STANDARD CO., ETC. v. Elliott Const. Co., Inc.

363 So. 2d 671
CourtSupreme Court of Louisiana
DecidedOctober 9, 1978
Docket61822
StatusPublished
Cited by21 cases

This text of 363 So. 2d 671 (STANDARD CO., ETC. v. Elliott Const. Co., Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
STANDARD CO., ETC. v. Elliott Const. Co., Inc., 363 So. 2d 671 (La. 1978).

Opinion

363 So.2d 671 (1978)

STANDARD COMPANY OF NEW ORLEANS, INC.
v.
ELLIOTT CONSTRUCTION COMPANY, INC., et al.
ELLIOTT CONSTRUCTION COMPANY, INC.
v.
DIVISION OF ADMINISTRATION, State of Louisiana, Legal Successor to the Capital Outlay Budget Board, Through the Department of Facility Planning and Control.

No. 61822.

Supreme Court of Louisiana.

October 9, 1978.
Rehearing Denied November 9, 1978.

*672 Thomas W. Prewitt, Butler, Snow, O'Mara, Stevens & Cannada, Jackson, Miss., Gordon A. Pugh and Charles W. Lamar, III, Breazeale, Sachse & Wilson, Baton Rouge, for Elliott Const. Co., Inc., applicant.

William J. Guste, Jr., Atty. Gen., Warren E. Mouledoux, First Asst. Atty. Gen., Robert E. Redmann, Asst. Atty. Gen., Jay H. Kern, Staff Atty., Dept. of Justice, State of La., New Orleans, for Div. of Administration, etc., et al., defendant-respondent.

DIXON, Justice.

Two cases have been consolidated and are before us.

A general contractor filed suit under R.S. 9:4201 et seq., asking the trial court to order the State of Louisiana to arbitrate a claim for equitable adjustment on a construction contract. The Nineteenth Judicial District Court for the Parish of East Baton Rouge granted an order requiring the State to arbitrate the claim brought by the general contractor in suit 205,827. The trial court also denied a motion to stay arbitration proceedings filed by the State in another suit (180,491) previously filed by a subcontractor in which the general contractor filed a third party demand against the State. The State appealed both decisions and the Court of Appeal stayed the proposed arbitration and reversed the trial court's two orders to arbitrate, holding that: (1) the court and not an arbitrator must decide whether the arbitration provision had been waived; (2) the obligation to arbitrate, once waived, could not be revived; and (3) the general contractor had waived the right to require the owner to arbitrate. We granted the general contractor's application for writ of certiorari to review the Court of Appeal decision.

These cases arise from the construction of the Southern University Minidome by Elliott Construction Company, Inc., the general contractor under a contract with the predecessor of the Division of Administration, State of Louisiana. During the course of construction, the State's architect, August Perez & Associates, Inc., rejected the work of the roofing subcontractor, Standard Company of New Orleans, Inc., on aesthetic grounds and because the roof leaked. The roofing subcontractor left the job and filed suit (180,491) against Elliott and the State to collect the unpaid balance on its subcontract. Elliott contracted with another roofer to replace the roof on the Minidome and reconvened against the original roofer for damages due to its breach of the roofing subcontract.

After the Minidome was completed and accepted by the State, Elliott filed with the architect a claim for equitable adjustment in contract time and money, asserting that the State was indebted to Elliott in excess of the contract sum for damages, because of *673 the State's interference with Elliott's planned sequence of construction activities and the State's withholding or misrepresenting information concerning sub-surface conditions at the worksite. The filing of these claims with the architect was in accordance with the procedures established by the contract. Two months after submitting the claim to the architect, Elliott filed its third party demand against the State in suit 180,491. In addition to Standard, Elliott and the State, the parties in suit 180,491 include the major suppliers of roofing components (The Celotex Corporation and National Gypsum Company), the architect and the sureties and insurers of several principal parties.

Perez issued its decision on the claim and Elliott invoked arbitration; the State then filed a motion in suit 180,491 in which it requested an order that Elliott show cause why it had not waived arbitration and should not proceed to litigate the claim. The trial court denied the State's motion, and Elliott then sought to compel the State to proceed with arbitration in suit 205,827. After a hearing in this latter suit, the trial court ordered the State to proceed with arbitration. The State appealed both decisions to the Court of Appeal, which reversed the trial court in both cases and entered judgment denying arbitration.

