David Kircher v. City of Ypsilanti

Court of Appeals for the Sixth Circuit·Decided April 13, 2020·No. 18-1589·Unpublished

Opinion

NOT RECOMMENDED FOR PUBLICATION File Name: 20a0206n.06

Case No. 18-1589

UNITED STATES COURT OF APPEALS FOR THE SIXTH CIRCUIT

FILED

Apr 13, 2020

DAVID KIRCHER, ) DEBORAH S. HUNT, Clerk )

Plaintiff-Appellant, )

) ON APPEAL FROM THE UNITED v. ) STATES DISTRICT COURT FOR ) THE EASTERN DISTRICT OF CITY OF YPSILANTI, et al., ) MICHIGAN )

Defendants-Appellees. ) OPINION )

BEFORE: SUTTON, NALBANDIAN, and READLER, Circuit Judges NALBANDIAN, Circuit Judge. This litigation between David Kircher and Defendants began in Michigan state court in the late 1980s as nuisance-abatement suits over three properties Kircher owned. During the litigation, Kircher lost all three properties. Over a decade later, Kircher hopes to continue the litigation in federal court and receive compensation for his losses. He asks this court to give him that chance. But life rarely gives do-overs. And this litigation is no different. We find the Michigan state courts’ decisions preclude Kircher from raising the federal claims he wants to now litigate in federal court. So Kircher’s claims fail. We AFFIRM the district court’s decision granting Defendants’ motion to dismiss and rejecting Kircher’s second motion to amend.

I.

The claims Kircher wants to now raise in federal court relate to events spanning over a decade and across multiple appeals and remands in state court. To determine the merits of Kircher’s claims, we must now revisit the long and relevant procedural history.

A.

In the late 1980s, this epic began. See Ypsilanti Fire Marshal v. Kircher, 730 N.W.2d 481, 488 (Mich. Ct. App. 2007). At that time, Kircher owned three properties relevant to this appeal: (1) the Thompson Building, (2) the Cross Street Property, and (3) the Perrin Street Property. In Washtenaw County Circuit Court, the City of Ypsilanti sued Kircher over one—the Thompson Building. It sought to compel him to “make certain repairs and abate certain building-code and fire-code violations” there. Id. The parties then agreed to a court order (1996 order) appointing Ypsilanti’s building supervisor as receiver for that property to “bring[] the exterior of the building into compliance with the building ordinances and the Historic District ordinance.” Id. (quoting the 1996 order). The order also appointed Kircher as the contractor to perform the specified repairs at his own cost. If Kircher flouted the order, the receiver could replace Kircher and “take certain other actions” to complete the required work. Id. And if he failed to pay, the parties agreed that “a lien shall be imposed upon the property . . . collectible through property taxes.” Id. (quoting the 1996 order).

Kircher did not comply. So the circuit court entered a second and final order (1997 order).

It directed Kircher “to ‘begin work on the building to complete the repairs and improvements listed . . . within 120 days.’” Id. at 488–89 (quoting the 1997 order).

A couple of years later, Ypsilanti again sued Kircher to abate nuisances—this time on all three of the properties. (See R. 95, Ypsilanti’s Resp., PageID 2002 (May 14, 2001 Cross Street Property Complaint), 2028 (April 11, 2002 Thompson Building Complaint), 2044 (July 30, 2001 Perrin Street Property Complaint).) It started with three complaints, again in Washtenaw County Circuit Court.

In its Thompson Building complaint, Ypsilanti alleged that Kircher had ignored the 1996 and 1997 orders. Kircher, 730 N.W.2d at 489. It asked the court to issue an order to show cause and requested immediate appointment of a receiver for the property. Id. And Ypsilanti argued all three properties violated the state Fire Prevention Code and local building and fire codes. Id. at 489 (Thompson Building), 494 (Cross Street Property); see Ichesco v. Rankin, No. 272905, 2008 WL 681856, at *1 (Mich. Ct. App. Mar. 13, 2008) (Perrin Street Property).

B.

The circuit court held show cause hearings for the Thompson Building and for the Cross Street Property.1 For the Thompson Building hearing, the court heard testimony from the parties’ witnesses.

Ypsilanti’s fire marshal, Jon Ichesco, testified on the building’s problems and how he reached his findings. For example, Ichesco discussed “problems with [that property’s] roof, . . . and [problems with its] windowpanes falling into the street.” Ypsilanti Fire Marshal v. Kircher, Nos. 242697, 242857, 2004 WL 895888, at *1 (Mich. Ct. App. Apr. 27, 2004). Kircher “offered only his own testimony about what he thought was required and what he did to repair the building.” Id. He also asserted that he could not possibly have completed the repairs in the 1997 order “because he had not received the grant money” referenced in the 1996 order. Id.

