Quinn Construction Co. v. Savoie

207 So. 2d 229
CourtLouisiana Court of Appeal
DecidedApril 19, 1968
Docket2886
StatusPublished
Cited by13 cases

This text of 207 So. 2d 229 (Quinn Construction Co. v. Savoie) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quinn Construction Co. v. Savoie, 207 So. 2d 229 (La. Ct. App. 1968).

Opinion

207 So.2d 229 (1968)

QUINN CONSTRUCTION CO., Inc.
v.
Maurice J. SAVOIE, Anthony G. Orgeron and William M. Justice, Jr., Clerk of Court for the Parish of Jefferson.

No. 2886.

Court of Appeal of Louisiana, Fourth Circuit.

February 5, 1968.
Rehearings Denied March 4, 1968.
Writ Refused April 19, 1968.

*230 David H. Seelig, New Orleans, for plaintiff-appellee.

Jackson & Hess, Ralph N. Jackson, New Orleans, for defendants-appellants.

A. W. Wambsgans, Metairie, for William M. Justice, Jr., Clerk of Court, Parish of Jefferson.

Before REGAN, SAMUEL, and JOHNSON, JJ.

REGAN, Judge.

The plaintiff, Quinn Construction Co., Inc., filed this suit against the defendants, Maurice J. Savoie and Anthony G. Orgeron, Savoie's surety, endeavoring to recover the sum of $61,924.27, representing damages for breach of contract and the improper recordation of a laborer's lien. The plaintiff seeks the amount of $49,924.27 as the alleged difference between the cost of completion of the work contracted for by Savoie and his original contract price, and $12,000.00 as damages together with attorney's fees for the improper recordation of the lien.

The defendants answered and denied the foregoing accusations relative to the breach of their contract and reconvened endeavoring to recover the sum of $2,717.50, representing the value of labor employed and materials used in the performance of the contract by Savoie.[1]

From a judgment in favor of the plaintiff in the amount of $23,969.71, the defendants have prosecuted this appeal.

The record discloses that on December 16, 1959, the plaintiff, Quinn Construction Co., Inc., entered into a contract with the Convent of the Good Shepherd, in Bridge City, Louisiana, for the construction of several buildings in conformity with the plans and specifications prepared by Freret & Wolf, architects for the convent. The total contract price was $1,460,894.00.

On March 29, 1960, Quinn Construction Co. contracted with the defendant, Maurice J. Savoie, for the installation of all masonry work in the proposed buildings, for the price of $113,000.00. The other defendant, Anthony Orgeron, was designated in the contract as a principal, but it is conceded that he entered into the agreement as a surety and guarantor of Savoie, apparently because *231 the latter could not obtain bonding from an insurance company.

The subcontract from Quinn to Savoie provided that Savoie was to furnish all labor, insurance, scaffolding, masonry saw blades, mortar, and other equipment to install all of the masonry work in accordance with the plans and specifications executed by the owner's architect. The agreement further stipulated that all masonry units, stone, wall ties, and wall reinforcement material was to be furnished by Quinn and installed by the defendant as masonry subcontractor.

The subcontract binds both parties to the terms and conditions of the general contract. Article VII of the subcontract provides that:

"Should the Subcontractor at any time refuse or neglect to supply a sufficient number of properly skilled workmen, or a sufficient quantity of materials of proper quality, or fail, in any respect, to prosecute the work covered by this contract, with promptness and diligence, or fail in the performance of any of the agreements herein contained, the Contractor may, at his option, after forty-eight (48) hours written notice to the Subcontractor provide any such labor and materials and deduct the costs thereof, from any money then due or thereafter to become due, to the Subcontractor under this contract; or the Contractor may, at his option, terminate the employment of the Subcontractor for the said work, and shall have the right to enter upon the premises and take possession, for the purpose of completing the work included under this contract, of all materials, tools, and appliances thereon, and may employ any other person or persons to finish the work and provide the materials therefor; and in case of such discontinuance of the employment of said Subcontractor, said Subcontractor shall not be entitled to receive any further payment under this contract until the said work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid under this contract exceeds the expenses incurred by the Contractor in finishing the work, such excess shall be paid by the Contractor to the Subcontractor; if such expense shall exceed such unpaid balance, then the Subcontractor shall pay the difference to the Contractor. The expense incurred by the Contractor as herein provided, either for furnishing materials or for finishing the work, and any damages incurred by such default, shall be chargeable to, and paid by, said Subcontractor and the Contractor shall have a lien upon all materials, tools and appliances, taken possession of, as aforesaid, to secure the payment thereof."

