Williams v. Kerns

265 S.E.2d 605, 153 Ga. App. 259, 1980 Ga. App. LEXIS 1766
CourtCourt of Appeals of Georgia
DecidedFebruary 1, 1980
Docket58496
StatusPublished
Cited by22 cases

This text of 265 S.E.2d 605 (Williams v. Kerns) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams v. Kerns, 265 S.E.2d 605, 153 Ga. App. 259, 1980 Ga. App. LEXIS 1766 (Ga. Ct. App. 1980).

Opinion

Carley, Judge.

Appellant entered into a contract with a general contractor for the renovation of his residence. Subsequently, with appellant’s consent, the general contractor assigned his contract to appellee. Before the work under the contract was finished, appellant dismissed appellee from the job. Appellee then brought *260 suit against appellant, alleging breach of contract, malicious interference with contractual relations, and conversion, and seeking recovery under the theory of quantum meruit. Appellee also made a claim for attorney fees. In this appeal from a judgment based on a jury verdict for appellee, appellant contends that the trial court erred in its charge to the jury on the measure of damages to be applied to the breach of contract claim and in denying appellant’s motions for directed verdict, new trial and judgment notwithstanding the verdict. Appellant’s argument regarding the denial of his motions is based on a claim that there was no evidence to which the jury could apply a measure of damages with any degree of certainty.

1. In recent years, there has been some apparent confusion regarding the measure of damages to be applied when an owner has breached a construction contract. The word "apparent” is used because careful analysis reveals that the confusion is illusory: The basic measure of damages in this context has remained the same for more than 100 years.

In 1871, the Supreme Court, in Wallace v. Tumlin & Stegall, 42 Ga. 462, 471, held that "the measure of the damages for such breach will be computed by ascertaining the profits of the enterprise, after deducting the legitimate cost of its execution.”

This court, some 38 years later, explained the method to be used in ascertaining the "profits of the enterprise”: "Where one employs another to furnish the labor and material and to do the work necessary to the improvement of real estate, but renounces the contract prior to the time when the contractor has incurred any expense toward the performance of it, the recovery for the breach of the contract is limited to the difference between the contract price and what it would have cost the contractor in labor and materials to have performed it. But if the contract is not broken until after the contractor has gone to expense toward its performance, the net loss incurred by him on account of the amount so expended should be added to the difference between the contract price and what it would have cost him to perform the contract.” Campbell & Co. v. Mion Bros., 6 Ga. App. 134 *261 (3) (64 SE 571) (1909). It may be seen that the net result of these calculations is that the contractor is awarded the benefits of his bargain, the profit he would have realized had he been permitted to perform the contract completely-

The measure of damages expressed in Campbell & Co. has been applied since it was announced, with only minor differences in wording and adjustments to the particular circumstances of cases. However, one of those minor changes of wording, and what we believe to have been a misinterpretation of that change, resulted in confusion and the eventual overruling of three decisions of this court.

In Herrman v. Conway, 83 Ga. App. 888, 891 (2) (65 SE2d 41) (1951), this court approved a statement of the measure of damages which, with the figures removed, read as follows: ". . . the difference between the contract price . . . and the cost to complete the work under the contract. . . plus the sum . . . expended for material and labor up to the time of the alleged breach.” (Emphasis supplied.) Robertson v. Gore, 115 Ga. App. 537, 538 (3) (154 SE2d 748) (1967), adopted the language used in Herrman: "The measure of damages for a contract not completed because of the fault of the opposite party is the difference between the contract price and the cost to complete the work plus sums expended by the contractor up to the time of the alleged breach.” That statement was quoted in Redman Development Corp. v. West, 127 Ga. App. 265, 266 (193 SE2d 213) (1972). It is from that point that the apparent confusion began. It is seen that, on their faces, these three decisions merely state the measure of damages as it had always been — the contractor’s "profit” (contract price less the cost to the contractor of full performance under the contract) plus his "net loss” (sums expended up to the time of the alleged breach). The only difference between these three cases and Campbell being that in the former, it was stated that "profit” is calculated by subtracting "the cost to complete the work under the contract” from the contract price and in the latter it was held that the "cost to perform the contract” must be subtracted from the contract price to obtain the "profit” figure.

