ADC Construction Co. v. McDaniel Grading, Inc.

338 S.E.2d 733, 177 Ga. App. 223, 1985 Ga. App. LEXIS 2947
CourtCourt of Appeals of Georgia
DecidedNovember 27, 1985
Docket71310
StatusPublished
Cited by24 cases

This text of 338 S.E.2d 733 (ADC Construction Co. v. McDaniel Grading, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ADC Construction Co. v. McDaniel Grading, Inc., 338 S.E.2d 733, 177 Ga. App. 223, 1985 Ga. App. LEXIS 2947 (Ga. Ct. App. 1985).

Opinion

Birdsong, Presiding Judge.

Stay of Arbitration. Plaintiff, ADC Construction Company, was the general contractor for the developer of the River Pointe Apartments being constructed in Dunwoody, Georgia. On April 18, 1984, plaintiff entered into a subcontract with McDaniel Grading, Inc., wherein McDaniel agreed to perform certain grading and related work in accordance with the project plan and specifications prepared by B. G. Sanders & Associates, the River Pointe project architect.

Article I of the subcontract provided that McDaniel was to perform his work in accordance with the terms of the “Contract Documents.” The “Contract Documents” were identified as the subcontract, the “General Conditions of the Contract for the Construction of Buildings,” of the current edition of the American Institute of Architects (AIA), and designated documents prepared by the architect for the River Pointe project. It further provided: “The Contract Documents are hereby made part of this Agreement.” The “General Conditions” contract of the AIA was identified as AIA Document A201. Paragraph 5.3.1 of Article 5 of the A201 document covered relations between the general contractor and the subcontractors. It required the general contractor to bind the subcontractors to the terms of the “Contract Documents” and for the subcontractors to assume toward the owner the obligations and responsibilities of the general contractor. It also granted to “the Subcontractor . . . the benefit of all rights, remedies and redress against the Contractor that the Contractor, by these Documents, has against the Owner.” Paragraph 7.9.1 of Article 7 of A201 required “[a]ll claims, disputes and other matters in question between the Contractor and the Owner arising out of, or relating to, the Contract Documents or the breach thereof except [the Architect’s decisions in matters relating to artistic effect], and except for claims which have been waived by the making or acceptance of final payment . . . shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association. ...”

*224 McDaniel commenced work and performed designated grading and other associated work assigned by the contractor, ADC. McDaniel contends that his grading work was based upon a mutual understanding that there was enough usable soil on the site to make the grades called for in the plans and specifications. He says the site was not balanced and there was insufficient usable soil to complete the designated work without a substantial amount of additional soil, which he was not obligated to provide under the subcontract. McDaniel ceased work on the project and ADC demanded that McDaniel return to work and gave notice of an alleged breach on August 28, 1984. ADC alleges McDaniel refused to return to work and the contract was terminated on September 4, 1984.

McDaniel presented a claim to ADC on August 20, 1984 for final payment. On August 28, he met with two ADC representatives and he said they agreed to a compromise settlement of his final invoice and the additional work for which he made claim. McDaniel stated they reached agreement on a figure of $145,000 plus other charges, provided he completed certain reshaping work. He alleges that when he attempted to finish the work, he was stopped by ADC’s employees. On November 6, 1984, McDaniel filed a Demand for Arbitration with the American Arbitration Association and served the architect and ADC. On November 26, 1984, ADC filed this action for a Stay of Arbitration, alleging that McDaniel breached his contract, refused to return to the job site within the time permitted, that there was no valid agreement to submit the claims of either party to arbitration, and if such agreement did exist, it has not been complied with and has been waived, and/or that arbitration is barred by limitation of time. The trial court found that the contract involved interstate commerce, that the Federal Arbitration Act was applicable, and denied the stay. ADC brings this appeal. Held:

1. Appellant contends that the trial court erred in finding that the contract between the parties involved transactions in interstate commerce. We do not agree. Where the transactions out of which the claim for arbitration arose involve “commerce” within the meaning of 9 USC § 1 of the Federal Arbitration Act, state law and policy must yield to federal law. Hilton Constr. Co. v. Martin Mechanical Contractors, 251 Ga. 701, 702 (308 SE2d 830). “Commerce,” within the meaning of the Arbitration Act, means interstate commerce, and the determination of whether a contract evidences transactions in interstate commerce is a question on which federal rules of contract construction and interpretation govern. In re Mercury Constr. Corp. v. Moses H. Cone Memorial Hosp., 656 F2d 933, 938 (4th Cir. 1981), aff’d 460 U. S. 1.

