W.J. O'Neil Co. v. Shepley, Bulfinch, Richardson & Abbott, Inc.

765 F.3d 625, 2014 FED App. 0213P, 2014 U.S. App. LEXIS 16607, 2014 WL 4237159
CourtCourt of Appeals for the Sixth Circuit
DecidedAugust 28, 2014
Docket13-2320
StatusPublished
Cited by19 cases

This text of 765 F.3d 625 (W.J. O'Neil Co. v. Shepley, Bulfinch, Richardson & Abbott, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W.J. O'Neil Co. v. Shepley, Bulfinch, Richardson & Abbott, Inc., 765 F.3d 625, 2014 FED App. 0213P, 2014 U.S. App. LEXIS 16607, 2014 WL 4237159 (6th Cir. 2014).

Opinions

COLE, C.J., delivered the opinion of the court, in which BOGGS, J., joined. McKEAGUE, J. (p. 635), delivered a separate dissenting opinion.

OPINION

COLE, Chief Judge.

After losing millions of dollars because of delays and coordination failures in building a hospital, W.J. O’Neil Company sued its construction manager in state court. The two ended up in arbitration. Shepley, Bulfinch, Richardson & Abbott, Inc., and Smith Seekman Reid, Inc., the defendants in this case, were added to the arbitration on indemnity claims. In the arbitration, O’Neil did not formally assert claims against the instant defendants, but O’Neil’s claims against its construction manager arose from the defendants’ defective and inadequate design of the hospital. O’Neil won the arbitration against its construction manager, but the construction manager did not establish its indemnity claims, so the defendants were not held liable. No party sought judicial confirmation or review of the arbitration award.

O’Neil then sued the defendants in federal court. The district court dismissed the claims, finding them barred by Michigan’s doctrine of res judicata. We find this conclusion in error. An arbitration award cannot bar a claim that the arbitrator lacked authority to decide, and an arbitrator lacks authority to decide a claim that the parties did not agree to arbitrate. Here, O’Neil did not agree to arbitrate the [628]*628instant claims. Accordingly, we reverse the district court’s orders, vacate the judgment, and remand for further proceedings.

I.

The parties helped design and construct the Cardiovascular Center Hospital at the University of Michigan in Ann Arbor. The University hired Shepley, Bulfinch, Richardson & Abbott, Inc., to serve as the project’s architect. Shepley Bulfinch, in turn, retained Smith Seckman Reid, Inc., to provide design services related to the mechanical, electrical, plumbing, and fire-protection systems of the new hospital. Separately, the University hired Barton Malow Company to serve as the construction manager. Barton Malow subcontracted W.J. O’Neil Company to serve as the mechanical contractor to supply and install plumbing, heating, ventilation, and cooling systems. O’Neil did not have a contract with Shepley Bulfinch or Smith Seckman.

According to O’Neil, design errors and other failures caused it to incur substantial damages during the construction. To recover its damages, O’Neil sued Barton Ma-low, Shepley Bulfinch, and Smith Seckman in state court in Michigan. The court dismissed Barton Malow because its contract with O’Neil required the two to resolve their disputes by binding arbitration. The court initially stayed O’Neil’s claims against Shepley Bulfinch and Smith Seck-man, but it eventually entered a stipulated order dismissing the claims without prejudice in light of the arbitration.

O’Neil filed a demand for arbitration against Barton Malow, alleging breach, cardinal change, and abandonment of contract “arising from substantial design errors and mismanagement of the project by the owner and general contractor.” O’Neil sought $19 million in damages. Barton Malow then filed its own demand for arbitration against the University, pursuant to their separate contract, seeking indemnity for the alleged design errors by the design team. The two arbitrations were consolidated over O’Neil’s objection. The University filed a demand for indemnification against Shepley Bulfinch, which filed a demand for indemnification against Smith Seckman. Thus began a consolidated arbitration involving O’Neil, Barton Malow, the University, Shepley Bulfinch, and Smith Seckman.

The arbitration was quite large. O’Neil admits that discovery was “substantial.” And by Smith Seckman’s count, the hearing lasted 42 days over the course of 9 months, the parties introduced more than 1400 exhibits, and more than 50 witnesses testified. In the arbitration, O’Neil formally asserted claims only against Barton Malow, the construction manager, but O’Neil’s claims implicated and were hostile to Shepley Bulfinch and Smith Seckman, the design team.

After hearing the evidence and the parties’ arguments, the arbitrators issued an interim award in O’Neil’s favor for $2.4 million. They found that O’Neil incurred damages “due to a change in the schedule caused by many factors, but largely due to the [hospital] plans being more difficult, time consuming, and expensive to coordinate ... all of which constitutes a breach of O’Neil’s contract [with Barton Malow].” (Interim Award of Arbitrators, R. 19-26, PagelD 1133.) The arbitrators also found that Barton Malow failed to establish its indemnity claims against the University, noting that “the bulk of the claims that [Barton Malow] might have had against [the University] were all settled and released” by change orders Barton Malow had signed with the University. (Id. at 1134.) The arbitrators thus denied the indemnity claims flowing through the University to Shepley Bulfinch and Smith Seckman. A few months later, the arbi[629]*629trators issued a final award, of which no party sought judicial confirmation or review.

O’Neil, a Michigan corporation, then filed this suit against Shepley Bulfinch and Smith Seckman, both non-Michigan corporations. O’Neil asserted claims for professional negligence, tortious interference, and innocent misrepresentation against both companies based on their design failures. Shepley Bulfinch and Smith Seckman jointly moved to dismiss on the pleadings under Federal Rule of Civil Procedure 12(c), and for summary judgment under Rule 56.

The district court granted the motion (under both rules), holding that Michigan’s res judicata doctrine barred O’Neil’s claims. The court declined to rule on three other arguments presented by the defendants for dismissal or summary judgment. O’Neil later filed a motion under Rule 59(e) to amend the district court’s judgment, but the court denied the motion. O’Neil timely appealed both rulings.

II.

This court reviews de novo an order dismissing an action under Federal Rule of Civil Procedure 12(c), a grant of summary judgment, and a denial of a Rule 59(e) motion seeking review of a grant of summary judgment. Fritz v. Charter Twp. of Comstock, 592 F.3d 718, 722 (6th Cir.2010); Santiago v. Ringle, 734 F.3d 585, 589 (6th Cir.2013); Bruederle v. Louisville Metro Gov’t, 687 F.3d 771, 776 (6th Cir.2012). We also review de novo a district court’s application of res judicata. Buck v. Thomas M. Cooley Law Sch., 597 F.3d 812, 816 (6th Cir.2010).

The district court employed Michigan law to guide its res judicata analysis, but it was not required by statute to do so. True enough, the Full Faith and Credit Act requires federal courts to give state court “judicial proceedings” the same preclusive effect those proceedings would receive in courts of the same state. 28 U.S.C. § 1738; Kremer v. Chem. Constr. Corp., 456 U.S. 461, 466, 102 S.Ct. 1883, 72 L.Ed.2d 262 (1982). But “[ajrbitration is not a ‘judicial proceeding’ and, therefore, § 1738 does not apply to arbitration awards.” McDonald v. City of W. Branch, Mich.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
765 F.3d 625, 2014 FED App. 0213P, 2014 U.S. App. LEXIS 16607, 2014 WL 4237159, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wj-oneil-co-v-shepley-bulfinch-richardson-abbott-inc-ca6-2014.