No Power Line, Inc. v. Minnesota Environmental Quality Council

262 N.W.2d 312, 11 ERC 1001, 8 Envtl. L. Rep. (Envtl. Law Inst.) 20310, 11 ERC (BNA) 1001, 1977 Minn. LEXIS 1283
CourtSupreme Court of Minnesota
DecidedSeptember 30, 1977
Docket48014, 48036 and 48043
StatusPublished
Cited by74 cases

This text of 262 N.W.2d 312 (No Power Line, Inc. v. Minnesota Environmental Quality Council) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
No Power Line, Inc. v. Minnesota Environmental Quality Council, 262 N.W.2d 312, 11 ERC 1001, 8 Envtl. L. Rep. (Envtl. Law Inst.) 20310, 11 ERC (BNA) 1001, 1977 Minn. LEXIS 1283 (Mich. 1977).

Opinions

SHERAN, Chief Justice.

Appellants1 appeal from the final orders of a specially appointed three-judge district court panel2 composed of Judge Ronald E. Hachey of St. Paul, Judge Charles W. Kennedy of Wadena, and Judge Thomas J. Stahler of Morris affirming decisions of the Minnesota Environmental Quality Council (MEQC)3 and the Minnesota Energy Agency (MEA) approving the joint construction by Cooperative Power Association (CPA) and United Power Association (UPA) of a high-voltage transmission line (HVTL) from the North Dakota border to Coon Rapids, Minnesota. The panel held that MEQC’s designation of a corridor for the HVTL,4 the later designation of a route within that corridor,5 and the issuance of a construction permit6 as well as MEA’s grant of a certificate of need7 for the HVTL were “proper and substantially supported by evidence in the record.” The panel rejected the claim that MEQC and MEA had violated the Minnesota Environmental Policy Act (MEPA)8 and denied appellants’ requests to introduce additional testimony and to remand the proceedings to MEQC and MEA. As part of its orders the panel also issued a 10-day stay which was extended by this court until August 25, 1977, the day on which oral arguments were to be presented to the supreme court sitting en banc.

Appellants are a number of farmer-citizen organizations formed over the past few years in response to the proposal by CPA/UPA to construct a HVTL across this part of Minnesota. No Power Line, Inc. (NPL), Save Our Countryside, Inc. (SOC), and Families Are Concerned Too, Inc. (FACT) are Minnesota nonprofit corpora[317]*317tions with a joint membership of over 200 citizens residing primarily in Grant, Douglas, and Pope Counties. Preserve Grant County (PGC) is a noncorporate association with approximately 40 members, most of whom reside in Grant County. Most of the members of these organizations allegedly are landowners who own property in the corridor designated for the proposed HVTL. During the pendency of the administrative hearings, NPL was a member of Counties United for Rural Environment (CURE), which participated through counsel in all the proceedings, but NPL has partially separated itself from CURE for purposes of this appeal. The members of FACT include many current and former members of the other organizations, and, although FACT was incorporated just prior to the consolidation of the appeals to the district court panel, its members allegedly participated in the various public hearings held throughout the affected counties through which the HVTL is routed.

Respondents CPA and UPA are wholesale suppliers of electric power and energy. CPA is composed of 19 rural cooperatives and UPA of 15; together they provide service to approximately 250,000 accounts in Minnesota and to three Wisconsin counties. In 1973, they agreed to construct an electric generating plant and conversion facility9 in North Dakota, approximately 427 miles (of which about 172 miles will lie in Minnesota) of ± 400 Kilovolt (kv) dc HVTL from the Coal Creek Station in North Dakota to a conversion facility in Wright County, and approximately 28 miles of 345 kv ac double circuit HVTL from there to a CPA/UPA facility in Coon Rapids, Anoka County.

Prior to May 24, 1973, the effective date of the Power Plant Siting Act (PPSA),10 the location and construction of electrical transmission lines were not regulated on a statewide basis. Instead, a public utility that wished to construct a power line had to secure permits from the local authorities of the counties and municipalities through which it proposed to locate its facilities.- In an attempt to ensure that the future development of power generating plants and high-voltage transmission lines in the state would proceed in an orderly and rational fashion11 and to guarantee wide-ranging, continuous public participation,12 the legislature passed the PPSA. The legislature included a savings clause which exempted from the operation of the act those—

“* * * high voltage transmission lines, the construction of which will commence prior to July 1, 1974; provided * * * that within 90 days following the date of enactment, the affected utility shall file with the council a written statement identifying such transmission lines, their planned location, and the estimated date for commencement of construction.” 13

