Marathon Oil Co. v. Hollis

305 S.E.2d 864, 167 Ga. App. 48, 1983 Ga. App. LEXIS 2388
CourtCourt of Appeals of Georgia
DecidedJune 21, 1983
Docket65454
StatusPublished
Cited by35 cases

This text of 305 S.E.2d 864 (Marathon Oil Co. v. Hollis) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marathon Oil Co. v. Hollis, 305 S.E.2d 864, 167 Ga. App. 48, 1983 Ga. App. LEXIS 2388 (Ga. Ct. App. 1983).

Opinion

Shulman, Chief Judge.

This complex action was initiated by appellee Hollis & Hollis Construction Company (“Hollis”) and its principals against appellee Waldron’s Petroleum Tank Services, Inc. (“Waldron’s”), Gary Waldron, and appellant Marathon Oil Company (“Marathon”) to recover money allegedly due Hollis pursuant to a subcontract with Waldron’s for concrete work on a construction project at the Marathon terminal in Macon. Hollis sought to recover the money allegedly due from both Waldron’s and Marathon and also sought a judgment lien on Marathon’s property. Marathon answered and cross-claimed against Waldron’s, seeking to recover damages allegedly resulting from Waldron’s breach of its construction contract for the mechanical work on the project at the Macon terminal. Waldron’s in turn answered and cross-claimed against Marathon, seeking to recover damages allegedly accruing from Marathon’s wrongful termination of Waldron’s and Marathon’s failure to pay sums claimed due pursuant to the construction contract. The case proceeded to trial before the judge sitting without a jury. After hearing several days of testimony and numerous exhibits, most of which concerned the defendants’ cross-claims, the trial court entered judgment in favor of Hollis in the amount of $37,639.24 and granted Hollis a lien on Marathon’s property in the amount of $33,285.90. The court also found that the termination of Waldron’s by Marathon “was unauthorized under all the facts and circumstances of this case,” and awarded Waldron’s $69,556.87. The trial court also made several other findings not relevant on appeal. From the judgments in favor of Hollis and Waldron’s against it, Marathon has appealed and enumerated five grounds of alleged error. These enumerations will be addressed in logical rather than numerical sequence.

1. In its second enumeration of error, Marathon contends that the trial court erred in finding that the termination of Waldron’s was unauthorized when the evidence demanded a contrary finding. Thus, Marathon contends, the trial court should not have entered judgment in favor of Waldron’s, but should have permitted Marathon to recover its reasonable costs for completion of the contract work.

Despite Marathon’s persuasive argument to the contrary, we *49 cannot conclude that the trial court’s finding with respect to the termination was without evidence to support it. The written contract contained numerous specifications relating to the quality of work as well as a schedule for completion of the project. The original schedule called for a completion date of November 19,1979. All parties agree that the project was not near completion on that date. However, the schedule was completely revised on several separate occasions, and Waldron’s was working pursuant to the latest revised schedule at the time of the termination. There was considerable testimony about faulty workmanship and lack of supervision, as well as delays in completing the work according to the original schedule and the reasons therefor. A review of the transcript reveals that counsel for all parties appear to have thoroughly adduced the facts relevant to their respective claims.

A. We agree with Marathon in its contention that Waldron’s was under a duty to perform the work under the contract according to specifications and “skillfully, carefully, diligently, and in a workmanlike manner.” Sam Finley, Inc. v. Barnes, 156 Ga. App. 802, 803 (275 SE2d 380). However, despite considerable evidence to the contrary, the trial court had before it evidence sufficient to authorize the conclusion that Waldron’s did perform the majority of the work properly pursuant to the contract and that it stood ready to correct any defects.

B. We also agree with Marathon’s contention that it had a right to performance of the work pursuant to the contract schedule. However, “[t]he terms of a written contract may be modified or changed by a subsequent parol agreement between the parties, where such agreement is founded on a sufficient consideration.” Ryder Truck Lines v. Scott, 129 Ga. App. 871 (3) (201 SE2d 672). “Even if the contract provides it may not be changed except by writing, parties may subsequently by mutual consent enter into a new agreement at variance with the other. [Cit.]” Wood v. Yancey Bros. Co., 135 Ga. App. 720, 721 (218 SE2d 698). The modified agreement “need not be expressed in words, in writing or signed, but the parties must manifest their intent to modify the original contract.” Ryder Truck Lines, supra, Division 4. “[W]hether there has been such a mutual and intended departure so as to make practically a new agreement is generally a question for [the fact finder] to determine.” Continental Cas. Co. v. Union Camp Corp., 230 Ga. 8, 11 (195 SE2d 417). There was ample evidence presented at trial from which the court could have concluded that due to unanticipated construction and design problems, unanticipated interruption of Waldron’s work at the terminal, or problems involving another contractor, all of which may have been attributable to Marathon, Waldron’s was unable to *50 complete its work according to the original schedule, and the parties entered into several revised agreements with revised scheduling and completion dates.