1 Kircher points out that the court held no evidentiary hearing before issuing the Thompson Building Order.

But he does not dispute (and in fact concedes) that the circuit court held a show cause hearing after Ypsilanti brought its three nuisance-abatement suits and before the court issued the Thompson Building Order. Instead, he explains that show cause hearings are not equivalent to evidentiary hearings. And the state courts confirmed Defendants’ explanation that the court at least held show cause hearings before issuing its orders for both properties. Kircher, 2004 WL 895888, at *1–2.

The court disagreed with Kircher. It found Kircher disregarded the 1996 and the 1997 orders. It “specifically f[ou]nd [] the building [] in dangerous condition” and “a nuisance.” Id. (quoting the trial court). So it entered the Thompson Building Order. That order appointed Robert Barnes as receiver for the property and required Barnes to “make the building economically viable[,]” id. (quoting the Thompson Building Order); it essentially authorized him to “complete all necessary repairs[,]” Kircher, 730 N.W.2d at 489. It required Barnes to “maintain detailed records of the costs expended [to] repair[]” that property and directed Barnes to bill Kircher monthly for those costs. Id. It also directed Kircher to “pay all billed costs within 30 days,” and to pay Ypsilanti’s attorney fees “incurred in conjunction with the enforcement and supervision of th[at] order.” Id. And it gave the receiver “a lien on the property at the conclusion of the repairs for any costs Kircher had not paid.” Id.

The circuit court entered its first order for the Cross Street Property after the show cause hearing for that property. That order enumerated 224 repair items. Kircher, 2004 WL 895888, at *2. The court also issued “an order to vacate the premises which also required a certificate of occupancy before further occupation and inspections.” Id.

The parties later met for an evidentiary hearing where they spoke on the record. Id.

Ypsilanti asserted that the parties agreed Kircher would make repairs “subject to a determination of workmanship by Harry Hutchinson, head of the city’s building department.” Id. It explained that the parties were trying to resolve the issues but that the parties would litigate anything unresolved. Id. Kircher also spoke on the record and “did not object” to Ypsilanti’s testimony. Id.

“[B]ecause the parties entered a stipulated order[,]” the court did not hear further testimony.

(R. 95, Ypsilanti’s Resp., PageID 2005.) Instead, the court entered another order requiring Kircher

to make the repairs within ten days and permitting city officials to inspect the building twenty-one days after the order’s entry. Kircher, 2004 WL 895888, at *3. It agreed to give Hutchinson authority to approve the workmanship of Kircher’s repairs. Id. Parties then stipulated to the entry of one more order that required Kircher to make “several repairs . . . immediately to bring th[e] [Cross Street Property] into compliance.” Id. (internal quotation marks omitted) (quoting the additional order).

Free access — add to your briefcase to read the full text and ask questions with AI

David Kircher v. City of Ypsilanti, (6th Cir. 2020).

David Kircher v. City of Ypsilanti (David Kircher v. City of Ypsilanti) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Railroad Comm'n of Tex. v. Pullman Co.
312 U.S. 496 (Supreme Court, 1941)
Weinstein v. Bradford
423 U.S. 147 (Supreme Court, 1975)
Mathews v. Eldridge
424 U.S. 319 (Supreme Court, 1976)
County of Los Angeles v. Davis
440 U.S. 625 (Supreme Court, 1979)
Keystone Bituminous Coal Assn. v. DeBenedictis
480 U.S. 470 (Supreme Court, 1987)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Colvin v. Caruso
605 F.3d 282 (Sixth Circuit, 2010)
Lloyd v. Crawford, III v. Jack A. Roane
53 F.3d 750 (Sixth Circuit, 1995)
ICHESCO v. Kircher
759 N.W.2d 390 (Michigan Supreme Court, 2009)
ICHESCO v. Kircher
755 N.W.2d 178 (Michigan Supreme Court, 2008)
Wayne County v. Hathcock
684 N.W.2d 765 (Michigan Supreme Court, 2004)
Adair v. State
680 N.W.2d 386 (Michigan Supreme Court, 2004)
Delay v. Rosenthal Collins Group, LLC
585 F.3d 1003 (Sixth Circuit, 2009)
Buck v. Thomas M. Cooley Law School
597 F.3d 812 (Sixth Circuit, 2010)
Schwartz v. City of Flint
466 N.W.2d 357 (Michigan Court of Appeals, 1991)
United States v. Williams
544 F.3d 683 (Sixth Circuit, 2008)