CPA and UPA initially availed themselves of the savings clause. On August 22, 1973, they notified MEQC by letter that they planned to construct HVTLs prior to July 1, 1974, and on November 13, 1973, MEQC adopted a resolution that the CPA/UPA transmission line satisfied the requirements of the savings clause. On [318]*318June 28, 1974, the utilities sent a letter to MEQC detailing 14 separate acts of construction that had been taken to satisfy the savings clause. Nevertheless, on April 3, 1975, the utilities withdrew this project from the savings clause and submitted it to the jurisdiction of MEQC.14

On April 8, 1975, MEQC resolved to accept the CPA/UPA application for a corridor designation and a certificate of corridor compatibility pursuant to Minn.St. 1976, §§ 116C.57 and 116C.61, respectively. CPA/UPA, in its application, proposed two alternative corridors for the HVTL (I and II). On June 10, 1975, MEQC expanded the study area to include two additional corridors (III and IV), and on August 27, 1975, the Power Plant Siting Staff of MEQC recommended a fifth corridor (V). All the proposed corridors fixed the point of entry of the line from North Dakota. MEQC appointed a hearing officer, and 11 public hearings were held between July 21, 1975, and August 27, 1975. On September 12, 1975, the Corridor Evaluation Committee,15 which had been appointed by MEQC, submitted its final report, and on September 19, 1975, the hearing officer submitted his findings of fact, conclusions, and recommendations.

On October 3, 1975, MEQC adopted the hearing officer’s report, designated the corridor recommended by the hearing officer through Traverse, Grant, Douglas, Pope, Stearns, Meeker, Wright, and Hennepin Counties, and issued a “Certificate of Corridor Compatibility.”

Appellants appealed to district court for judicial review of this decision on December 3, 1975.16 After the appeal was dismissed, and further appeal was taken to this court, the case was remanded for trial17 and later consolidated with other appeals stemming from the approval of the HVTL.

On October 6, 1975, CPA/UPA applied to MEA for a certificate of need pursuant to Minn.St. 1976, § 116H.13.18 MEA appointed a hearing officer, and 14 days of public hearings were held between December 8, 1975, and January 15, 1976. On March 5, 1976, the hearing officer submitted his report and recommendations, and on April 2, 1976, MEA issued a certificate of need. On May 3, 1976, appellants appealed for judicial review of this decision.

On December 9, 1975, pursuant to § 116C.57, subd. 2, CPA/UPA applied for a construction permit for construction of the HVTL within the approved corridor. Twelve public hearings were held between March 22, 1976, and April 14, 1976, at least one in each of the affected counties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Applications of Enbridge Energy, Ltd.
930 N.W.2d 12 (Court of Appeals of Minnesota, 2019)
Marriage of Gossman v. Gossman
847 N.W.2d 718 (Court of Appeals of Minnesota, 2014)
Centra Homes, LLC v. City of Norwood Young America
834 N.W.2d 581 (Court of Appeals of Minnesota, 2013)
Marriage of Perry v. Perry
749 N.W.2d 399 (Court of Appeals of Minnesota, 2008)
Fine v. Bernstein
726 N.W.2d 137 (Court of Appeals of Minnesota, 2007)
Allen v. City of Mendota Heights
694 N.W.2d 799 (Court of Appeals of Minnesota, 2005)
Irwin v. Goodno
686 N.W.2d 878 (Court of Appeals of Minnesota, 2004)
Star Tribune Co. v. University of Minnesota Board of Regents
683 N.W.2d 274 (Supreme Court of Minnesota, 2004)
State v. Harris
667 N.W.2d 911 (Supreme Court of Minnesota, 2003)
Carlson v. Chermak
639 N.W.2d 886 (Court of Appeals of Minnesota, 2002)
Info Tel Communications, LLC v. U.S. West Communications, Inc.
592 N.W.2d 880 (Court of Appeals of Minnesota, 1999)
Minnegasco v. Minnesota Public Utilities Commission
549 N.W.2d 904 (Supreme Court of Minnesota, 1996)
Contel of Minnesota, Inc. v. Minnesota Public Utilities Commission
532 N.W.2d 583 (Court of Appeals of Minnesota, 1995)
Iron Rangers for Responsible Ridge Action v. Iron Range Resources
531 N.W.2d 874 (Court of Appeals of Minnesota, 1995)
Minnesota League of Credit Unions v. Minnesota Department of Commerce
467 N.W.2d 42 (Court of Appeals of Minnesota, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
262 N.W.2d 312, 11 ERC 1001, 8 Envtl. L. Rep. (Envtl. Law Inst.) 20310, 11 ERC (BNA) 1001, 1977 Minn. LEXIS 1283, Counsel Stack Legal Research, https://law.counselstack.com/opinion/no-power-line-inc-v-minnesota-environmental-quality-council-minn-1977.