L & B Construction Co. v. Ragan Enterprises, Inc.

482 S.E.2d 279, 267 Ga. 809, 97 Fulton County D. Rep. 683, 1997 Ga. LEXIS 81
CourtSupreme Court of Georgia
DecidedMarch 3, 1997
DocketS96G1535
StatusPublished
Cited by12 cases

This text of 482 S.E.2d 279 (L & B Construction Co. v. Ragan Enterprises, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L & B Construction Co. v. Ragan Enterprises, Inc., 482 S.E.2d 279, 267 Ga. 809, 97 Fulton County D. Rep. 683, 1997 Ga. LEXIS 81 (Ga. 1997).

Opinion

Sears, Justice.

We granted certiorari in this case in order (1) to review the judicial construction of a “flow down” clause purported to incorporate a “no-damages-for-delay” provision from a general contract into a subcontract, and (2) to determine whether that “flow down clause” barred a subcontractor’s action for delay damages when the subcontract also provided that “only an extension of time” would be accorded the subcontractor in the event of contractor-caused delay. We determine that, under the unambiguous terms of the general and *810 subcontracts at issue here, the “flow down clause” incorporated the “no-damages-for-delay” provision into the subcontract, barring the subcontractor’s action against the contractor for delay damages. Therefore, we reverse the contrary ruling by the Court of Appeals.

Appellant L & B Construction, Inc. (“L & B”) was the general contractor on a construction project owned by the State of Georgia. Appellee Ragan Enterprises, Inc. (“REI”) was the electrical subcontractor on the construction project. The general contract between L & B and the State contained the following relevant clauses:

The contractor [L & B] expressly agrees that the contractor’s sole remedy for . . . delay shall be an extension of contract time and that the contractor shall make no demand for damages or extended overhead.
The Contractor shall not be entitled to payment or compensation of any kind from the Owner for direct, indirect, or impact damages . . . arising because of any hindrance or delay from any cause whatsoever [except those involving fraud and bad faith],

(Emphasis supplied.)

The subcontract entered between L & B and REI contained these relevant clauses:

Should subcontractor be delayed in his work by contractor then contractor shall owe subcontractor therefor only an extension of time for completion equal to the delay caused and then only if a written claim for delay is made to the contractor within forty-eight hours from the time of the beginning of the delay.
The contractor [L & B] has heretofore entered into a General Contract with [the Owner] . . . and which is now made a part of this Sub-contract insofar as \it\ appl[ies\.
Contractor shall have the same rights and privileges as against the Sub-contractor herein as the Owner in the General Contract has against the Contractor. Sub-contractor acknowledges that he has read the General Contract and all plans and specifications and is familiar therewith and agrees to comply with and perform all provisions thereof applicable to Sub-contractor. (Emphasis supplied.)
The Sub-contractor agrees to be bound to the contractor by *811 the terms of the contract documents and assume toward the contractor all of the obligations and responsibilities that the contractor by aforesaid document assumes toward the Owner.

REI filed suit against L & B and its surety for breach of contract and resulting damages due to a two-year delay in the project caused by L & B. L & B defended on grounds that REI’s suit was barred by the “no-damages-for-delay” provision in the subcontract. The superior court agreed, and on cross-motions for summary judgment, denied REI’s motion and granted L & B’s motion. The Court of Appeals reversed, and instructed the superior court to enter summary judgment in favor of REI. 1

In its opinion, the Court of Appeals concluded that the clause in the subcontract that L & B had argued addressed damages for delay merely provided for a time extension in the event of delay, did not address delay damages, and therefore did not bar REI’s recovery. Specifically, the Court of Appeals held that the clause in the subcontract stating that, in the event of delay caused by L & B, L & B would owe REI “only an extension of time for completion equal to the delay causéd” was ambiguous as to whether the term “only” modified (1) the length of the extension of time given in the event of delay, or (2) the scope of permitted remedies in the event of delay. 2 Because exculpatory clauses must be unambiguous, and because any ambiguities in a contract must be construed against the drafter (in this case L & B), the Court of Appeals concluded that this clause did not bar REI’s action for delay damages against L & B. 3 In a later division, the Court of Appeals appears to have resolved this ambiguity for itself by stating that within this clause, the term “only” simply modifies the length of any extension of time that would be permitted in the event of delay, and therefore does not limit the scope of remedies available to the subcontractor for delays caused by the general contractor. 4

As for the general contract, the Court of Appeals found that by its clear terms, it did affirmatively bar an action for delay damages brought by the general contractor against the project’s owner, and therefore conflicted with the subcontract. For that reason, the Court of Appeals refused to construe the “flow down” clause as incorporating the “no-damages-for-delay” provision from the general contract in to the subcontract. 5

*812 This Court granted certiorari in order to review the propriety of this ruling. For the reasons explained below, we reverse.

The law in Georgia has long recognized the legitimacy of contractual provisions that impose on a subcontractor some or all of the contractor’s obligations to the owner, commonly referred to as “flow down clauses.” 6 “Flow down clauses” in construction contracts are effective to impose on a subcontractor the incorporated duties as set forth in the general contract. 7 When a “flow down” clause is used in a subcontract, the subcontract need not contain additional language of incorporation in order to impose on a subcontractor duties owed by the general contractor to the project owner. 8

In this matter, the “flow down clause” in the subcontract states that the “contractor shall have the same rights and privileges as against the Sub-contractor ... as the Owner in the General Contract has against the Contractor.” The only legitimate meaning of this clause is to allow the general contractor to invoke against the subcontractor all of the rights and defenses that the project owner would be able to invoke against the general contractor under the general contract. As recognized by the Court of Appeals, the rights and defenses available to the project owner against the general contractor under the general contract clearly and unambiguously bar the recovery of delay damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bennon L. Prine, Jr. v. Chailland Inc.
402 F. App'x 469 (Eleventh Circuit, 2010)
Executive Fitness, LLC v. Healey Building Ltd. Partnership
660 S.E.2d 26 (Court of Appeals of Georgia, 2008)
Walker v. 90 FAIRLIE CONDOMINIUM ASS'N
659 S.E.2d 412 (Court of Appeals of Georgia, 2008)
Bernotas v. Super Fresh Food Markets, Inc.
816 A.2d 225 (Superior Court of Pennsylvania, 2002)
Yargus v. Smith
562 S.E.2d 371 (Court of Appeals of Georgia, 2002)
Time Warner Entertainment Co. v. Six Flags Over Georgia, LLC
537 S.E.2d 397 (Court of Appeals of Georgia, 2000)
Ragan Enterprises, Inc. v. L & B Construction Co.
492 S.E.2d 671 (Court of Appeals of Georgia, 1997)