Iowa Student Public Interest Research Group v. Callaway

379 F. Supp. 714
CourtDistrict Court, S.D. Iowa
DecidedAugust 2, 1974
DocketCiv. 74-8-2
StatusPublished
Cited by12 cases

This text of 379 F. Supp. 714 (Iowa Student Public Interest Research Group v. Callaway) is published on Counsel Stack Legal Research, covering District Court, S.D. Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Iowa Student Public Interest Research Group v. Callaway, 379 F. Supp. 714 (S.D. Iowa 1974).

Opinion

MEMORANDUM AND ORDER

HANSON, Chief Judge.

This cause of action arises under the National Environmental Policy Act (NEPA), 42 U.S.C., Section 4321 et seq. Jurisdiction of this Court is invoked pursuant to 5 U.S.C., Sections 701 et seq.; 28 U.S.C., Section 1362; 28 U.S.C., Section 1331; 28 U.S.C., Section 1337; and 28 U.S.C., Sections 2201 and 2202.

I.

The plaintiffs are seeking to restrain the defendants from proceeding with a contract involving Phase III of the construction of the Saylorville Dam Project whereby trees, brush, and fences would be removed from the permanent pool area of the dam site in preparation for closure of the dam in the summer of 1974. The plaintiffs wish to halt this project pending the release of the final environmental impact statement.

The plaintiffs have alleged that the: Clearing and destruction of the trees, and further construction, would have an adverse effect on the environment of the plaintiffs which would be avoided by and in an alternative presently under consideration pursuant to NEPA. One such alternative under study is discontinuance of the project all together.
“That the issuance of a notice to proceed by the defendant [on the clearing contract] and subsequent commencement of demolition of such trees pursuant to the contract above cited, irretrievably blocks any realistic appraisal of the alternative being considered, and renders the consideration of such alternative an exercise in futility.”

The plaintiffs prayed for a temporary restraining order restraining the defendants from issuing any notice to proceed on the clearing contract. The plaintiffs also pray for preliminary and permanent injunctive and declaratory and request this Court to:

“Permanently enjoin defendants from pursuing any activity or project, contract or work order, or activating or sponsoring, any project which conflicts, limits, precludes, or in any way hinders, a realistic appraisal of all considered alternatives as contained in the Draft Environmental Impact Statement as herein filed, until such time as subsequent to the filing of the Final Environmental Impact Statement.”

The plaintiffs also pray that the Court enter a judgment declaring the defendants’ actions in pursuing and in continuing the Saylorville Dam Project *716 to be in violation of the provisions of the National Environmental Policy Act, 42 U.S.C., Sections 4321 et seq.

On the 11th day of January, 1974, this Court entered a Temporary Restraining Order restraining the defendants from issuing any written Notice to Proceed to contractors relating to the clearing or removal of trees within the project area pending a full hearing upon preliminary injunctive relief.

The immediate effect of the TRO was to delay notice to proceed on a contract awarded on December 28, 1973 for $639,000. General provisions of this contract were for the removal of trees, brush and fences only in the conservation pool [the permanent lake] of the Saylorville Project. This would be a maximum elevation of the permanent conservation pool. [The additional three foot clearance is for a freeboard requirement.] The clearing contract covers an area of 1,618 acres consisting of 550 acres of brush, and the remainder of trees.

On February 7, 1970 this Court held a hearing at which both parties agreed that this cause could be fully submitted as it relates to the Motion for Summary Judgment filed by the defendants and injunctive and declaratory relief for the plaintiffs. This Court received evidence in the form of affidavits and live testimony which both parties agreed could be accepted by the Court for the determination of both Summary Judgment and declaratory and injunctive relief. The Court considers this matter to be submitted upon the merits at this time.

II.

The Saylorville Dam Project is a multi-purpose project for flood control, low-flow augmentation, fish and wildlife management and recreation, located on the Des Moines River, a tributary of the Mississippi River, in Polk, Dallas and Boone Counties, Iowa, approximately 5.5 miles above the city of Des Moines. The first surveys of flood damage in the Des Moines River basis which ultimately led to the project began in the 1940’s. The various studies and surveys culminated in a report submitted to Congress later identified as Senate Documents No. 9 85th Congress First Session and was filed with Congress in 1955. Subsequently the Saylorville Lake Project was authorized by Congress in the Flood Control Act of 1958. The first designing of the project began in 1959 with Congress first appropriating money for the project in 1960. There have been yearly appropriations from Congress since 1960.

The Saylorville Dam, as planned, is an earth embankment dam with a length of 6,750 feet and a height above sea level of 915 feet, with an average height above the valley floor of 105 feet. The dam at its top is 44 feet wide and the average bottom width is 870 feet. The conservation pool is planned at 833 feet m. s. 1. with a maximum flood pool at elevation 890 feet.

The construction of the dam itself was divided into three stages. Stage I consisted of construction of about one-half the total length of the dam from near the west abutment to a point near the Des Moines River, about one-half the total height, and excavation of most of the spillway channel. Stage I construction was completed in 1960 at a cost of about 1.8 million dollars.

Stage II construction consisted of the construction of the control structure, conduit, spilling basin, concrete spillway structure, excavation of the portion of the approach and discharge channels, construction of a dam embankment to tie into the west abutment, and excavation of the remainder of the spillway channel. This construction was completed in April, 1971 at a cost of 4.9 million dollars.

Stage III of the construction consists of an additional 55 feet of fill on top of Stage I and Stage II construction, and making the permanent river closure completing the entire dam. A contract for construction of Stage III *717 was awarded on December 29, 1972. Stage III construction is under present scheduling and is to be completed in 1975. The closure of the river is scheduled to occur in the summer of 1974.

The clearing contract for clearance to the 836 foot level, which is the subject of tins lawsuit, was awarded on December 28, 1973 after an invitation for bids on November 20, 1973 and bid opening on December 20, 1973. The contractor’s performance and payment bonds and executed contract document were received on January 16, 1974. The Corps of Engineers could not issue notice to proceed due to the temporary restraining order.

The Saylorville Dam Project is estimated to cost a total of $72,500,000, of which approximately $48,000,000 has been expended to date. Expressed in percentage terms, the project is approximately 66 percent complete.

III.

In the planning of a Corps of Engineers water resources project, master plans are prepared for the Corps of Engineers for each project. The initial step in the process of developing an Environmental Impact Statement or a master plan is essentially the same.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moore Business Forms, Inc. v. Wilson
953 F. Supp. 1056 (N.D. Iowa, 1996)
Headwaters, Inc. v. Bureau of Land Management
665 F. Supp. 873 (D. Oregon, 1987)
Barcelo v. Brown
478 F. Supp. 646 (D. Puerto Rico, 1979)
Sierra Club v. Cavanaugh
447 F. Supp. 427 (D. South Dakota, 1978)
Woida v. United States
446 F. Supp. 1377 (D. Minnesota, 1978)
Organizations United for Ecology v. Bell
446 F. Supp. 535 (M.D. Pennsylvania, 1978)
Dalsis v. Hills
424 F. Supp. 784 (W.D. New York, 1976)
Friends of Yosemite v. Frizzell
420 F. Supp. 390 (N.D. California, 1976)
Moore v. State
553 P.2d 8 (Alaska Supreme Court, 1976)
Concerned About Trident v. Schlesinger
400 F. Supp. 454 (District of Columbia, 1975)
Save the Courthouse Committee v. Lynn
408 F. Supp. 1323 (S.D. New York, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
379 F. Supp. 714, Counsel Stack Legal Research, https://law.counselstack.com/opinion/iowa-student-public-interest-research-group-v-callaway-iasd-1974.