ADC and McDaniel are both Georgia companies and this contract was to be fully performed in Georgia. However, the affidavit of *225 the president of McDaniel revealed that he used equipment in the performance of this contract that was manufactured in Japan and purchased in Canada. He also used equipment purchased in Louisiana and North Carolina. One electrical subcontractor on this project was from Kingsport, Tennessee. A mechanical subcontractor was from Arkansas. An affidavit of an employee of ADC showed he was an Alabama resident. An electrical subcontractor used material incorporated into the project which was purchased in New Jersey. Another subcontractor used trusses and floor systems bought in Alabama.

Although this contract was to be performed in Georgia and the general and subcontractor were both from Georgia, where the contractor uses employees from another state, and material incorporated into the construction is purchased in another state, and some of the subcontractors are from another state, these facts are sufficient to support a finding of the trial court that this contract involved “commerce” as that term is used in the Federal Arbitration Act. Metro. Industrial Painting Corp. v. Terminal Constr. Co., 287 F2d 382, 384 (2d Cir. 1961), cert. den. 368 U. S. 817; accord Warren Bros. Co. v. Community Bldg. Corp., 386 FSupp. 656, 664 (MD NC 1974). Other federal courts have found that where a subcontractor purchased products from another state which were incorporated into the construction, and used equipment shipped to the construction site from another state, this is sufficient to support the finding of the trial court that the contract is one involving interstate commerce as contemplated by the Federal Arbitration Act. American Home Assur. Co. v. VECCO Concrete Constr. Co., 629 F2d 961, 963 (4th Cir. 1980). Accordingly, we find sufficient indicia of interstate commerce in the record to support the finding of the trial court.

2. It is argued, by appellant, that the trial court erred in holding that a valid agreement to arbitrate existed between the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Web IV, LLC v. Samples Construction, LLC
824 S.E.2d 107 (Court of Appeals of Georgia, 2019)
Municipio de Mayagüez v. Lebrón
167 P.R. Dec. 713 (Supreme Court of Puerto Rico, 2006)
Municipio De Mayagüez v. Lebrón H/N/C Lebrón & Associates
2006 TSPR 70 (Supreme Court of Puerto Rico, 2006)
Krut v. Whitecap Housing Group, LLC
602 S.E.2d 201 (Court of Appeals of Georgia, 2004)
Yates Paving & Grading Co. v. Bryan County
594 S.E.2d 756 (Court of Appeals of Georgia, 2004)
Phillips v. TermNet of New Mexico, Inc.
580 S.E.2d 544 (Court of Appeals of Georgia, 2003)
Wise v. Tidal Const. Co., Inc.
583 S.E.2d 466 (Court of Appeals of Georgia, 2003)
Eure v. Cantrell Properties, Inc.
512 S.E.2d 323 (Court of Appeals of Georgia, 1999)
L & B Construction Co. v. Ragan Enterprises, Inc.
482 S.E.2d 279 (Supreme Court of Georgia, 1997)
North Augusta Associates Ltd. Partnership v. 1815 Exchange, Inc.
469 S.E.2d 759 (Court of Appeals of Georgia, 1996)
Columbus Anesthesia Group, P. C. v. Kutzner
459 S.E.2d 422 (Court of Appeals of Georgia, 1995)
Primerica Financial Services, Inc. v. Wise
456 S.E.2d 631 (Court of Appeals of Georgia, 1995)
Race, Inc. v. Shell
442 S.E.2d 767 (Court of Appeals of Georgia, 1994)
Williams Tile & Marble Co. v. Ra-Lin & Associates, Inc.
426 S.E.2d 598 (Court of Appeals of Georgia, 1992)
Tigner v. Shearson-Lehman Hutton, Inc.
411 S.E.2d 800 (Court of Appeals of Georgia, 1991)
United Parcel Service, Inc. v. Universal Diamond Corp.
409 S.E.2d 558 (Court of Appeals of Georgia, 1991)
City of College Park v. BATSON-COOK COMPANY
395 S.E.2d 385 (Court of Appeals of Georgia, 1990)
Brockett Pointe Shopping Center, Ltd. v. Development Contractors, Inc.
389 S.E.2d 374 (Court of Appeals of Georgia, 1989)
Godwin v. Stanley Smith & Sons
386 S.E.2d 464 (Court of Appeals of South Carolina, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
338 S.E.2d 733, 177 Ga. App. 223, 1985 Ga. App. LEXIS 2947, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adc-construction-co-v-mcdaniel-grading-inc-gactapp-1985.