Woida v. United States

446 F. Supp. 1377, 11 ERC 1492, 8 Envtl. L. Rep. (Envtl. Law Inst.) 20305, 11 ERC (BNA) 1492, 1978 U.S. Dist. LEXIS 19107
CourtDistrict Court, D. Minnesota
DecidedMarch 10, 1978
Docket4-77 Civ. 443
StatusPublished
Cited by18 cases

This text of 446 F. Supp. 1377 (Woida v. United States) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Woida v. United States, 446 F. Supp. 1377, 11 ERC 1492, 8 Envtl. L. Rep. (Envtl. Law Inst.) 20305, 11 ERC (BNA) 1492, 1978 U.S. Dist. LEXIS 19107 (mnd 1978).

Opinion

MEMORANDUM ORDER

ALSOP, District Judge.

I. FACTUAL BACKGROUND

Cooperative Power Association (CPA) and United Power Association (UPA) are Minnesota cooperative associations. Both are engaged in the business of the generation and transmission of electric power to their respective members. CPA’s members are 19 rural electric cooperative distribution systems. CPA’s member cooperatives serve residential, agricultural and commercial users in west central and southern Minnesota. UPA’s members are 15 rural electric cooperative distribution systems. UPA’s member cooperatives serve residential, agricultural and commercial users in central, north central and east central Minnesota and in northwest Wisconsin.

In 1972, CPA and UPA initiated discussions which eventually led to a decision to construct a joint electric generation and transmission project (CU project). The CU project is to consist of the following components and associated facilities: (1) “Coal Creek Station,” a 1000 megawatt lignite coal-fired steam electric generating plant located near Underwood, North Dakota; (2) a facility located at the Coal Creek Station site to be used to convert the alternating current (ac) produced there into direct current (dc); (3) a ± 400 kilovolt (kV) dc high *1381 voltage transmission line (HVTL) which is to connect Coal Creek Station with “Dickinson Substation,” a conversion facility located near Delano, Minnesota; (4) a 345 kV ac double circuit HVTL which is to run from Dickinson Substation to “Coon Creek Substation,” located in Coon Rapids, Minnesota; and (5) a 345 kV ac single circuit HVTL which is to run from Dickinson Substation to the site of a generating facility owned by Northern States Power Company and located near Mankato, Minnesota. The CU project is scheduled to commence commercial operation on November 1, 1978.

Falkirk Mining Company has contracted with CPA and UPA to supply the lignite coal to be burned at Coal Creek Station. That coal is to be extracted from a strip mine located on lands adjacent to the Coal Creek Station site.

At the time that the decision to construct the CU project was made, it was determined that it would be necessary to develop a communication system to link Coal Creek Station to the areas in which the electricity generated was to be used, but the type of system to be installed was not determined until much later. Subsequently, CPA and UPA decided to build and are in the process of building separate microwave radio communication systems which will be used in connection with the CU project.

The Rural Electrification Administration (REA) has provided and will provide loans and loan guarantees to finance much of the CU project. The REA is also guaranteeing that CPA and UPA will perform their contract with Falkirk Mining Company and is providing loans to finance the construction of the microwave radio communication systems. Because financing the CU project constitutes a major federal action, the REA is required to comply with the provisions of the National Environmental Policy Act (NEPA), 42 U.S.C. § 4321 et seq.

The REA began an environmental review of the CU project in November 1972. Subsequently, the REA prepared and made available a draft environmental impact statement (EIS) for the project. On October 3,1973, the REA published notice of the availability of this draft EIS in the Federal Register. Copies of the draft EIS were sent to other federal agencies with jurisdiction over or special expertise concerning various aspects of the CU project, to regional, state and local clearinghouses with an interest in the CU project and to members of the general public who requested them. Comments were solicited. The REA individually answered and incorporated all comments which the agency received into the final EIS. On August 4, 1974, the REA issued the final EIS. On August 6, 1974, the REA published notice of the availability of the final EIS in the Federal Register. Copies of the final EIS were sent to the federal, state and local agencies which had commented on the draft EIS, to appropriate regional, state and local clearinghouses and to members of the public who requested them.

On April 8, 1975, CPA and UPA applied to the Minnesota Environmental Quality Council (MEQC) to designate a corridor for the ± 400 kV dc HVTL. The MEQC then held nine (9) informational meetings and conducted eleven (11) public hearings. After the hearings process concluded, the MEQC hearing examiner issued proposed findings of fact and made a recommendation. On October 3, 1975, the MEQC met, adopted the hearing examiner’s recommendation and issued a certificate of corridor compatibility.

On December 9, 1975, CPA and UPA applied to the MEQC to designate a route for the ± 400 kV dc HVTL within the approved corridor and to issue a construction‘permit. The MEQC made an independent environmental analysis and prepared its own EIS. It also held twelve (12) informational meetings and conducted twelve (12) public hearings. On June 3, 1976, the MEQC designated a route within the approved corridor and granted a construction permit.

