Albert K. Newlin, Inc. v. Morris

758 So. 2d 222, 99 La.App. 3 Cir. 1093, 2000 La. App. LEXIS 6, 2000 WL 4396
CourtLouisiana Court of Appeal
DecidedJanuary 5, 2000
Docket99-1093
StatusPublished
Cited by8 cases

This text of 758 So. 2d 222 (Albert K. Newlin, Inc. v. Morris) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Albert K. Newlin, Inc. v. Morris, 758 So. 2d 222, 99 La.App. 3 Cir. 1093, 2000 La. App. LEXIS 6, 2000 WL 4396 (La. Ct. App. 2000).

Opinion

758 So.2d 222 (2000)

ALBERT K. NEWLIN, INC.
v.
Millard E. MORRIS, et al.

No. 99-1093.

Court of Appeal of Louisiana, Third Circuit.

January 5, 2000.

*224 R. William Collings, Collings & Collings, Lake Charles, Counsel for Plaintiff/Appellee.

Frank C. Miller, III, Lake Charles, Counsel for Defendant/Appellant.

Court composed of Chief Judge NED E. DOUCET, Jr., Judge MARC T. AMY, Judge GLENN B. GREMILLION.

AMY, Judge.

This action arises out of a dispute between a subcontractor and a general contractor regarding an amount allegedly owed to the subcontractor for work performed in the construction of a personal residence. The general contractor asserted that the court proceedings should be stayed and the parties should be ordered to arbitrate the dispute in accordance with their contract. The trial court denied the motion to stay and determined that the general contractor had waived its right to arbitration. This action proceeded to trial and the trial court rendered judgment in favor of the subcontractor. We affirm in part and reverse in part.

Factual and Procedural Background

On June 3, 1994, Millard E. Morris, the prospective homeowner, entered into a contract with Ribbeck Construction Corporation (Ribbeck), as general contractor, for the construction of a home in DeRidder, Louisiana. The price agreed upon for construction of the residence was $1,433,550.00. Ribbeck then subcontracted with Albert K. Newlin, Inc. (Newlin), on June 31, 1994, to perform the plumbing and electrical portion of the contract for the total sum of $175,066.00.

After a substantial amount of work had been completed, a dispute arose between Morris and Ribbeck regarding the construction of the residence, which eventually led to the termination of Ribbeck as general contractor. Ribbeck instituted arbitration proceedings against the owner for wrongful termination and for payment of work performed. The arbitration panel determined that Ribbeck's termination was without cause and issued an award to Ribbeck. The arbitration panel found that the final contract price, after adjustment for extra and deleted work, totaled $1,271,071.00. The contract price was credited with payments already made to Ribbeck in the amount of $967,000.00. The panel also determined that $182,629.00 worth of work remained to complete the home. After adding $13,076.00 in delay damages, Ribbeck's total award was $134,482.00.

On August 7, 1997, Newlin filed suit to enforce a materialmen's lien against Morris, Ribbeck, and United States Fidelity & Guaranty Company in the sum of $69,069.73, for material and labor allegedly provided by Newlin under the subcontract with Ribbeck.[1] Thereafter, Ribbeck filed *225 a reconventional demand against Newlin alleging that Newlin owed it a proportionate share of attorney's fees and arbitration cost, which Ribbeck had incurred during its arbitration with Morris.

The matter was set for trial on March 24, 1998. However, after several continuances, this matter was eventually heard on March 17, 1999. Prior to trial, on March 12, 1999, Ribbeck filed a motion to stay the proceedings alleging that Newlin was bound by the subcontract with Ribbeck to submit any dispute arising out of its subcontract to arbitration. The trial court considered Ribbeck's motion to stay on the day of trial. The trial court determined that Ribbeck waived its right to have the case arbitrated by failing to timely raise the question and since Ribbeck, in filing a motion for continuance on January 19, 1999, specifically requested that the case be re-fixed for trial on the next available date. After dismissing Ribbeck's motion to stay, the trial court proceeded to hear the merits of the action.

After considering all of the evidence adduced at trial, the trial court concluded that Newlin was entitled to $36,534.42. The sum represented the contract price, including written authorized change orders to the subcontract and the undisputed unwritten change orders, less credit for payment Newlin had received, and the cost of work to be completed. Further, the trial court dismissed Ribbeck's claim for attorney's fees, which had been raised by Ribbeck in its reconventional demand. Ribbeck appeals the trial court's decision asserting several assignments of error.