C. Marathon argues that Waldron’s should not be permitted a recovery, irrespective of any contract modifications, because Waldron’s failed to perform its original contract obligations. “[A]n offer or an agreement to extend the time conditioned upon the defendant performing is not binding on the plaintiff where the defendant in fact fails to perform. Each alleged agreement for extension of time ... is conditioned upon the defendant (a) meeting the new deadline, and (b) satisfactorily completing the original contract.” Berston v. Futo, 97 Ga. App. 5, 9 (102 SE2d 87). We agree with Marathon’s contention that any extension of time in this case anticipated performance of Waldron’s contract obligations. Again, however, there was evidence from which the trial judge could have concluded that Waldron’s was performing its contract obligations according to the latest schedule at the time of termination and would have completed the contract pursuant to the new schedule. Consequently, the evidence supports the trial court’s finding that the termination was improper, thus entitling Waldron’s to recover from Marathon any damages sustained (Stowers v. Hall, 159 Ga. App. 501 (2) (283 SE2d 714)), and preventing recovery by Marathon (Allied Enterprises v. Brooks, 93 Ga. App. 832, 834 (93 SE2d 392)).

D. Recovery by Waldron’s would not be prevented by its failure to request any extension of the completion date in writing, as required by the contract. As with the completion date itself, there was ample evidence from which the trial court could have concluded that this contractual requirement was waived or modified by mutual agreement. Commercial Trust Co. v. Mathis, 100 Ga. App. 620, 622 (112 SE2d 291).

E. “The Court of Appeals is a court for the correction of errors of law only, and has no jurisdiction to hear evidence aliunde the record, or to decide disputed issues of fact.” Jones v. Smith, 83 Ga. App. 798, 800 (65 SE2d 188).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rudy Robles v. Patricia Yugueros
779 S.E.2d 139 (Court of Appeals of Georgia, 2015)
Lynx Real Estate, Inc. v. F. A. L. Investments, LLC
718 S.E.2d 552 (Court of Appeals of Georgia, 2011)
Securities & Exchange Commission v. Price
108 F. Supp. 3d 1342 (N.D. Georgia, 2010)
Insurance Industry Consultants, LLC v. Alford
669 S.E.2d 724 (Court of Appeals of Georgia, 2008)
Monterrey Mexican Restaurant of Wise, Inc. v. Leon
638 S.E.2d 879 (Court of Appeals of Georgia, 2006)
Wilkinson Homes, Inc. v. Stewart Title Guaranty Co.
610 S.E.2d 187 (Court of Appeals of Georgia, 2005)
Marchelletta v. Seay Construction Services, Inc.
593 S.E.2d 64 (Court of Appeals of Georgia, 2004)
Trust Associates v. Snead
559 S.E.2d 502 (Court of Appeals of Georgia, 2002)
Bush v. Northside Trucking, Inc.
556 S.E.2d 909 (Court of Appeals of Georgia, 2001)
Thompson v. Enterprise Leasing Co.
522 S.E.2d 670 (Court of Appeals of Georgia, 1999)
Savannah Airport Commission v. Higgerson-Buchanan, Inc.
519 S.E.2d 475 (Court of Appeals of Georgia, 1999)
Harkleroad v. Stringer
499 S.E.2d 379 (Court of Appeals of Georgia, 1998)
Allgood Electric Co. v. Martin K. Eby Construction Co.
959 F. Supp. 1573 (M.D. Georgia, 1997)
Jennings Enterprises, Inc. v. Carte
481 S.E.2d 541 (Court of Appeals of Georgia, 1997)
Apac-Georgia, Inc. v. Department of Transportation
472 S.E.2d 97 (Court of Appeals of Georgia, 1996)
Dalcor Management, Inc. v. Sewer Rooter, Inc.
423 S.E.2d 419 (Court of Appeals of Georgia, 1992)
Summit-Top Development, Inc. v. Williamson Construction, Inc.
416 S.E.2d 889 (Court of Appeals of Georgia, 1992)
Randall & Neder Lumber Co. v. Randall
414 S.E.2d 718 (Court of Appeals of Georgia, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
305 S.E.2d 864, 167 Ga. App. 48, 1983 Ga. App. LEXIS 2388, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marathon-oil-co-v-hollis-gactapp-1983.