Applicant, Elliott, contends that the Court of Appeal erred in ruling Elliott waived its right to submit the claim to a panel of arbitrators and in not following Bartley, Inc. v. Jefferson Parish School Board, 302 So.2d 280 (La.1974), where this court held that a question of waiver of the right to claim arbitration should be decided by the arbitrator and not the court.

The trial court relied on the Bartley case and found that the issues before it were (1) whether an agreement to arbitrate had been made, and (2) whether the opponent had refused or failed to comply. R.S. 9:4203.[1] The trial court held that affirmative answers to both questions left it no authority than to order arbitration.

The Court of Appeal disagreed with the trial court's conclusion and quoted from R.S. 9:4201,[2] which provides in part that the provision to arbitrate "shall be valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract." The Court of Appeal interpreted that provision to mean that the court is not required to order arbitration under R.S. 9:4203 if there are grounds under R.S. 9:4201 for revocation, and reasoned: "It follows, necessarily, that the court must consider and rule upon any contention that such ground exists. Certainly, the State is contending that waiver is a ground for revocation." Standard Company of New Orleans, Inc. v. Elliott Construction Co., Inc., 359 So.2d 224, 226 (1st Cir. 1978).

Continuing, the Court of Appeal noted the recent decision of George Engine Co., Inc. v. Southern Shipbuilding Corp., 350 So.2d 881 (La.1977), where this court held that the court, not the arbitrator, had to decide the validity of the contract attacked for lack of consent and that it would be absurd to require arbitration under a contract *674 that did not legally exist. We find the Court of Appeal erred when it concluded, "we believe there should be a similar result if the arbitration provision has been waived."

In George Engine, supra, the issue was whether a party to a contract containing an arbitration clause may sue to rescind that contract in a court because the contract is, and was, void ab initio. George Engine involved the invalidity of the entire contract of which the arbitration clause was a part, and the court noted that by its very terms § 4201 presupposes the existence of a valid contract as a basis for invoking arbitration. In George Engine this court recognized that arbitration finds its principal support in the knowledge, experience and expertise of the arbitrator which qualify him to decide factual questions regarding performance of contractual obligations. Also, arbitration, as contrasted to litigation, can resolve quickly disputes over performance of contracts, and thus mitigate damages and allow parties to continue performance under the contracts. But the court found that arbitration serves neither of these functions where an entire contract is sought to be rescinded, because the courts can better resolve the legal issues which go to the validity of a contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wilson v. Allums
94 So. 3d 908 (Louisiana Court of Appeal, 2012)
Long v. Jeb Breithaupt Design Build Inc.
4 So. 3d 930 (Louisiana Court of Appeal, 2009)
Lincoln Builders, Inc. v. RAINTREE INVEST. CORP.
866 So. 2d 326 (Louisiana Court of Appeal, 2004)
Intern. River Ctr. v. Johns-Manville Sales
861 So. 2d 139 (Supreme Court of Louisiana, 2003)
HOSPITAL SERV. DIST. 3 v. Fidelity & Dep. Co.
809 So. 2d 145 (Louisiana Court of Appeal, 2001)
Albert K. Newlin, Inc. v. Morris
758 So. 2d 222 (Louisiana Court of Appeal, 2000)
ELECTRICAL & INSTRUMENTATION v. McDermott
627 So. 2d 702 (Louisiana Court of Appeal, 1993)
Big River Const. v. UNIVERSITY CLUB I ARTS.
598 So. 2d 542 (Louisiana Court of Appeal, 1992)
Nunnery v. Brantley Construction Co., Inc.
345 S.E.2d 740 (Court of Appeals of South Carolina, 1986)
Folkland v. Thomson McKinnon Sec., Inc.
484 So. 2d 310 (Louisiana Court of Appeal, 1986)
Charles J. Frank, Inc. v. Associated Jewish Charities of Baltimore, Inc.
450 A.2d 1304 (Court of Appeals of Maryland, 1982)
Burke County Public Schools Board of Education v. Shaver Partnership
279 S.E.2d 816 (Supreme Court of North Carolina, 1981)
IDC, Inc. v. McCain-Winkler Partnership
396 So. 2d 590 (Louisiana Court of Appeal, 1981)
Willis-Knighton Med. Ctr. v. So. Builders, Inc.
392 So. 2d 505 (Louisiana Court of Appeal, 1980)
West Baton Rouge Parish Sch. Bd. v. TR Ray, Inc.
367 So. 2d 332 (Supreme Court of Louisiana, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
363 So. 2d 671, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-co-etc-v-elliott-const-co-inc-la-1978.