of action for the architect’s negligence was [218]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Zoll Medical Corporation
D. Massachusetts, 2025
Wood v. Bank of America , N.A.
D. Massachusetts, 2025
Stearns v. Metropolitan Life Insurance Co.
117 N.E.3d 694 (Massachusetts Supreme Judicial Court, 2019)
Reed v. Zak (In re Zak)
573 B.R. 13 (D. Massachusetts, 2017)
Butler v. Candlewood Road Partners, LLC (In re Raymond)
529 B.R. 455 (D. Massachusetts, 2015)
Wyman v. Ayer Properties, LLC
11 N.E.3d 1074 (Massachusetts Supreme Judicial Court, 2014)
Wyman v. Ayer Properties, LLC.
979 N.E.2d 782 (Massachusetts Appeals Court, 2012)
Barret v. Wakefield Crossing, LLC
30 Mass. L. Rptr. 287 (Massachusetts Superior Court, 2012)
In re Heartland Payment Systems, Inc.
834 F. Supp. 2d 566 (S.D. Texas, 2011)
Deheer v. American Academy of Podiatric Practice Management
28 Mass. L. Rptr. 204 (Massachusetts Superior Court, 2011)
Long v. Niles Co.
2010 Mass. App. Div. 43 (Mass. Dist. Ct., App. Div., 2010)
Driscoll v. Toll MA Ltd. Partnership
26 Mass. L. Rptr. 345 (Massachusetts Superior Court, 2009)
Cumis Insurance Society, Inc. v. BJ's Wholesale Club, Inc.
455 Mass. 458 (Massachusetts Supreme Judicial Court, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
437 Mass. 213, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aldrich-v-add-inc-mass-2002.