Pumpelly Oil, Inc. v. Ribbeck Const. Corp.

838 So. 2d 88, 2002 La.App. 3 Cir. 868, 2003 La. App. LEXIS 188, 2003 WL 246041
Louisiana Court of Appeal·Decided February 5, 2003·No. 02-868·Published·Cited by 7 cases

Opinion

838 So.2d 88 (2003)

PUMPELLY OIL, INC.
v.
RIBBECK CONSTRUCTION CORPORATION.

No. 02-868.

Court of Appeal of Louisiana, Third Circuit.

February 5, 2003.

*89 Richard A. Chozen, Kevin J. Koenig, Raggio, Cappel, Chozen & Berniard, Lake Charles, LA, for Plaintiff/Appellee, Pumpelly Oil, Inc.

Frank C. Miller, III, Attorney at Law, Lake Charles, LA, for Defendant/Appellant, Ribbeck Construction Corporation.

Court composed of ULYSSES GENE THIBODEAUX, MICHAEL G. SULLIVAN, and BILLY H. EZELL, Judges.

*90 SULLIVAN, Judge.

Ribbeck Construction Corporation (Ribbeck) appeals the trial court's denial of its exception of lack of subject matter jurisdiction and the issuance of a preliminary injunction enjoining it from proceeding with arbitration. For the following reasons, we affirm.

Facts

On March 30, 1998, Ribbeck entered into a contract with Pumpelly Oil Company, Inc. (Pumpelly) for the construction of the Conoco Breakplace in Lake Charles. After being awarded the contract, Ribbeck subcontracted with Richard Barras d/b/a Barco Foundations to do the dirt work and foundation work required by the contract. Apparently, Mr. Barras could not accomplish the requirements of the subcontract on his own, and he contacted Mike Duhon d/b/a Mike Duhon Dirt Pit to provide certain services. The record indicates that Pumpelly and Ribbeck knew of Mr. Duhon's involvement in the project. The services rendered by Mr. Duhon exceeded the costs included in the contract for the dirt work and the foundation work at the construction site. On July 10, 1998, Ribbeck filed a petition against Richard "Ricky" Barras and Barco Foundations, seeking a money judgment against Mr. Barras and a writ of attachment. In its petition, Ribbeck alleged that Mr. Barras had not performed his work as contracted and that, due to representations by him, it incurred additional costs of $45,000.00 over the contract price. Then, on October 21, 1998, Mike Duhon d/b/a Mike Duhon Dirt Pit filed suit against Mr. Barras, Ribbeck, and Pumpelly, seeking a money judgment in the amount of $48,576.25 and enforcement of a materialman's lien and privilege in conjunction with the work he performed at the construction site. In November 1998, Ribbeck filed a bond to release the lien filed against the Conoco Breakplace.

On January 20, 1999, Ribbeck sought and received final payment from Pumpelly under the contract. In connection with the final payment, it executed a document entitled "Unconditional Waiver and Release upon Final Payment."

Thereafter, on March 24, 1999, counsel for Ribbeck filed a motion for summary judgment on behalf of Pumpelly in the Duhon suit, which was granted, and Pumpelly was dismissed from the litigation. The Barras suit and the Duhon suit were then consolidated. During trial of the consolidated matters in December 2001, Ribbeck settled with Mr. Duhon for $46,500.00. The settlement documents included an assignment of Mr. Duhon's claim to Ribbeck.

In February 2002, Ribbeck filed a demand for arbitration with the American Arbitration Association regarding the additional funds it sought to recover from Pumpelly. On March 1, 2002, Pumpelly filed a petition for declaratory judgment, seeking a judgment declaring that Ribbeck had waived its right to collect additional payments and/or that its obligations to Ribbeck were extinguished under the terms of the contract. In response, Ribbeck filed an exception of lack of subject matter jurisdiction, alleging that the contract contained a provision for arbitration and that determination of whether it was entitled to proceed in arbitration was not subject to a judicial determination. Following a hearing held May 8, 2002, the trial court denied the exception. On May 9, 2002, Pumpelly filed a motion for temporary restraining order (TRO) and rule for preliminary injunction to enjoin the arbitration instituted by Ribbeck. The trial court granted the TRO and, after a hearing, granted a preliminary injunction.

Ribbeck filed an application for writs regarding the issuance of the TRO and the preliminary injunction; it filed an appeal *91 regarding the denial of its exception of subject matter jurisdiction. The two matters were consolidated by this court.