Prior to Savoie's substantial assumption of the work, he erected various sample panels of brick in order to permit the architect to decide which type of work satisfied him. The architect then selected a sample and requested Savoie to proceed in conformity therewith.

The specifications in the contract called for a 3/8 inch "flush cut" joint between the bricks and blocks in the masonry walls and facings of the buildings. The one exception to this requirement involved the masonry work around the window casings, in which location the specifications call for a "tooled" joint. In masonry terminology, a "joint" is the space filled with mortar between bricks or blocks in a masonry wall or facing. The flush cut joint is achieved when the brick mason, after laying the brick, scrapes a trowel along the face of the brick in order to eliminate excess cement from the surface thereof. This process ideally results in the surface of the mortar being approximately even with the surface of the brick. Sometimes this process leaves small holes in the mortar, commonly referred to as "bee holes", which are caused by pieces of gravel or pebble in the mortar sticking to the face of the trowel as it is passed along the base of the fresh mortar. These holes must be filled while the work is in progress or after it has been completed, in order to avoid water seepage and other complications.

A tooled joint is one in which a rounded bar or tool is passed over the fresh mortar *232 between the bricks so as to create a concave indentation in the mortar. This method involves more work for the brick mason and more time on the job, but results in a smoother finish.

To reiterate the plans and specifications called for a flush cut joint; however, the architect was dissatisfied with the appearance of this type of joint after the work commenced. He requested that the defendant substitute a tooled joint instead, and the defendant complied with this request voluntarily, irrespective of the fact that it would probably involve more cost to him. The architect was still not satisfied with the appearance of the bricks or blocks with this type of joint, and requested that the joints be rubbed with a burlap bag after partially drying in addition to the tooling. The defendant complied with this request until he was asked to discontinue it later during the course of his work.

The architect still continued to manifest disapproval of the brick work; he then requested the defendant to substitute a "rubber heel" joint in the performance thereof. This type of joint is one which is literally rubbed with a rubber shoe heel after the fresh mortar is laid in order to smooth it and give it a more uniform appearance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Albert K. Newlin, Inc. v. Morris
758 So. 2d 222 (Louisiana Court of Appeal, 2000)
Moore v. Automotive Protection Corp.
695 So. 2d 550 (Louisiana Court of Appeal, 1997)
B & S EQUIPMENT CO., INC. v. Carl E. Woodward, Inc.
620 So. 2d 347 (Louisiana Court of Appeal, 1993)
Mini Togs Products, Inc. v. Wallace
513 So. 2d 867 (Louisiana Court of Appeal, 1987)
New Orleans v. United Gas Pipe Line Co.
517 So. 2d 145 (Louisiana Court of Appeal, 1987)
IDC, Inc. v. McCain-Winkler Partnership
396 So. 2d 590 (Louisiana Court of Appeal, 1981)
May v. Southland Corp.
341 So. 2d 421 (Louisiana Court of Appeal, 1977)
Colbert v. Mike-Baker Brick Co. of New Iberia, Inc.
326 So. 2d 900 (Louisiana Court of Appeal, 1976)
Sim v. Beauregard Electric Cooperative, Inc.
322 So. 2d 410 (Louisiana Court of Appeal, 1975)
Noel v. State
311 So. 2d 182 (District Court of Appeal of Florida, 1975)
Lee v. Blackwell
286 So. 2d 185 (Louisiana Court of Appeal, 1973)
Irby Steel v. W. R. Fairchild Construction Co.
270 So. 2d 233 (Louisiana Court of Appeal, 1972)
Quinn Construction Co. v. Savoie
209 So. 2d 42 (Supreme Court of Louisiana, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
207 So. 2d 229, Counsel Stack Legal Research, https://law.counselstack.com/opinion/quinn-construction-co-v-savoie-lactapp-1968.