Minnesota Public Interest Research Group v. Adams

482 F. Supp. 170, 14 ERC 1695, 14 ERC (BNA) 1695, 1979 U.S. Dist. LEXIS 8116
CourtDistrict Court, D. Minnesota
DecidedDecember 7, 1979
DocketCiv. 4-73-461
StatusPublished
Cited by2 cases

This text of 482 F. Supp. 170 (Minnesota Public Interest Research Group v. Adams) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Minnesota Public Interest Research Group v. Adams, 482 F. Supp. 170, 14 ERC 1695, 14 ERC (BNA) 1695, 1979 U.S. Dist. LEXIS 8116 (mnd 1979).

Opinion

MacLAUGHLIN, District Judge.

This matter is before the Court on the motion of plaintiffs, the Minnesota Public Interest Research Group [hereinafter MPIRG], the Dakota County Environmental Protective Association [hereinafter DCE-PA], and plaintiff-intervenor the City of Sunfish Lake, for a preliminary injunction which seeks to enjoin the defendants from proceeding with the construction of the final 11 miles of Interstate 494, a part of the interstate highway beltline route which encircles the Twin Cities metropolitan area. In 1974, the plaintiffs and the state and federal defendants entered into a stipulation whereby defendants agreed to refrain from proceeding in the construction or development of Interstate 494 in order to prepare an environmental impact statement in accordance with Section 102 of the National Environmental Policy Act (NEPA). 42 U.S.C. § 4332. A final environmental impact statement (FEIS) has been prepared and approved by the defendants, and as no expiration date was specified in the 1974 stipulation of the parties, plaintiffs have made the present motion for a preliminary injunction to halt construction. Plaintiffs’ principal contentions with respect to their motion for a preliminary injunction are that the FEIS is both proeedurally and substantively inadequate under NEPA, and that the proposed construction violates the provisions of the Minnesota Environmental Policy Act (MEPA), Minn.Stat. Ch. 116D, and the Minnesota Environmental Rights Act (MERA), Minn.Stat. Ch. 116B. At the hearing on plaintiffs’ motion, the Court orally denied plaintiffs’ request for a preliminary injunction. The Court, having considered the entire record, hereby makes the following findings of fact and conclusions of law pursuant to Federal Rule of Civil Procedure 52(a). The Court has jurisdiction of this controversy under 28 U.S.C. § 1331, 28 U.S.C. § 1346 and 5 U.S.C. § 701.

THE PARTIES

MPIRG is a Minnesota non-profit corporation supported by contributions from student members attending various colleges and universities in Minnesota and is involved in various public interest issues, including environmental protection. DCEPA is also a Minnesota non-profit corporation *174 whose members reside in Dakota County, and this organization is likewise engaged in efforts to preserve the environment. The City of Sunfish Lake is a small residential city located in northern Dakota County along the proposed route of Interstate 494.

The individual defendants are various officials of the federal and state agencies [the federal defendants and the state defendants] responsible for the Interstate 494 construction proposal. The Minnesota Department of Transportation [hereinafter MDOT] is also named as a defendant.

THE PROPOSED ACTION

The proposed interstate highway construction. advocated by the defendants involves the building of a six lane interstate highway beginning near 24th Avenue in Bloomington and extending eastward across the Minnesota River and Dakota County to the Mississippi River Bridge directly east of South Saint Paul. The proposed construction would complete the southern component of the Interstate 494 beltline which surrounds the Twin Cities metropolitan area. The proposed highway will run in an east-west direction and contemplates the construction of a bridge across the Minnesota River. Thus, the beginning point and terminus with respect to the present proposal were predetermined, as the interstate highway has previously been constructed west of 24th Avenue in Bloomington and east of the Mississippi River Bridge. The present proposal involves approximately 11 miles of highway construction. Prior to the actual construction, the federal and state defendants must obtain a number of permits from both federal and state agencies.

Dakota County encompasses an area located directly south of the City of St. Paul, east of Bloomington and southeast of Minneapolis, and is bounded on the north, east and west by the Minnesota and Mississippi Rivers. The northern portion of Dakota County includes the communities of West St. Paul, South St. Paul, Mendota Heights, Eagan, Sunfish Lake, Mendota, and Inver Grove Heights. While commercial and industrial development and the population of Dakota County has continually increased, it has also retained a certain rural character. The major east-west thoroughfare in northern Dakota County is T.H. (Trunk Highway) 110 which intersects with T.H. 13 in the western portion of Dakota County, and eventually intersects with T.H. 55, T.H. 49 (Dodd Road), T.H. 52 (Robert Street), and T.H. 3. T.H. 55 runs generally in a northwest-southeast direction. Interstate 35E, in various stages of construction, is eventually planned by defendants to run in a north-south direction through western Dakota County. The Mendota Bridge crosses the Minnesota River near Mendota, and three highways — T.H.’s 3, 110 and'55 — all intersect in a confined area southeast of this bridge in Dakota County. According to the FEIS, this intersection has currently reached its theoretical traffic capacity. The FEIS indicates that the automobile accident rate at this intersection is consistently among the highest in the eastern section of the Twin Cities metropolitan area.

The alternate selected, alternate B3, was one of three options within the “preferred corridor,” which is basically an area which runs in nearly a straight east-west direction consistent with the beginning point and terminus of the already constructed Interstate 494 from Bloomington to the Mississippi River Bridge. The construction of the selected alternate B3 will result in the impairment of some wetlands, vegetation and wildlife, and the use of the completed interstate highway will to some degree contribute to air and noise pollution.

THE FINAL ENVIRONMENTAL IMPACT STATEMENT

The final environmental impact statement (FEIS) for the Interstate 494 project was prepared by the personnel of MDOT and ultimately adopted by the Regional Federal Highway Administration on January 23, 1979. The Minnesota Environmental Quality Board (MEQB) approved the FEIS in February of 1979. A draft environmental impact statement (DEIS) had previously been released, and a public hearing was held on the DEIS in August of 1977. The plaintiffs took an active role in the public hearing with respect to the *175 DEIS, and made their specific objections known to agency planners. Incorporated in the FEIS is a “Final Section 4(f) Statement for Interstate 494,” which is necessary because the proposed construction requires the use of land from Fort Snelling State Park. The FEIS and Final 4(f) Statement is a 233 page document replete with tables, diagrams, maps and analysis. The FEIS focuses on five basic alternatives — alternates Bl, B2 and B3 (all located within the preferred corridor), alternate A (which is variously referred to as the “historic” alternate and incorporates T.H. 110 in its design) and the “no build” alternative.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Citizens Concerned About Jet Noise, Inc. v. Dalton
48 F. Supp. 2d 582 (E.D. Virginia, 1999)

Cite This Page — Counsel Stack

Bluebook (online)