On October 6, 1975, CPA and UPA applied to the Minnesota Energy Agency (MEA) for a certificate of need. The MEA then conducted fourteen (14) days of public hearings. On April 2,1976, the MEA issued a certificate of need.

*1382 On June 29, 1976, CPA and UPA applied to the North Dakota Public Service Commission (PSC) for a construction permit to build the ± 400 kV dc HVTL. The PSC conducted fourteen (14) days of public hearings. It also made an extensive analysis of the line’s impact on the environment. On December 17, 1976, the PSC designated a route and granted a construction permit.

After the MEQC and the PSC had designated the route for the ± 400 kV dc HVTL, the REA reviewed the effect of the state agencies’ actions. The REA determined that, although there were some differences between the designated route and the one proposed by the REA, the designated route was within the corridor proposed by the REA and did not significantly alter the HVTL’s impact on the environment. The REA concluded that the differences did not warrant either the publication of a draft supplement to the EIS or the solicitation of comments from other agencies or from the public. After it had reached that conclusion, the REA consulted with the Council on Environmental Quality (CEQ) and proposed that the REA dispense with issuing a draft statement, notice and the opportunity for comment and that it instead publish only a final supplement which would inform government agencies and the public of the route changes. The CEQ raised no objection to the procedure proposed by the REA.

In December 1976, the REA issued a supplement to the final EIS in which route changes in Minnesota were described (Minnesota supplement). On January 4, -1977, the REA published notice of the availability of that supplement in the Federal Register. In March 1977, the REA issued a second supplement in which route changes in North Dakota were described (North Dakota supplement). On March 18, 1977, the REA published notice of the availability of the North Dakota supplement in the Federal Register.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sierra Club v. Marsh
744 F. Supp. 352 (D. Maine, 1989)
White Earth Band of Chippewa Indians v. Joseph N. Alexander, Individually and as Commissioner of Natural Resources for the State of Minnesota and Fredean C. Hammer, Director of the Division of Enforcement and Field Service for the Department of Natural Resources, Counties of Mahnomen, Clearwater and Becker, Elmer H. Winter, Kenneth Albertson, Joe Klinkhammer, Ed Grahame, United States of America v. State of Minnesota, Appellee/cross White Earth Band of Chippewa Indians v. Joseph N. Alexander, Individually and as Commissioner of Natural Resources for the State of Minnesota and Fredean C. Hammer, Director of the Division of Enforcement and Field Service for the Department of Natural Resources, Counties of Mahnomen, Clearwater and Becker, Elmer W. Winter, Kenneth Albertson, Joe Klinkhammer, Ed Grahame, United States of America v. State of Minnesota, White Earth Band of Chippewa Indians v. Joseph N. Alexander, Individually and as Commissioner of Natural Resources for the State of Minnesota and Fredean C. Hammer, Director of the Division of Enforcement and Field Service for the Department of Natural Resources, Counties of Mahnomen, Clearwater and Becker, Elmer W. Winter, Kenneth Albertson, Joe Klinkhammer, Ed Grahame, United States of America v. State of Minnesota, White Earth Band of Chippewa Indians v. Joseph N. Alexander, Individually and as Commissioner of Natural Resources for the State of Minnesota and Fredean C. Hammer, Director of the Division of Enforcement and Field Service for the Department of Natural Resources, Counties of Mahnomen, Clearwater and Becker, Elmer W. Winter, Kenneth Albertson, Joe Klinkhammer, Ed Grahame
683 F.2d 1129 (Eighth Circuit, 1982)
White Earth Band of Chippewa Indians v. Alexander
683 F.2d 1129 (Eighth Circuit, 1982)
Sutter Sensible Planning, Inc. v. Board of Supervisors
122 Cal. App. 3d 813 (California Court of Appeal, 1981)
Dataphase Systems, Inc. v. C L Systems, Inc.
640 F.2d 109 (Eighth Circuit, 1981)
ABA Distributors, Inc. v. Adolph Coors Co.
496 F. Supp. 1194 (W.D. Missouri, 1980)
Wampler v. Goldschmidt
486 F. Supp. 1130 (D. Minnesota, 1980)
Minnesota Public Interest Research Group v. Adams
482 F. Supp. 170 (D. Minnesota, 1979)
Barcelo v. Brown
478 F. Supp. 646 (D. Puerto Rico, 1979)
State of Alaska v. Carter
462 F. Supp. 1155 (D. Alaska, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
446 F. Supp. 1377, 11 ERC 1492, 8 Envtl. L. Rep. (Envtl. Law Inst.) 20305, 11 ERC (BNA) 1492, 1978 U.S. Dist. LEXIS 19107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/woida-v-united-states-mnd-1978.