CAJUN CONTRACTORS, INC. v. PEACHTREE PROPERTY SUB, LLC D/B/A CROWNE PLAZA HOTEL ATLANTA-MIDTOWN

CourtCourt of Appeals of Georgia
DecidedJune 30, 2021
DocketA21A0311
StatusPublished

This text of CAJUN CONTRACTORS, INC. v. PEACHTREE PROPERTY SUB, LLC D/B/A CROWNE PLAZA HOTEL ATLANTA-MIDTOWN (CAJUN CONTRACTORS, INC. v. PEACHTREE PROPERTY SUB, LLC D/B/A CROWNE PLAZA HOTEL ATLANTA-MIDTOWN) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CAJUN CONTRACTORS, INC. v. PEACHTREE PROPERTY SUB, LLC D/B/A CROWNE PLAZA HOTEL ATLANTA-MIDTOWN, (Ga. Ct. App. 2021).

Opinion

FIRST DIVISION BARNES, P. J., GOBEIL and MARKLE, JJ.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. https://www.gaappeals.us/rules

DEADLINES ARE NO LONGER TOLLED IN THIS COURT. ALL FILINGS MUST BE SUBMITTED WITHIN THE TIMES SET BY OUR COURT RULES.

June 30, 2021

In the Court of Appeals of Georgia A21A0311. CAJUN CONTRACTORS, INC. v. PEACHTREE PROPERTY SUB, LLC et al. A21A1120. CAJUN CONTRACTORS, INC. v. LAGUERRE et al.

BARNES, Presiding Judge.

Max Laguerre was injured by a metal pipe that fell from a construction site

located on the roof of a hotel. Laguerre settled his negligence claims against the

entities that owned and managed the hotel, Peachtree Property Sub, LLC, d/b/a

Crowne Plaza Hotel Atlanta-Midtown, FO Peachtree Property, LLC, d/b/a Crowne

Plaza Hotel Atlanta-Midtown, and AWH Partners, LLC, d/b/a Crowne Plaza Hotel

Atlanta-Midtown (collectively, the “Hotel Defendants”). A trial thereafter ensued on

Laguerre’s negligence claims against the general contractor for the construction

project, Cajun Contractors, Inc., and the jury awarded Laguerre compensatory and

punitive damages and apportioned 100 percent of the fault to Cajun. The trial court subsequently awarded attorney fees to Laguerre under OCGA § 9-11-68 based on

Cajun’s pre-trial rejection of his offer to settle. Additionally, the trial court granted

summary judgment in favor of the Hotel Defendants on their cross-claims for

contractual indemnification against Cajun. These companion appeals followed.

In Case No. A21A1120, Cajun appeals from the final judgment entered on the

jury verdict, contending that the trial court erred in denying its motions for directed

verdict, for judgment notwithstanding the verdict (“JNOV”), and for a new trial, and

that the trial court erred in its award of attorney fees to Laguerre. In Case No.

A21A0311, Cajun appeals the trial court’s order granting summary judgment in favor

of the Hotel Defendants on their contractual indemnification cross-claims. For the

reasons discussed more fully below, we affirm in Case No. A21A1120 but reverse in

Case No. A21A0311.

Case No. A21A1120

Following a jury verdict, we view the evidence in the light most favorable to

the prevailing party. Norton v. Holcomb, 299 Ga. App. 207, 208 (682 SE2d 336)

(2009). So viewed, the evidence shows that in March 2015, Cajun entered into a

contract to perform renovation work at the Crowne Plaza Atlanta – Midtown Hotel,

which was owned and managed by the Hotel Defendants (the “Trade Contract”).

2 Under the Trade Contract, Cajun agreed to supervise the work done on the renovation

project and to be liable for any loss or damage to the property or injuries to persons

caused by the action or neglect of its employees, subcontractors, or consultants. Cajun

also agreed to “keep the premises and the surrounding area free from accumulation

of waste materials or rubbish caused by operations under the [Trade] Contract,” and

to “take all reasonable actions needed to provide clean, unencumbered, well defined,

and safe access to the Owner’s facilities for vehicles, guests, visitors, and

employees.”

The renovation project was later expanded through a change-work order to

include renovations to the outside pool deck located on the roof of the hotel.1 As part

of the renovation, Cajun was to demolish cabanas and a wall along the edge of the

hotel roof. Cajun hired RYR Construction, LLC2 to perform some of the renovation

work at the hotel, including the painting of a ballroom and the pool deck renovation.

With respect to the pool deck renovation, workers for RYR considered Troy Bossier,

the president of Cajun, to be their boss on the job, and he was at the work site

1 The terms of the Trade Contract applied to change-work orders. 2 RYR Construction is sometimes referred to as “R&R” Construction in the record, but for ease of reference, we will refer to the company as RYR. The difference in name is not material to this appeal.

3 everyday and controlled the demolition work done in the pool area. No decisions

were made about the work done on the roof without first talking to Bossier, who

would come to the pool deck and direct RYR workers “as to what part of the project

they should be doing.” Cajun provided tools and equipment to RYR, told RYR what

hours it could work on the pool deck, devised the plan for demolishing the rooftop

wall and the sequence in which the work should be performed, and controlled the

work site and work flow.