Discussion of the Merits

Ribbeck, in its first several assignments of error, advances various reasons why the trial court erred in denying its motion to stay the proceedings and ordering arbitration. Principally, Ribbeck contends that the subcontract signed by Newlin contains a provision which binds the parties to settle all claims and disputes between the subcontractor and the general contractor arising out of or related to the subcontract, through arbitration. Though the trial court ultimately determined that Ribbeck had the right to have its dispute with Newlin arbitrated, it determined that Ribbeck waived that right by not timely raising the issue and by specifically requesting a trial date.

Subject Matter Jurisdiction

We first address Ribbeck's assertion that the trial court lacked subject matter jurisdiction to decide the issue of waiver. Ribbeck argues that once confronted with a request for arbitration, the only issues a court may consider are whether a valid agreement to arbitrate exists and whether a party has refused or failed to comply with a request to arbitrate. In support of this contention, Ribbeck cites: Standard Company of New Orleans, Inc. v. Elliott Construction Co., Inc., 363 So.2d 671 (La.1978); Bartley, Inc. v. Jefferson Parish School Board, 302 So.2d 280 (La.1974); Willis-Knighton Medical Center v. Southern Builders Inc., 392 So.2d 505 (La.App. 2 Cir.1980). We find this line of jurisprudence distinguishable from the instant matter however, and conclude that it does not prohibit an exercise of subject matter jurisdiction by the trial court under the present circumstances.

The cases cited by Ribbeck are instances in which a party aggrieved by the failure or refusal of another to perform under a written agreement to arbitrate, petitions the court, in accordance with La.R.S. 9:4203, for an order directing arbitration to proceed.[2] In those instances, the courts *226 have held that the only triable issues before the court are whether a valid agreement to arbitrate exists and whether a party has refused or failed to comply with a request to arbitrate. See Bartley, Inc., 302 So.2d 280; Elliott, 363 So.2d 671. Thereafter, if the court makes such a determination, then interpretation of and compliance with the procedures of the contract and the question of contractual waiver are issues of procedural arbitrability that should be decided by an arbitrator rather than the courts. Id. See also Conagra Poultry Co. v. Collingsworth, 30,155 (La.App. 2 Cir. 1/21/98); 705 So.2d 1280.

However, the instant matter is not one in which a party has filed suit seeking enforcement of an arbitration agreement pursuant to La.R.S. 9:4203. Rather, Ribbeck filed an action to enforce a materialmen's lien and only after the matter was ready for trial did it file a motion to stay seeking performance of the arbitration agreement. In I.D.C., Inc. v. McCain-Winkler Partnership, 396 So.2d 590 (La. App. 3 Cir.1981), a panel of this court concluded that the limited subject matter jurisdiction, explained by the supreme court in Bartley and Elliott is inapplicable to a situation wherein a party seeks enforcement of an arbitration agreement while participating in an ongoing judicial proceeding.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rathborne v. Rathborne
999 So. 2d 816 (Louisiana Court of Appeal, 2008)
Lagrange v. Dynamic Industries, Inc.
875 So. 2d 1059 (Louisiana Court of Appeal, 2004)
Ricky Lagrange v. Dynamic Industries, Inc.
Louisiana Court of Appeal, 2004
West v. Bruner Health Group, Inc.
866 So. 2d 260 (Louisiana Court of Appeal, 2003)
Shelley W. West v. Bruner Health Group, Inc.
Louisiana Court of Appeal, 2003
Integrity Flooring v. Mid South Contractors
857 So. 2d 582 (Louisiana Court of Appeal, 2003)
Pumpelly Oil, Inc. v. Ribbeck Const. Corp.
838 So. 2d 88 (Louisiana Court of Appeal, 2003)
Flatland Real Estate Co., LLC v. Dugas Const., Inc.
784 So. 2d 867 (Louisiana Court of Appeal, 2001)
Albert K. Newlin, Inc. v. Morris
782 So. 2d 1116 (Louisiana Court of Appeal, 2001)
HOSPITAL SERV. DIST. 3 v. Fidelity & Dep. Co.
809 So. 2d 145 (Louisiana Court of Appeal, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
758 So. 2d 222, 99 La.App. 3 Cir. 1093, 2000 La. App. LEXIS 6, 2000 WL 4396, Counsel Stack Legal Research, https://law.counselstack.com/opinion/albert-k-newlin-inc-v-morris-lactapp-2000.