Alabama Aircraft Industries, Inc.—Birmingham v. United States

586 F.3d 1372, 2009 U.S. App. LEXIS 25115, 2009 WL 3818528
CourtCourt of Appeals for the Federal Circuit
DecidedNovember 17, 2009
Docket2009-5021, 2009-5022, 2009-5023
StatusPublished
Cited by356 cases

This text of 586 F.3d 1372 (Alabama Aircraft Industries, Inc.—Birmingham v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alabama Aircraft Industries, Inc.—Birmingham v. United States, 586 F.3d 1372, 2009 U.S. App. LEXIS 25115, 2009 WL 3818528 (Fed. Cir. 2009).

Opinion

PLAGER, Circuit Judge.

This is a post-award bid protest case. The Department of the Air Force (agency) awarded a billion-dollar-plus contract to the Boeing Company (Boeing) for long-term maintenance on the Air Force’s fleet of KC-135 Stratotanker aircraft. Alabama Aircraft Industries, Inc. — Birmingham (AAII), 1 an unsuccessful bidder on the contract, protested the award through the established administrative channels and eventually, pursuant to 28 U.S.C. § 1491(b)(1), filed a bid protest complaint in the United States Court of Federal Claims.

Under the statute, the Court of Federal Claims reviews the agency’s decision according to the standards contained in the Administrative Procedure Act. 28 U.S.C. § 1491(b)(4). Thus, the court can set aside the agency’s decision only if it is “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A). Following cross-motions for judgment on the administrative record, the trial court adjudged that the agency’s contract award was arbitrary and capricious, set aside the award, enjoined the Air Force from proceeding with the award to Boeing, and ordered the agency to resolicit the procurement. Ala. Aircraft Indus., Inc. — Birmingham v. United States, 83 Fed.Cl. 666, 700, 703 (2008).

BACKGROUND

The Air Force issued its Request for Proposals No. FA8105-05-R-0014 (RFP) in August 2005 for a contract to perform maintenance on KC-135 Stratotanker aircraft. The RFP contemplated the award of a commercial item contract with a five-year base period 2 and five one-year options. The award was to be made to the offeror whose proposal represented the best value to the Air Force based on four evaluation factors. As part of the agency’s evaluation of the cost/price factor, the RFP required a “price-realism” analysis *1374 based on certain rate information submitted by the offerors.

In September 2007, after extensive discussions and subsequent evaluations by the Air Force Source Selection Evaluation Team and Source Selection Advisory Council, the Air Force Source Selection Authority awarded the contract to Boeing. AAII filed a protest of the award with the Government Accountability Office (GAO), as the law provides. See Competition in Contracting Act, 31 U.S.C. §§ 3551-56. The GAO denied the protest on all grounds raised by AAII, with the exception of the agency’s cost/price evaluation. The GAO concluded that the record was insufficient for the GAO to determine the reasonableness of the agency’s price-realism analysis. In particular, the GAO was concerned about a significant labor hour reduction in Boeing’s final proposal revisions, especially in the context of an aging aircraft fleet, an issue discussed in an Air Force “Talking Paper” submitted to the GAO but not part of the original RFP.

In response to the GAO’s decision and consistent with its recommendations, the Air Force undertook another detailed analysis of the offerors’ proposals and documented the various factors supporting its conclusion that the prices proposed by all offerors were realistic and reasonable. The agency noted that because aging aircraft issues were not predictable with any certainty, the RFP instructed offerors to base their proposals on a three-tier work package as explained in Addendum 1 to the RFP. The three-tier work package contemplated a basic “programmed depot maintenance” (PDM) element, an “intermittent task” (IT) element, and an “over and above” (0 & A) work element. The agency further explained that the RFP provided for the agency to negotiate new work packages as might be needed in future years, as set forth in the Addendum. Based on this review, the Air Force in March 2008 affirmed the contract award to Boeing. AAII subsequently filed a second protest with the GAO. The GAO, in view of the Air Force’s explanation, denied the second protest in June 2008.

AAII then filed its complaint in the Court of Federal Claims. Boeing was granted leave to participate in the case as an intervening defendant. On cross-motions for judgment on the administrative record, with one exception the trial court rejected AAII’s claims, including alleged organizational conflicts of interest on the part of Boeing and the agency’s evaluation of Boeing’s past performance. The trial court, however, held that the Air Force’s price-realism analysis was “arbitrary and capricious” because the agency failed “to deal explicitly with the aging-fleet issue in the RFP” and then sought “to sidestep the aging-fleet issue in the price-realism analysis of Boeing’s prevailing offer.” Ala. Aircraft, 83 Fed.Cl. at 700. The court ordered the Air Force to “resolicit the procurement and take the necessary steps in a new solicitation to address explicitly the role of an ever-aging KC-135 fleet on the PDM to be performed.” Id. at 703.

The Government and Boeing appealed the decision of the Court of Federal Claims to this court. AAII then filed a cross-appeal challenging the trial court’s rejection of its conflicts of interest and past performance claims. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(3).

DISCUSSION

We review the trial court’s judgment on the administrative record without deference. Bannum, Inc. v. United *1375 States, 404 F.3d 1346, 1351 (Fed.Cir.2005). This means that we apply the APA “arbitrary and capricious” standard anew to the agency’s procurement decision. Id. Courts have found an agency’s decision to be arbitrary and capricious when the agency “entirely failed to consider an important aspect of the problem, offered an explanation for its decision that runs counter to the evidence before the agency, or [the decision] is so implausible that it could not be ascribed to a difference in view or the product of agency expertise.” Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43, 103 S.Ct. 2856, 77 L.Ed.2d 443 (1983).

The trial court dealt thoughtfully and comprehensively with the various issues raised by AAII. With one exception, the price-realism analysis, we find nothing on which to fault the trial court. With regard to the price-realism analysis conducted by the Air Force, the trial court disagreed with the Air Force’s decision to reaffirm its conclusions following the review requested by the GAO, and disagreed with the GAO when the GAO concluded, based on this review, that the bids were properly evaluated.

The trial court’s concern was with the issue of aging aircraft.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
586 F.3d 1372, 2009 U.S. App. LEXIS 25115, 2009 WL 3818528, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alabama-aircraft-industries-incbirmingham-v-united-states-cafc-2009.