Winthrop Resources Corporation, a Minnesota Corporation v. Eaton Hydraulics, Inc., Formerly Known as Vickers, Inc., a Delaware Corporation

361 F.3d 465, 2004 U.S. App. LEXIS 4620, 2004 WL 439405
CourtCourt of Appeals for the Eighth Circuit
DecidedMarch 11, 2004
Docket03-1790
StatusPublished
Cited by68 cases

This text of 361 F.3d 465 (Winthrop Resources Corporation, a Minnesota Corporation v. Eaton Hydraulics, Inc., Formerly Known as Vickers, Inc., a Delaware Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Winthrop Resources Corporation, a Minnesota Corporation v. Eaton Hydraulics, Inc., Formerly Known as Vickers, Inc., a Delaware Corporation, 361 F.3d 465, 2004 U.S. App. LEXIS 4620, 2004 WL 439405 (8th Cir. 2004).

Opinion

SMITH, Circuit Judge.

Eaton Hydraulics, Inc. (“Eaton”), 1 appeals the district court’s 2 summary judg *467 ment issued in favor of Winthrop Resources Corporation (“Winthrop”) in Winthrop’s breach-of-contract claim. The district court determined that Eaton breached the contract and owes $4,365,437.64 in damages, costs, disbursements, and attorney’s fees. We affirm.

I. Background

Winthrop leases computer systems and other technology equipment to corporate customers. After Winthrop’s customers select their equipment, Winthrop then purchases and leases the equipment to the customers. In June 1997, Eaton and Winthrop entered into a master lease agreement. 3 The agreement provided that Winthrop would purchase almost $9 million of computer equipment that Eaton selected. The parties also signed nine lease schedules (001R, 002R, A01, A02, A03, B01, B02, COI and C02) issued pursuant to the master lease agreement. 4 Each lease schedule identified particular pieces of equipment leased by Eaton, and each incorporated the terms of the master lease by reference. Each lease schedule listed the monthly amount Eaton agreed to pay for the use of Winthrop’s equipment. By executing the Lease, both Winthrop and Eaton expressly agreed that each provision was binding and enforceable. 5

Winthrop sued Eaton on April 13, 2001, alleging that Eaton breached the Lease. Specifically, Winthrop claimed that Eaton failed to meet numerous payment obligations, failed to properly maintain the equipment during possession, failed to properly package the equipment upon return, and impermissibly sold pieces of equipment in violation of the Lease terms. Eaton counterclaimed that Winthrop breached the implied covenant of good faith and fair dealing, committed fraud, breached the contract, and violated various provisions of Minnesota law.

Winthrop moved for summary judgment on its claims and moved to dismiss Eaton’s counterclaims. In its motion, Winthrop requested damages in the amount of $4,222,024.67, plus costs, disbursements, and attorney’s fees. Winthrop provided affidavits and supporting documents detailing Eaton’s various Lease breaches. Winthrop submitted its damage calculation pursuant to section 18 of the Lease setting forth past-due Lease charges, past-due taxes and late fees, and the greater of: (i) the accelerated rent remaining due, or (ii) the Casualty Loss Value (“CLV”) for each lease schedule. 6

In its counterclaim, Eaton asserted that: (i) Winthrop failed to give notice and op *468 portunity to cure the payment defaults; (ii) it had procured Manufacturer’s Maintenance Agreements (“MSMAs”) on the equipment and that Winthrop purchased the MSMAs; (iii) Winthrop breached first; (iv) the CLV was an unenforceable penalty; (v) the CLV did not apply to equipment on “terminated” lease schedules. Applying Minnesota law, the district court rejected Eaton’s arguments as insufficient to avoid liability and damages under the plain terms of the Lease.

On April 23, 2002, the district court granted Winthrop’s motion for summary judgment. The district court found that Eaton breached the Lease and that the CLV damages provision was enforceable. The district court noted that Eaton did not dispute that it had breached the Lease. The court also noted that Eaton did not dispute Winthrop’s damages calculation.

Winthrop subsequently filed a motion pursuant to Federal Rules of Civil Procedure 58 and 59(e) requesting clarification of the damages award in the summary judgment and dismissal order. The district court awarded judgment on April 23, 2002, in the amount of $4,365,437.64, which included Winthrop’s costs and attorney’s fees, less mitigation, because Eaton failed to challenge Winthrop’s calculation of damages.

On May 8, 2002, Eaton moved pursuant to Federal Rule of Civil Procedure 59(e) to alter or amend the judgment. Eaton argued that the expert reports it submitted after the summary-judgment hearing demonstrated the unreasonableness of the CLV provision. Eaton also argued-for the first time-that: (i) Winthrop failed to prove that its claimed damages were reasonable; (ii) it could not maintain MSMAs on the equipment because MSMAs did not exist for this equipment; (iii) Eaton properly terminated lease schedules A02 and C01.

On December 10, 2002, the district court denied Eaton’s Rule 59(e) motion. The district court determined that Eaton failed to submit any newly-discovered evidence, failed to show reversible error, and failed to present any facts or law overlooked by the court. Following this decision, Winthrop moved for entry of judgment on damages, and on February 21, 2003, the district court entered an amended judgment including damages in the amount of $4,365,437.64.

Eaton timely filed a notice of appeal from all of the district court’s orders. However, in this appeal, Eaton challenges only the grant of summary judgment and the order clarifying the damages award.

II. Standard of Review

Rule 56(c) provides that a motion for summary judgment shall be granted only if “there is no genuine issue as to any material fact and ... the moving party is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(c). We review de novo a grant of summary judgment, applying the same standard as the district court. Evergreen Inv., LLC v. FCL Graphics, Inc., 334 F.3d 750, 753 (8th Cir.2003). When considering a motion for summary judgment, we must view the evidence and the inferences that may be reasonably drawn from the evidence in the light most favorable to the non-moving party. Enter. Bank v. Magna Bank, 92 F.3d 743, 747 (8th Cir.1996). The burden of demonstrating that there are no genuine issues of material fact rests on the moving party. Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986); Medtronic, Inc. v. U.S. Xpress, Inc., 341 F.3d 798, 800 (8th Cir.2003). If the moving party has carried its burden, the non-moving party must demonstrate the existence of specific facts in the record that create a genuine issue for trial. Anderson *469 v. Liberty Lobby, Inc., 477 U.S. 242, 256, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986); Krenik v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
361 F.3d 465, 2004 U.S. App. LEXIS 4620, 2004 WL 439405, Counsel Stack Legal Research, https://law.counselstack.com/opinion/winthrop-resources-corporation-a-minnesota-corporation-v-eaton-ca8-2004.