*262 However, in the contracts article of Mercer Law Review’s annual survey of Georgia law of 1974, Redman, Robertson and Herrman were criticized as stating an erroneous measure of damages:

"It is rather unusual that a case stating a basic rule of damages needs description in a survey article. In Redman Development Corp. v. West, a construction contract was breached by the owner of the real estate, who ordered the contractor off the job. A judgment in favor of the contractor was reversed because the amount did not appear to be justified by the figures available in the record. The case is remarkable for a statement of the appropriate measure of damages in such a case. The court of appeals’ decision quoted:

" 'The measure of damages for a contract not completed because of the fault of the opposite party is the difference between the contract price and the cost to complete the work plus sums expended by the contractor up to the time of the alleged breach
"The flagrant error of the italicized portion of this 'rule,’ if not self-evident, can best be seen in the case of its origin. In Herrman v. Conway, when a construction contract was wrongfully terminated by the owner, the court accepted as a proper measure of damages the following:
"'[T]he difference between the contract price of $9,280.59 and the cost to complete the work under the contract of $6,527.79, which cost he itemized, plus the sum of $421.02 expended for material and labor up to the time of the alleged breach, which final figure is $3,173.82 . . .’
"Of course, reversing the figures, if plaintiff had already expended the $6,527.79, and $421.02 was the cost to complete, this measure of damages would give a patently absurd judgment of $15,387.36. [Calculated as follows: Contract price of $9,280.59 less cost to 'complete the work’ of $421.02, equaling $8,859.57, plus sums expended by the contractor of $6,527.79, equaling $15,387.36.]
"The correct rule of damages in this situation is that the contractor should receive the unpaid contract price less what he saves as a result of the breach — the cost of completing the contract. It is occasionally stated that the *263

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Champion Windows of Chattanooga, LLC v. Edwards
756 S.E.2d 314 (Court of Appeals of Georgia, 2014)
Al and Zack Brown, Inc. v. Bullock
518 S.E.2d 458 (Court of Appeals of Georgia, 1999)
Dill v. Chastain
507 S.E.2d 872 (Court of Appeals of Georgia, 1998)
Imaging Systems International, Inc. v. Magnetic Resonance Plus, Inc.
490 S.E.2d 124 (Court of Appeals of Georgia, 1997)
American Aluminum Products Co. v. Binswanger Glass Co.
391 S.E.2d 688 (Court of Appeals of Georgia, 1990)
Energy Contractors, Inc. v. Georgia Metal System & Engineering, Inc.
367 S.E.2d 324 (Court of Appeals of Georgia, 1988)
Ray v. Strawsma
359 S.E.2d 376 (Court of Appeals of Georgia, 1987)
Rome Housing Authority v. Allied Building Materials, Inc.
355 S.E.2d 747 (Court of Appeals of Georgia, 1987)
Abernethy v. Cates
356 S.E.2d 62 (Court of Appeals of Georgia, 1987)
Franklin v. Demico, Inc.
347 S.E.2d 718 (Court of Appeals of Georgia, 1986)
Marathon Oil Co. v. Hollis
305 S.E.2d 864 (Court of Appeals of Georgia, 1983)
Kent v. Hunt & Associates, Inc.
299 S.E.2d 123 (Court of Appeals of Georgia, 1983)
McDaniel v. Green
275 S.E.2d 124 (Court of Appeals of Georgia, 1980)
Classic Restorations, Inc. v. Bean
272 S.E.2d 557 (Court of Appeals of Georgia, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
265 S.E.2d 605, 153 Ga. App. 259, 1980 Ga. App. LEXIS 1766, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-v-kerns-gactapp-1980.