Arbitration

Ribbeck contends that it was error for the trial court to determine whether Pumpelly had to submit to arbitration, arguing that an arbitrator, not the trial court, should make that determination. The contract's arbitration provision provides:

4.6.1 Any Claim arising out of or related to the Contract, except Claims relating to aesthetic effect and except those waived as provided for in Subparagraphs 4.3.10, 9.10.4 and 9.10.5., shall,... be subject to arbitration.

Pumpelly's claim that Ribbeck waived additional payment is based on Subparagraph 9.10.5 of the contract which provides:

Acceptance of final payment by the Contract, a Subcontractor or material supplier... shall constitute a waiver of claims by that payee except those previously made in writing and identified as unsettled as of the time of final Application for Payment.

The right to demand arbitration is strong under federal and state law. Collins v. Prudential Ins. Co. of America, 99-1423 (La.1/19/00); 752 So.2d 825; Matthews-McCracken Rutland Corp. v. City of Plaquemine, 414 So.2d 756 (La.1982). La. R.S. 9:4201 provides that when a contract contains an arbitration provision it "shall be valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract."

Ribbeck argues that the trial court determined issues of "procedural arbitrability" that should have been presented to an arbitrator, citing Bartley, Inc. v. Jefferson Parish School Board, 302 So.2d 280 (La. 1974), Willis-Knighton Medical Center v. Southern Builders, Inc., 392 So.2d 505 (La.App. 2 Cir.1980), and Charles Ragusa & Son, Inc. v. St. John the Baptist Parish School Board, 629 So.2d 1302 (La.App. 4 Cir.1993), writ denied, 94-100 (La.3/11/94); 634 So.2d 395. In Bartley, the contractor filed suit against the owner of a project to compel arbitration regarding its claim for payment for work that it performed after accepting final payment from the owner. The owner attempted to enjoin the arbitration. The supreme court refused to consider the owner's claims of prematurity and waiver because they are "questions of procedural arbitrability [which] should not be decided by the courts, without having been submitted to the arbitrator...." Bartley, 302 So.2d at 283.

The courts in Willis-Knighton, 392 So.2d 505, and Ragusa, 629 So.2d 1302, followed Bartley, 302 So.2d 280. In these cases, as in Bartley, the work for which payment was sought was performed after final payment. In Ragusa, the school board participated in arbitration of the contractor's claim, but sought to have the arbitrator's award vacated. The court refused to vacate the award, noting that the school board failed to object to the arbitration proceedings or to file an injunction to prevent Ragusa from proceeding with the arbitration.

In spite of La.R.S. 9:4201's provision that an arbitration clause is irrevocable and cases like Bartley, Willis-Knighton, and Ragusa, courts have held that a party's conduct can effect a waiver of its right to demand arbitration. See Thomas v. Desire Community Hous. Corp., 98-2097 (La.App. 4 Cir. 7/19/00); 773 So.2d 755; Albert K. Newlin, Inc. v. Morris, 99-1093 (La.App. 3 Cir. 1/5/00); 758 So.2d 222;

Free access — add to your briefcase to read the full text and ask questions with AI

Pumpelly Oil, Inc. v. Ribbeck Const. Corp., 838 So. 2d 88, 2002 La.App. 3 Cir. 868, 2003 La. App. LEXIS 188, 2003 WL 246041 (La. Ct. App. 2003).

838 So. 2d 88 (Pumpelly Oil, Inc. v. Ribbeck Const. Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Advanced Logistics, LLC v. Comeaux
86 So. 3d 105 (Louisiana Court of Appeal, 2012)
Advanced Logistics, LLC v. Jennifer Comeaux
Louisiana Court of Appeal, 2012
Norris v. KILCHRIST
996 So. 2d 74 (Louisiana Court of Appeal, 2008)
Misty Marie Norris v. Leroy J. Kilchrist
Louisiana Court of Appeal, 2008
Guilbeaux v. Guilbeaux
981 So. 2d 913 (Louisiana Court of Appeal, 2008)
Francis v. Francis
981 So. 2d 920 (Louisiana Court of Appeal, 2008)
Diana Istre Francis v. Michael G. Francis
Louisiana Court of Appeal, 2008
Pumpelly Oil, Inc. v. Ribbeck Const. Corp.
839 So. 2d 447 (Louisiana Court of Appeal, 2003)