Before the work on the pool renovation commenced, Cajun did not develop a

public hazard control plan or a site-specific safety plan, have any safety meetings

with RYR, or inform RYR of any safety rules. Cajun simply told RYR to ensure that

nothing fell from the roof, even though RYR had no prior experience performing

exterior demolition work. No barriers, catch platforms, enclosures, or perimeter debris

netting were installed to protect the public from hazards from the rooftop construction

site. No signs were placed outside the hotel to warn that there was construction

overhead, and no portion of the sidewalk below was blocked off with barricades. Nor

was any effort made to relocate the hotel taxi stand, which was in the front of the

hotel below the elevated construction site.

4 On July 20, 2015, RYR was demolishing part of the wall along the side of the

hotel roof, which caused the cabanas to shake. As a result of the shaking caused by

the demolition work, an unsecured eight-foot metal pipe fell from the roof of one of

the cabanas down the side of the hotel and struck Laguerre, a taxi cab driver, who was

standing outside of his cab at the hotel taxi stand.3 As a result of the impact, Laguerre

suffered a broken nose and injuries to his arm, face, head, and wrist, and he was

diagnosed with a “mild traumatic brain injury.” Prior to the incident, RYR had not

inspected the pool cabana roofs, even though one of RYR’s partners who worked on

the project acknowledged that he knew that there was a danger of objects or debris

falling from the hotel roof as a result of the demolition work, and even though Cajun

had provided ladders to RYR so that workers could see and reach the top of the

cabanas. Nor did Cajun ever direct RYR to conduct such an inspection as part of the

demolition plan that Cajun developed, and Cajun disavowed any responsibility to

itself conduct a safety inspection.

3 There was testimony at trial that the pipe was a conduit for containing electrical wiring, and that there were electrical subcontractors hired by Cajun working on the pool renovation. There was other, conflicting testimony that the pipe could have been placed on the cabana roof by a hotel employee.

5 In April 2017, Laguerre filed suit against the Hotel Defendants and Cajun.4

Laguerre’s complaint alleged, among other things, that Cajun breached its duty of

reasonable care by negligently failing to implement safety precautions for the pool

renovation project and by negligently training, supervising, and retaining those who

worked on the project. The complaint further alleged that Cajun was vicariously liable

under respondeat superior and agency principles for the negligence of RYR in failing

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blum v. Stenson
465 U.S. 886 (Supreme Court, 1984)
City of Burlington v. Dague
505 U.S. 557 (Supreme Court, 1992)
Towles v. Cox
351 S.E.2d 718 (Court of Appeals of Georgia, 1986)
Griffin v. AAA Auto Club South, Inc.
470 S.E.2d 474 (Court of Appeals of Georgia, 1996)
Robert & Co. Associates v. Pinkerton & Laws Co.
169 S.E.2d 360 (Court of Appeals of Georgia, 1969)
City of Atlanta v. Hofrichter/Stiakakis
663 S.E.2d 379 (Court of Appeals of Georgia, 2008)
Johnson v. GAPVT Motors, Inc.
663 S.E.2d 779 (Court of Appeals of Georgia, 2008)
Friedrich v. Fidelity National Bank
545 S.E.2d 107 (Court of Appeals of Georgia, 2001)
Stern v. Wyatt
231 S.E.2d 519 (Court of Appeals of Georgia, 1976)
Department of Transportation v. Montgomery Tank Lines, Inc.
575 S.E.2d 487 (Supreme Court of Georgia, 2003)
RBF HOLDING COMPANY v. Williamson
397 S.E.2d 440 (Supreme Court of Georgia, 1990)
Golosh v. Cherokee Cab Company
176 S.E.2d 925 (Supreme Court of Georgia, 1970)
Berryhill v. Georgia Community Support & Solutions, Inc.
638 S.E.2d 278 (Supreme Court of Georgia, 2006)
Union Camp Corp. v. Louisville & Nashville Railroad
202 S.E.2d 508 (Court of Appeals of Georgia, 1973)
Bartlett v. Holder Construction Co.
535 S.E.2d 537 (Court of Appeals of Georgia, 2000)
Atkins v. MRP Park Lake, L.P.
687 S.E.2d 215 (Court of Appeals of Georgia, 2009)
Norton v. Holcomb
682 S.E.2d 336 (Court of Appeals of Georgia, 2009)
Otis Elevator, Inc. v. HARDIN CONST. CO. GROUP
450 S.E.2d 41 (Supreme Court of South Carolina, 1994)
GAF CORPORATION v. Tolar Construction Co.
271 S.E.2d 811 (Supreme Court of Georgia, 1980)
Griffiths v. Rowe Properties
609 S.E.2d 690 (Court of Appeals of Georgia, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
CAJUN CONTRACTORS, INC. v. PEACHTREE PROPERTY SUB, LLC D/B/A CROWNE PLAZA HOTEL ATLANTA-MIDTOWN, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cajun-contractors-inc-v-peachtree-property-sub-llc-dba-crowne-plaza-gactapp-2021.